It was agreed that the director of adults and communities would be invited to the next committee meeting when the corporate risk register was due to be discussed [March 2020]. · Completion dates were agreed with the relevant manager and SWAP would expect that there would progress to implement recommendations if the completion dates would not be met, especially in connection with priority 1 and 2 recommendations. · Savings targets are set by the council when agreeing the budget at the budget setting council meeting. There is monitoring throughout the year but the targets may be revisited. Any changes will be dealt with by cabinet or cabinet member. If there are significant changes, then these would be considered by Council. · A briefing for members on Verto was requested as it was noted councillors had not yet had a formal introduction to the system. It was agreed that this would be considered by the management board. RESOLVED that a) The head of corporate performance request that clarification is provided in connection with the internal audit for property maintenance for schools [page 64 of the agenda pack] and corporate risk register [CRR 50 on page 80 of the agenda pack] as there appears to be an inconsistency between the two sets of narratives. b) That the director of adults and wellbeing be invited to the next committee meeting when the corporate risk register is due to be presented. c) Management Board to consider an all members’ briefing session on Verto .
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Further information on the subject of this report is available from Paul Harris, Tel: 01432 383675, email: [email protected] 1. The committee could choose not to monitor the progress made on audit recommendations; however this would not be recommended as it is a function of the committee to monitor the effective development and operation of risk management and corporate governance in the council, and this report enables the committee to gain assurance that actions in response to recommendations are being suitably prioritised which reduces the risk to the council.
Key considerations 2. South West Audit Partnership (SWAP) provides the internal audit services for Herefordshire Council. SWAP is required to deliver an annual audit plan, which is scoped using a risk-based assessment of the council’s activities. Additional audits are added to the plans as necessary to address any emerging risks and issues identified during the year.
3. Upon completion of each audit review, a formal report is drafted for discussion with service managers. These reports include; the main conclusions of the review and the overarching opinion, individual findings and the potential associated risk exposure.
4. Management responses to each audit recommendation are obtained and recorded, identifying the actions required, the person responsible and the target date for the implementation that has been agreed.
5. Recommendations are each scored to indicate their severity. The scoring matrix is shown below:
Priority Findings that are fundamental to the integrity of the service’s Priority 1 business processes and require the immediate attention of the management Important findings that need to be resolved by management Priority 2 Finding that requires attention Priority 3
6. All staff responsible for audit recommendations are asked to review progress on the implementation of recommendations. Managers were asked to self-report on the action which had been taken in respect of the SWAP recommendation and the overarching status.
7. The last report to Audit & Governance Committee in June 2020 provided an update on the progress of audit recommendations. At this meeting, it was reported that there were thirteen recommendations that were overdue. Following recent updates ten of these are still to be completed, details for which are in appendix 1.
8. A further briefing note was provided to the committee following the meeting in June with further information on 2 recommendations in relation to ICT Access Controls. Many of these recommendations that remain outstanding have been impacted on by COVID-19, either having a direct result on the recommendation, or where teams responsible have been focussed on the response to the pandemic.
9. For the period May to September 2020, 12 audit recommendations were due for completion. The following table provides a summary of the status of these recommendations; their priority and allocation across directorates.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Final Annual Governance StatementThat the Annual Governance Statement for 2025/26 properly reflects the council’s internal control environment and the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.