Peterchurch Primary School Rebuild

Decided Executive 1 paper

Cabinet decided this item on Thursday 13 December 2018. Below is the council's own wording, with the papers it was decided on.

Item29

Resolved

Resolved that: (a) the director for children and families be authorised to commission feasibility work and take all other steps necessary to inform a further decision on the replacement of Peterchurch primary school and associated on-site facilities on its current site, and determination of the most appropriate route to procurement, within a budget of not more than £180k.
Word for word from the decision Herefordshire published for this meeting. Source: councillors.herefordshire.gov.uk

Follow this further

Built from Herefordshire's papers

What the report saysPro

Report to Cabinet

Meeting: Cabinet

Meeting date: Thursday 13 December 2018

Title of report: Peterchurch Primary School Rebuild

Report by: Cabinet member children and families

Classification Open

Decision type Key

This is a key decision because it is likely to result in the council incurring expenditure which is, or the making of savings which are, significant having regard to the council’s budget for the service or function concerned. A threshold of £500,000 is regarded as significant.

This is a key decision because it is likely to be significant having regard to: the strategic nature of the decision; and / or whether the outcome will have an impact, for better or worse, on the amenity of the community or quality of service provided by the authority to a significant number of people living or working in the locality (two or more wards) affected.

Notice has been served in accordance with Part 3, Section 9 (Publicity in Connection with Key Decisions) of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012.

Wards affected Golden Valley North;

Purpose and summary To authorise the commissioning of a feasibility study by (or through) Herefordshire Council Property Services for the rebuild of Peterchurch Primary School on its existing site.

This will enable the commissioning of a feasibility study to Royal Institute of British Architect (RIBA) Stage 2 (concept design) by (or through) Herefordshire Council Property Services for the rebuild of Peterchurch Primary School on its existing site and to delegate authority to the Director of Education to commission further design work to RIBA Stages 3 (developed design) and 4 (technical design).

Further information on the subject of this report is available from Andrew Hind, Tel: 01432 260920, email: [email protected] Following provision being made in the capital programme to replace Peterchurch Primary School discussions have been held with interested parties including the primary school, Fairfield High School, local parish council and ward member to identify the most suitable site for the new building. There is now local consensus that it would be most appropriate to seek to rebuild on the current site. The consultation identified some highways and transportation improvements needed to improve traffic flows and access to the Fairfield High School site; these will form the subject of a separate decision.

This report is seeking approval to undertake detailed feasibility work for the rebuilding of Peterchurch Primary School on its existing site, including provision of permanent accommodation for the onsite charitable pre-school and refurbishment of the building housing the school swimming pool and progress all other activity necessary to inform a final decision.

Recommendation(s) That:

(a) the director for children and families be authorised to commission feasibility work and take all other steps necessary to inform a further decision on the replacement of Peterchurch primary school and associated on-site facilities on its current site, and determination of the most appropriate route to procurement, within a budget of not more than £180k.

Alternative options 1. The problems with the condition and suitability of Peterchurch Primary School have been recognised for some years. Three options were identified for consideration: 1. Do nothing; 2. Rebuild on another location adjacent to Fairfield High School; or 3. Rebuild on the current site.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Peterchurch Primary School RebuildReport 346 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 23 attended
JL
Councillor JG LesterChairperson, present
HB
Councillor H BramerMember, present
BD
Councillor BA DurkinMember, present
DH
Councillor DG HarlowMember, present
PP
Councillor PD PriceMember, present
PR
Councillor P RoneMember, present
NS
Councillor NE ShawVice-Chairperson, present
ES
Councillor EJ SwinglehurstMember, present
AJ
Councillor AW JohnsonCabinet support, present
PA
Councillor PA AndrewsScrutiny, present
WB
Councillor WLS BowenScrutiny, present
TJ
Councillor TM JamesGroup leader, present

All 23 on the meeting page

More from Herefordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. Approved Open
24 Sep 2026 MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. Approved Open
30 Jul 2026 MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. Approved Open
25 Jun 2026 MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. Approved Open
21 May 2026 MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies