Resolved
That the minutes of the meeting held on 4 July 2017 be confirmed as a correct record and signed by the chairman.
Audit and Governance Committee decided this item on Wednesday 20 September 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the meeting held on 4 July 2017 be confirmed as a correct record and signed by the chairman.
Minutes of the meeting of Audit and governance committee held at Committee Room 1, Shire Hall, St. Peter's Square, Hereford, HR1 2HX on Tuesday 4 July 2017 at 2.00 pm
Present: Councillor PD Newman OBE (Chairman) Councillor ACR Chappell (Vice-Chairman)
Councillors: BA Durkin, EPJ Harvey and J Stone
Officers: Andrew Lovegrove and Claire Ward, Kevin Lloyd and Zoe Thomas (Grant Thornton)
211. APOLOGIES FOR ABSENCE
Apologies for absence were received from Cllr RJ Phillips and Cllr LC Tawn.
212. NAMED SUBSTITUTES (IF ANY)
There were no substitutes.
213. DECLARATIONS OF INTEREST
There were no declarations of interest.
214. MINUTES
RESOLVED:
That the minutes of the meeting held on 10 May 2017 be confirmed as a correct record and signed by the chairman.
215. QUESTIONS FROM MEMBERS OF THE PUBLIC
There were no questions from members of the public.
216. QUESTIONS FROM COUNCILLORS
There were no questions from councillors.
217. EXTERNAL AUDIT PROGRESS UPDATE
Members were presented with an update on the external audit progress.
The external auditors had been on site since 12 June and anticipated completing the audit by the end of July.
It was noted that this audit had been a dry run as from next year the audit will need to have been finished by July. There had been some teething issues which were being addressed. The external auditors and the chief finance officer were meeting in order resolve any outstanding issues, which were mainly around the valuation of property.
The committee requested that acronyms were not used in reports unless there was an explanation of what they stood for.
RESOLVED
That the report be noted.
218. CORPORATE RISK REGISTER
The business intelligence officer presented the quarterly corporate risk register report.
Following a query from a member, it was confirmed that the risk register was based on a 5 x 5 matrix. It was noted that the colouring rating would need to be reviewed as the numerical risk did not always match the colour rating.
It was noted that the performance, risk, opportunity and management (“PROM”) policy was currently being reviewed and would be presented to cabinet in September for approval. The policy would form part of the corporate risk register report in November in order that the committee could receive an overview of the changes to enable them to understand any amendments to the framework.
Following a query from a member, it was confirmed that flood alleviation did appear on a service risk register. It was agreed that a copy of the risk as it appeared on the relevant risk register would be an appendix to the next corporate risk register report so that the committee could assure themselves that the risk was being appropriately monitored. It was also noted that a report on the local flood risk management strategy would be presented to the general scrutiny committee meeting on 11 July 2017.
The committee thanked officers for tracking changes on the risk register and requested consideration be given to illustrating when any changes last took place. The committee were interested in the rate of change in the corporate risk register.
Officers were also thanked for producing three detailed responses in connection with the three examples of fracking, water quality and flood alleviation which had previously been used to test the operation of risk management in the council.
The committee requested further clarification as to why the following risks had been removed from the risk register:
Fastershire – as a new contract had been approved for a new provider, the committee felt that there was a potential reputational risk of non-delivery. Brexit – the committee felt that it seemed counter intuition that this risk was removed when negotiations were just starting. It was noted that Herefordshire was the only county which qualified as rural in England and there were emerging significant effects on rural counties.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 225 KB | DownloadRead as text |
Follow Audit and Governance Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | MinutesThat the minutes of the meeting held on 29 September 2026 be confirmed as a correct record and signed by the chairman. | Decided | Open |
| 3 Nov 2026 | Work programmeThat, subject to the updates made by the committee, the work programme be noted. | Noted | Open |
| 29 Sep 2026 | MinutesThat the minutes of the meeting held on 21 July 2026 be confirmed as a correct record and signed by the chairperson. | Decided | Open |
| 29 Sep 2026 | External Audit Findings ReportThat the report of the external auditor having been considered agreed that no issues raised in the report be added to... | Agreed | Open |
| 29 Sep 2026 | Final Annual Governance StatementThat the Annual Governance Statement for 2025/26 properly reflects the council’s internal control environment and the... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.