Resolved that: a) the revised joint agreement at appendix 1 setting out the role, functions and terms of reference for the joint executive committee overseeing the strategy and direction of West Mercia Energy (WME) joint purchasing operation be approved; and b) the assistant director communities be authorised to agree with the other constituent authorities any further amendments to the Joint Agreement required, following consultation with the cabinet member, prior to completion and to complete the necessary deeds of variation on behalf of the council.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Meeting: Cabinet Meeting date: 3 November 2016 Title of report: Revised governance arrangements for West Mercia Energy Report by: Cabinet member corporate strategy and finance
Classification
Open
Key decision This is not a key decision. Wards affected
County wide
Purpose To approve the revised, joint agreement following consultation with Shropshire Council, the Borough of Telford and Wrekin and Worcestershire County Council. Recommendations
THAT:
a) the revised joint agreement at appendix 1 setting out the role, functions and terms of reference for the joint executive committee overseeing the strategy and direction of West Mercia Energy (WME) joint purchasing operation be approved; and
b) the assistant director communities be authorised to agree with the other constituent authorities any further amendments to the Joint Agreement required, following consultation with the cabinet member, prior to completion and to complete the necessary deeds of variation on behalf of the council.
Alternative options 1 Cabinet could decide not to approve the revised governance documents but this
Further information on the subject of this report is available from Richard Wood, head of environment and waste services on Tel (01432) 383009 would carry the risk that decision–making was not conducted in accordance with constitutional and statutory requirements.
2 The joint purchasing operation could be established under different governance arrangements, such as a legal entity in its own right. Whilst the advantages and disadvantages of such an option are being explored and will be subject to a decision in the future, there remains a need to ensure that existing governance arrangements are robust and fit for purpose.
Reasons for recommendations 3 The WME joint committee has discussed the need for revising and updating the governance arrangements. Since February 2016 Shropshire Council legal services, on behalf of WME, have conducted a review of the joint agreement between the member authorities as well as internal documents for the joint committee such as the financial regulations, standing orders, and scheme of delegation. The joint agreement has been subject to consultation with the relevant officers and a joint agreed recommended approach.
Key considerations 4 WME offers energy procurement and management on behalf of its four partner councils (Herefordshire Council, Shropshire Council, Borough of Telford & Wrekin Council and Worcestershire County Council). The contracts cover electricity, natural gas, petroleum fuels and liquid petroleum gas. West Mercia Energy is overseen by a joint executive committee with representation from the four owning authorities.
5 WME comprises a small, specialist energy buying team which purchases gas and electricity on behalf of the councils and gives assurance on price by giving a yearly capped rate. Additional benefits include passing on in-year savings where possible, validation checking of meter readings to ensure the council is not overcharged and computerised access to all the individual energy bills.
6 WME is able to trade with other public bodies as defined by the Local Authorities (Goods and Services) Act 1970, and when a financial surplus is generated from those activities it is shared amongst the four owning authorities annually.
7 The attached joint agreement shows tracked changes to the agreement previously entered into. The changes seek to clarify the working governance arrangements.
8 The key governance changes proposed to the main agreement are;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies