Resolved
That the Minutes of the meeting held on 16 June 2016 were approved as a correct record and signed by the Chairman.
Cabinet approved this item on Thursday 21 July 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Minutes of the meeting held on 16 June 2016 were approved as a correct record and signed by the Chairman.
HEREFORDSHIRE COUNCIL MINUTES of the meeting of Cabinet held at Council Chamber, The Shire Hall, St Peter's Square, Hereford, HR1 2HX on Thursday 16 June 2016 at 2.00 pm
Present: Councillor PM Morgan (Deputy Leader in the Chair)
Councillors H Bramer, DG Harlow, JG Lester, PD Price and P Rone
Cabinet support Councillors NE Shaw and EJ Swinglehurst members in attendance Group leaders in Councillors JM Bartlett and RI Matthews attendance Scrutiny chairmen in Councillors PA Andrews and WLS Bowen attendance Other councillors in Councillors EPJ Harvey attendance:
Officers in attendance: Alistair Neill, Jo Davidson, Richard Gabb, Geoff Hughes, Mairead Lane, Josie Rushgrove, Martin Samuels and Claire Ward.
1. APOLOGIES FOR ABSENCE
Apologies were received from Councillor AW Johnson.
2. DECLARATIONS OF INTEREST
None.
3. MINUTES
RESOLVED: That the Minutes of the meeting held on 9 May 2016 be approved as a correct record and signed by the Chairman.
4. HEREFORD RELIEF ROAD (HEREFORD BYPASS)
The cabinet member, infrastructure, presented the report on the Hereford relief road (Hereford bypass).
He reported that the decision made on the 6th June at the planning committee to approve the route of the southern link road had not been called in by the Minister of State.
During his presentation he highlighted a number of areas, including that:
The relief road was a key infrastructure project that was necessary to drive the economic growth of Hereford and the region and had been identified as a priority within the LTP, the Core Strategy and the Marches Strategic Economic Plan. It had also been a key theme within the emerging economic masterplan for Herefordshire.
The Core Strategy had been adopted in October 2015 and committed the council (in policy SS3) to work with developers and stakeholders to ensure the timely development of strategic proposals and key infrastructure requirements. The preferred option for Hereford had been published for consultation in September 2010 and included a western bypass with a package of sustainable transport measures. The supporting analysis had concluded that whilst these measures improved the performance of the network, it was only in combination with a bypass that they provided the network capacity necessary to support growth. The western alignment had been preferred due to the likely significant impacts to the east on the River Lugg Site of Special Scientific Interest (SSSI), the River Wye Special Area of Conservation (SAC), and the Lugg Meadows SSSI.
A Hereford bypass would increase traffic capacity to allow the city to grow with more homes and jobs and enable full delivery of Herefordshire’s Core Strategy housing and employment allocations, including those at the Hereford Enterprise Zone and the Three Elms employment site.
In reply to questions from members, he went on to say that:
One of the substantial risks in timetable for the project had been overcome as the southern link road had been approved by the planning committee although it was still open to a possible judicial review. It was important that target dates should be met within the overall timetable.
Traffic monitoring was in place on all roads in and around the city in order to provide the necessary data to support the business case for the relief road. The council was in dialogue with Highways England and the government regarding the project, and it was important that it be pushed forward in order to ensure that these partners were confident that progress was being made.
The Leader of the Independent Group said that there were alternative routes, and that a road to the east would make more sense from the point of view of serving the Enterprise Zone.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTESMinutes | 149 KB | DownloadRead as text |
Follow Cabinet at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 24 Sep 2026 | MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 30 Jul 2026 | MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 25 Jun 2026 | MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 21 May 2026 | MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.