Resolved
That the minutes of the meeting held on 21 March 2018 be confirmed as a correct record and signed by the chairman.
Audit and Governance Committee decided this item on Tuesday 8 May 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the meeting held on 21 March 2018 be confirmed as a correct record and signed by the chairman.
Minutes of the meeting of audit and governance committee held at Committee Room 1, Shire Hall, St. Peter's Square, Hereford, HR1 2HX on Wednesday 21 March 2018 at 2.00 pm
Present: Councillor PD Newman OBE (Chairman) Councillor ACR Chappell (Vice-Chairman)
Councillors: CR Butler, EPJ Harvey, RJ Phillips, AJW Powers and J Stone
Officers: Andrew Lovegrove, Alistair Neill, Laura Tyler, Stephen Vickers and Claire Ward
269. APOLOGIES FOR ABSENCE
There were no apologies for absence.
270. NAMED SUBSTITUTES (IF ANY)
None.
271. DECLARATIONS OF INTEREST
There were no declarations of interest.
272. MINUTES
RESOLVED:
THAT the minutes of the meeting held on 24 January 2018 be confirmed as a correct record and signed by the chairman.
273. QUESTIONS FROM MEMBERS OF THE PUBLIC
There were no questions from members of the public.
274. QUESTIONS FROM COUNCILLORS
There were no questions from councillors.
275. CAPITAL PROJECT MANAGEMENT AND CONTROL INTERNAL AUDIT PROGRESS UPDATE
It was noted that the committee would be meeting the chief finance officer in private session once the committee meeting had been formally closed.
The chief finance officer presented the report and highlighted the following:
All invoices now have to have a purchase order number otherwise they are sent back to the organisation. The internal control working group were thanked for their input which had been helpful. As from the new financial year, the system would require that all orders have a pre-loaded budget otherwise they will not proceed. The work on the Blueschool House recommendations had concluded but the internal control improvement board would continue as a continuous improvement board. During the discussion, the following points were raised:
Concern over the length of time that it would take to change the culture, especially as some of the recommendations were matters which should be a matter of course. The chief executive explained that it would take time to train approx. 1,200 employees on the new systems and for the culture to change. There were changes to how projects were monitored which included gateways which had to be met otherwise the project would not proceed. Blueschool House had exposed governance issues which should not have occurred. It was felt that the timescales needed to be tightened up and should be within 12 months. That if there was a culture that says you can work round any procedures, then this is separate to the roll out of training. A robust system would not be able to be by-passed as there would be checks and balances in place.
A member of the committee noted that there had been a recommendation at the committee meeting on 20 September 2017 that the corporate peer challenge have a focus on the economy, communities and corporate (ECC) directorate. The recent corporate peer challenge had not had a sole ECC focus and an assurance was sought that the recommendation had been discharged in its fullest sense. The chief executive explained that he had indicated at the committee meeting on 28 November 2017 that the peer challenge would not be solely focused on ECC. It was anticipated that the full final letter would be received within the next 2-3 weeks and the recommendations would be accepted and prioritised. However, the chief executive had contacted the lead chief executive reviewer and had provided a briefing on Blueschool House. As part of the information which had been sent to the peer challenge team, a position statement had been prepared which had also included Blueschool House. The chief executive agreed to circulate a copy of the position statement to the committee.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Public questions and answers to audit and governance committee on 8 May 2018Appendix 1 | 12 KB | Download |
PDF |
Member questions and answers to audit and governance committee on 8 May 2018Appendix 2 | 12 KB | Download |
PDF |
MinutesMinutes | 241 KB | DownloadRead as text |
Follow Audit and Governance Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | MinutesThat the minutes of the meeting held on 29 September 2026 be confirmed as a correct record and signed by the chairman. | Decided | Open |
| 3 Nov 2026 | Work programmeThat, subject to the updates made by the committee, the work programme be noted. | Noted | Open |
| 29 Sep 2026 | MinutesThat the minutes of the meeting held on 21 July 2026 be confirmed as a correct record and signed by the chairperson. | Decided | Open |
| 29 Sep 2026 | External Audit Findings ReportThat the report of the external auditor having been considered agreed that no issues raised in the report be added to... | Agreed | Open |
| 29 Sep 2026 | Final Annual Governance StatementThat the Annual Governance Statement for 2025/26 properly reflects the council’s internal control environment and the... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.