It was agreed at this point that the meeting should continue beyond 3 hours in length in order to properly conclude this item. Group leaders were invited to present the comments and queries of their group. The need for more affordable homes was acknowledged and it was noted that: • If the government white paper on planning came to fruition it could make the situation worse by reducing provision of affordable housing on smaller sites; • Housing associations were not meeting all the local needs and it was important that the council retain control of the properties it developed; • The council should look to use local firms to work on the developments; • There was concern from one group leader that this proposal would create a debt burden for the council for the long term future and it was suggested that there were other ways to ensure that more affordable homes were provided, including working with other providers; • Cabinet members highlighted the extraordinarily low borrowing rates and felt that it was the ideal time to borrow to invest in the local economy and produce an asset for the council. The cabinet member housing, regulatory services and community safety noted the points raised and explained that the next report would bring forward details of the first sites. The decision now would agree the principle of development of council owned affordable housing. It was resolved that: a) Having considered the options set out in the paper to deliver up to 2,500 homes in the County over the next 10 years Cabinet agree that: i. the council own the affordable units ... view the full minutes text for item 26.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Title of report: Options for the Delivery of Council Owned Affordable Housing
Report by: Cabinet Member Housing, Regulatory Services, and Community Safety
Classification Open
Decision type Key
Wards affected (All Wards); County Wide
Purpose To approve the approach to the delivery housing model options available to the council to increase the supply of affordable housing in the County. Cabinet is also requested to approve Phase 2 of this strategic work to develop a pipeline of sites suitable for development as affordable housing to support discussions with key partners including Homes England.
The County Plan 2020-2024 sets out the council’s ambition to provide 1,000 affordable housing units in the county. The term affordable is taken in its widest sense – to provide a range of housing that is genuinely affordable to both rent and purchase given local earnings. The council has not owned its own housing stock since 2002 and a review has therefore been undertaken as to the most appropriate role for the council in delivering its ambition. The options and delivery proposals suggested recognise the structures already in place and available to the council.
Recommendation(s) That:
Further information on the subject of this report is available from Andrew Lovegrove, 01432 383519, email: [email protected] (a) Cabinet consider the options set out in this paper and select the one that best represents the way forward to deliver up to 2,500 homes in the County over the next 10 years. The options are:
i. the council own the affordable units initially under the General Fund and then establish a HRA,
ii. the council set up a Housing Company to deliver and own the units,
iii. the council set up a formal Joint Venture to deliver and own the units, or
iv. the council enter a formal partnership with existing Registered Provider(s) for them to deliver and own the units;
(b) approval to spend up to £72k on the development of the housing model chosen in option (a), by developing a full business case;
(c) ask Engie to develop recommendations for proceedable sites to be reviewed at Cabinet in December 2020;
(d) approval to spend up to £71k to develop recommendations for potential sites to be reviewed at Cabinet in January 2021 to agree how to progress affordable housing delivery in Herefordshire; and
(e) appoint an independent expert within a budget of £20k to advise on ensuring that housing built through this programme is compatible with our commitment to being a net zero carbon council by 2030.
Alternative options 1. The council could choose not to intervene in the provision of affordable housing in the County and allow the current arrangement of Registered Providers (RPs) and house builders to meet provision. However, the type and scale of development produced via RPs and private house builders in recent times has not kept pace with demand for affordable housing seen as one of the key components of the County’s wider economic ambitions.
Key considerations 2. Herefordshire has experienced a housing affordability gap for a number of years and is regularly identified as having one of the worst house price to earnings ratios in the West Midlands. Based upon median house price to income levels the ratio was 9.82 in September 2018 compared to highest (Malvern Hills) at 11.31 and lowest (Stoke on Trent) at 4.39.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.