174269 - BROOK FARM, MARDEN, HEREFORDSHIRE, HR1 3ET

Refused Planning 1 paper

Planning and Regulatory Committee refused this item on Wednesday 19 June 2019. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

The application was refused contrary to the case officer’s recommendation.
Word for word from the decision Herefordshire published for this meeting. Source: councillors.herefordshire.gov.uk

Follow this further

Built from Herefordshire's papers

What the report saysPro

Report to Planning and Regulatory Committee

MEETING: PLANNING AND REGULATORY COMMITTEE

DATE: 19 JUNE 2019 TITLE OF 174269 - PROPOSED MODIFICATION TO EXISTING REPORT: AGRICULTURAL BUILDING TO ACCOMMODATE A BIOMASS BOILER, INCLUDING FLUE AT BROOK FARM, MARDEN, HEREFORDSHIRE, HR1 3ET

For: [name removed] per [name removed], 20 Park Lane Business Centre, Park Lane, Basford, NG6 0DW https://www.herefordshire.gov.uk/info/200142/planning_services/planning_application_search/details?id=174269&search=174269 WEBSITE LINK: Reason Application submitted to Committee – Redirection

Date Received: 13 November 2017 Ward: Sutton Walls Grid Ref: 352142,248333 Expiry Date: 1 June 2018 Local Member: Councillor K S Guthrie

1. Site Description and Proposal

1.1Brook Farm is located in the countryside approximately 1km to the northern edge of the village of Marden six miles north of Hereford, and alongside the C1120 Road and Three Rivers Ride Recreational Route. The site is known principally for the growing, storage, packaging and distribution of soft fruit. The site extends to approximately 64 hectares, the majority of which is used for the agricultural processes. Buildings within the site include Brook Farm House (Grade II listed) and its adjacent stone barns. In addition there are the packing sheds associated with the agricultural business and the seasonal agricultural workers accommodation. There are a number of portacabins and temporary building within the site which accommodate the offices on site. Permission was granted in early 2018 (under application 163158/F) for a new headquarters and offices.

1.2The site currently features a number of different plant items which are used to provide heating for existing operations. This includes 2 x 200kW biomass boilers, 2 x natural gas fired boilers and a combined heat and power (CHP) unit. The CHP unit containerised and is moveable; whilst the two existing gas boilers are housed in a pre-existing general purpose farm building which also houses the asparagus grading lines.

1.3The CHP unit is operated all day, every day and supplies electricity to the Brook Farm site and heat to the polytunnels via the hot water storage tank. Previously this was done via diesel generators. The boilers currently provide all of the heat for the heated tunnels on site. Carbon dioxide from the burning of gas is also piped to the tunnels to promote plant growth. The two gas boilers each have a rated output of 6MW of heat. The boilers are currently operated much of the day during the winter months (November to April) and when needed during September and May.

Further information on the subject of this report is available from [name removed] on 01432 261961 PF2 1.4 This application seeks planning permission to modify an existing building and erect a new building to house a biomass boiler. The extract from the location plan, inserted below, details the siting of the proposed building in the red edge.

1.5The biomass boiler, which will have a rated output of 10 MW, will significantly reduce the running hours of the gas boilers, however the planning statement advises that the applicant wishes to retain the gas boilers for times of very cold weather when there will be a need to run both. The majority of the time however the intention is to run the proposed biomass boiler only. As such, the application has been considered with this in mind. For ease of reference, a plan detailing the siting of the existing CHP unit, biomass and gas boilers and proposed biomass boiler is inserted below.

Figure 2 – ADMS-5-Inputs from the Air Quality Assessment Ocober 2018

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
174269: BROOK FARM, MARDEN, HEREFORDSHIRE, HR1 3ETReport 1.4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 22 attended
GA
Councillor Graham AndrewsMember, apologies
PA
Councillor Paul AndrewsMember, present
PA
Councillor Polly AndrewsMember, present
CB
Councillor Christy BoldersonMember, present as substitute
TF
Councillor Toni FaganMember, present
EF
Councillor Elizabeth FoxtonMember, present
KG
Councillor Kema GuthrieMember, in attendance
JH
Councillor John HardwickChairperson, present
JH
Councillor John HarringtonMember, present as substitute
LH
Councillor Liz HarveyMember, in attendance
HI
Councillor Helen I'AnsonMember, in attendance
TJ
Councillor Terry JamesMember, present

All 22 on the meeting page

On this subject at Herefordshire

Search all
  1. 174269 - BROOK FARM, MARDEN, HEREFORDSHIRE, HR1 3ETThis decision
  2. 163158 - brook farm, marden, herefordshire, hr1 3etApproved
  3. 150431 - Land opposite Brook Farm, Marden, Herefordshire, HR4 9EARefused
  4. Dcnw2005/1056/f & dcnw2005/1057/l - conversion of redundant farm building to form six houses. marlbrook hall, at leinthall starkes, ludlow, herefordshire, sy8 2hr for: s r morgan & sons, burton & co, lydiatt place, brimfield, ludlow, shropshire, sy8 4npAgreed
  5. DCCW2005/0698/F - Brook Farm, Marden, Herefordshire, HR1 3ETDecided
  6. Dcne2004/1250/l & dcne2004/1249/f - conversion of redundant farm buildings into 6 residential dwellings and alterations to main farm house at brook farm, little marcle road, ledbury, hereford. (agenda item 8)Decided

More from Herefordshire Planning and Regulatory Committee

All decisions
MeetingDecisionOutcome
14 Oct 2026 260943 - land southeast of woonton farm, woonton, almeley, herefordApplication approved in accordance with the case officer’s recommendation and a change to the conditions. Approved Open
14 Oct 2026 253316/253317 - 123 the homend, ledbury, herefordshire, hr8 1bpApplication approved, contrary to the case officer’s recommendation. Approved Open
9 Sep 2026 251908/251909 - land at town well station road, credenhill, herefordshire, hr4 7dwApplication approved in accordance with the case officer’s recommendation. Approved Open
9 Sep 2026 261671 - town well, station road, credenhill, hereford, herefordshire, hr4 7dwApplication approved in accordance with the case officer’s recommendation. Approved Open
9 Sep 2026 260149 - land south east of greyhound close, longtown, hereford, herefordshireApplication approved in accordance with the case officer’s recommendation. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies