It was resolved that: (a) Single Local Growth Funding of a minimum of the value shown in column 3 of Table 1 be allocated to the named Growth Deal 3 projects, set out in Table 1; and (b) Should additional funds for this purpose be forthcoming, funding of a maximum value of that shown in column 2 of Table 1 be allocated to the named projects, set out in Table 1.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Marches Enterprise Joint Committee Meeting date: 18 July 2017 Title of report: Growth Deal 3 - Funding Allocations
Classification
Open
Key Decision
This is a key decision because it is likely to be significant in terms of its effect on communities living or working in an area comprising one or more wards in the Marches local enterprise partnership (LEP) area; and Notice has been served in accordance with Part 3, Section 10 (General Exception) of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) Regulations 2012
Purpose
To agree Marches Growth Deal 3 Single Local Growth Funding allocations towards five projects, agreed with government, to support economic growth across the Marches.
Recommendation(s)
THAT: (a) Single Local Growth Funding of a minimum of the value shown in column 3 of Table 1 be allocated to the named Growth Deal 3 projects, set out in Table 1; and (b) Should additional funds for this purpose be forthcoming, funding of a maximum value of that shown in column 2 of Table 1 be allocated to the named Growth Deal 3 projects, set out in Table 1.
Summary Background
1. On 28 July 2016, the Marches LEP submitted proposals for the third competitive round of Growth Deal, comprising of a prioritised list of projects, detailing the financial package and outputs, for which round 3 funding was being sought and a set of supplementary paperwork covering the Marches approach to investment for growth, current programme delivery progress, governance and assurance around value for money.
Further information on the subject of this report is available from Gill Hamer, Director, The Marches LEP, [email removed] 2. Following submission, the LEP team provided further clarification to government on projects of interest. The government’s Cities and Local Growth Unit Director advised the LEP team on 21 February 2017 that the Growth Deal award to the Marches LEP is £21.91m.
3. The funding award was not sufficient to cover the five schemes of interest. The Marches LEP Board met on 7 March 2017 to discuss the funding award and how this might be allocated against a set of the submitted projects, to maximise the investment opportunity across the Marches and the economic growth potential for the business community it serves. The LEP agreed that the funding award of £21.91m would be allocated to all five schemes of interest, as follows:-
4. Since the announcement, project promoters have been at pains to restructure their financial profiles based upon a lower GD3 funding allocation. The LEP Team has sought evidence from project promoters to demonstrate the ability of the project to proceed on the basis of a lower allocation, without significant compromise on outputs and quality. Notwithstanding this, the LEP Team is continuing to pursue additional funding with a view to being able to allocate the originally planned combined funding allocation of £25.3m against the schemes.
5. Should additional funding become available, the LEP Board would wish to allocate funding to the value of the originally submitted funding request shown in the second column of Table 1.
Reasons for recommendations 6. To ensure that the selected Marches Growth Deal 3 funded projects are delivered in a manner that maximises project quality and optimises outputs and outcomes for economic growth for the Marches area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Marches Enterprise Joint Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.