Resolved
That the report be noted
Audit and Governance Committee noted this item on Thursday 22 September 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted
Countywide
Purpose
To provide the audit and governance committee with the projected outturn for 2016/17 for the committee to consider the effectiveness of budgetary control.
Recommendation(s)
THAT the committee: (a) note the council is projecting an overspend for this financial year and the remedial action being taken; (b) confirms that appropriate and timely budgetary and control measures are in place; and
(c) identify any further control measures deemed necessary.
Alternative options 1 There are no alternative options.
Reasons for recommendations 2 The latest published forecast outturn for the year as reported to Cabinet on 21 July 2016 is an overspend of £1.5m. Remedial action is being taken to reduce this forecast position with the next report to Cabinet scheduled for 1 December.
Further information on the subject of this report is available from Josie Rushgrove, head of corporate finance on tel (01432) 261867 Key considerations 3 The projected full year outturn based on spend until the end of May 2016 is an over spend of £1.5m, this represents 1% of the budget. The 2016/17 savings are £10.9m; £9.4m (86%) of which are on track to be delivered during the current year. Action plans are being undertaken in all directorates to address the in-year pressures and to help mitigate the impacts of the external economic environment. It is not unusual at this period in the year for there to be a forecasted over spend and actions are being taken to manage this.
Projected Revenue Outturn 2016/17 (as at the end of May)
Directorate Net Budget Net budget May outturn May variance £000 £000 £000 Over / (Under)spend Adults and wellbeing 51,239 52,233 994 Children’s wellbeing 22,292 22,751 459 Economy, communities and corporate 47,557 47,625 68 Directorate total 121,088 122,609 1,521 Other budgets and reserves 26,891 26,891 0 Outturn 147,979 149,500 1,521
Adults and wellbeing (AWB)
4 The latest forecast predicts a £994k overspend of the budget at year end.
5 The forecast overspend within the adult social care client groups is £1.047m at year end. This is due to higher than budgeted expenditure on direct payments that are over and above the compensating reduction in domiciliary care spend that would normally be expected.
6 The client forecast assumes that any further demand pressures will be managed within the operational teams, by AWB panel and by senior management. The directorate leadership team are currently in the process of preparing a recovery plan document to identify required actions and additional savings initiatives in order to ensure a balanced outturn for 2016/17.
7 The first recovery plan meeting has now taken place and the initial focus will be on the following two areas:
a. The ‘single handed care project’ which aims to reduce the number of ‘double handed’ care packages with better use of equipment and technology. This is anticipated to reduce the over spend in 2016/17 by £150k.
b. Maximising the occupancy of all block purchased beds to reduce the current over spend by a further £300k.
Children’s wellbeing (CWB)
8 The forecast outturn for 2016/17 is an over spend of £459k, this is due the timing of savings implementation. The 2015/16 outturn was an over spend of £2.1m, Further information on the subject of this report is available from Josie Rushgrove, head of corporate finance on tel (01432) 261867 reductions in the number of agency staffing (60 to 26) and the reductions in the number of looked after children and child protection plans will ensure the budget is manageable in 2016/17, recognising there is pressure on delivering the £1.6m 2016/17 savings.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BI-ANNUAL FORECASTReport | 315 KB | DownloadRead as text |
Follow Audit and Governance Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | MinutesThat the minutes of the meeting held on 29 September 2026 be confirmed as a correct record and signed by the chairman. | Decided | Open |
| 3 Nov 2026 | Work programmeThat, subject to the updates made by the committee, the work programme be noted. | Noted | Open |
| 29 Sep 2026 | MinutesThat the minutes of the meeting held on 21 July 2026 be confirmed as a correct record and signed by the chairperson. | Decided | Open |
| 29 Sep 2026 | External Audit Findings ReportThat the report of the external auditor having been considered agreed that no issues raised in the report be added to... | Agreed | Open |
| 29 Sep 2026 | Final Annual Governance StatementThat the Annual Governance Statement for 2025/26 properly reflects the council’s internal control environment and the... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.