That (a) the £7.674m (Pothole and Challenge Fund 2020/21 grant allocation) be added to the capital programme as a new programme; (b) the £4.027m (Priority Flood Repair Works) be added to the capital programme as a new programme; (c) priority flood repair works totalling £4.027m, as set out in paragraph 27 of this report, are funded by extended prudential borrowing; and (d) in the event that new funds are made available by Government specifically to address the priority flood repair works, then those funds would be added to the Priority Flood Repair Works programme.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Title of report: In year changes to the capital programme budgets for priority flood works
Report by: Leader of the Council
Classification Open
Decision type Budget and policy framework
Wards affected (All Wards);
Purpose Following consideration at Cabinet on 23 July 2020, approve the allocation of funding for priority flood damage repairs and for works to enhance the resilience of the county’s infrastructure.
The Bellwin scheme will not fund all repair needs following flooding in February 2020. With no further funding having been specifically made available by Government for recovery from Storm Dennis, the significant gap between what the Bellwin scheme provides and the cost of all necessary repairs must be met from within the capital programme. This report sets out the Cabinet’s recommendations from their consideration of the funding options from across the capital programme and including the allocation of capital funding available following the announcement of Pothole and Challenge Fund allocations for 2020/21.
Recommendation(s) That:
(a) The £7.674m (Pothole and Challenge Fund 2020/21 grant allocation) be added to the capital programme as a new programme;
Further information on the subject of this report is available from Clive Hall, Tel: 01432 260786, email: [email protected] (b) The £4.027m (Priority Flood Repair Works) be added to the capital programme as a new programme;
(c) Priority flood repair works totalling £4.027m, as set out in paragraph 27 of this report, are funded by extended prudential borrowing; and
(d) In the event that new funds are made available by Government specifically to address the priority flood repair works, then those funds would be added to the Priority Flood Repair Works programme.
Alternative options 1. That priority flood repair works totalling £4.027m, as set out in paragraph 24 of this report, are funded through the use of either, the reallocation of existing capital programme budgets, the proposed new programme allocation of the Pothole and Challenge fund or combination of the aforementioned options or in part, additional borrowing as identified in the recommended option. This is not recommended by cabinet as it would impact upon the delivery of other projects in the capital programme.
2. Do Nothing, this is not recommended as the Council would be put at risk of failing to meet its statutory duty to maintain the highway network, property would be at risk of damage and persons at risk of injury as a consequence of further deterioration in the condition of the highway asset, particularly at the sites where the highway has had to be closed to through traffic as a consequence of storm damage.
3. Postpone this decision, this is not recommended as, not only would the Council be put at risk of failing to meet its duty to maintain the highway, and property and persons put at further risk, the funding received through the Pothole and Challenge Fund will be put at risk as the window for spend in the remainder of the 2020/21 financial year closes. Further, schemes underway to repair storm damage will have to be halted until their funding is determined, this will prolong the impact that severance is having on the community of Fownhope and the surrounding area.
Key considerations 4. Storm Dennis hit Herefordshire during the weekend of 15 and 16 February 2020, resulting in significant damage and flooding, from both runoff and river overspill with many of the rivers reaching their highest levels in 200 years. The council successfully mobilised all resources to respond to the event, with the clean-up and recovery work commencing as soon as flooding had subsided with resources focussed on making safe the worst hit areas.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Notices of motion under standing ordersRESOLVED – that: Statutory Council meetings to which the public have access are held during the normal working day. T...
Notices of motion under standing ordersRESOLVED – that: Council notes that: 1. Herefordshire has demonstrated its solidarity with the people of Ukraine sinc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.