It was resolved that: That: (a) Feasibility studies, within an approved budget of £475K, are commissioned to inform a programme of school capital investment work; (b) The Assistant Director for Education, Development and Skills be authorised to take all operational decisions necessary to deliver the required schedule of feasibility studies within the approved budget of £475k including fees; and (c) The Assistant Director for Education, Development and Skills be authorised to take all operational decisions necessary to vary the schedule of feasibility studies should any information received require them to do so.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Title of report: Schools Capital Investment Programme
Report by: Cabinet member commissioning, procurement and assets
Classification Open
Decision type Key
This is a key decision because it is likely to result in the council incurring expenditure which is, or the making of savings which are, significant having regard to the council’s budget for the service or function concerned. A threshold of £500,000 is regarded as significant.
This is a key decision because it is likely to be significant having regard to: the strategic nature of the decision; and / or whether the outcome will have an impact, for better or worse, on the amenity of the community or quality of service provided by the authority to a significant number of people living or working in the locality (two or more wards) affected.
Notice has been served in accordance with Part 3, Section 9 (Publicity in Connection with Key Decisions) of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012.
Wards affected (All Wards);
Purpose To approve the proposed expenditure of the preliminary works budget included in the capital programme.
The distribution of this funding is determined in accordance with the principles set out in the schools capital investment strategy and is based on regular condition surveys, suitability assessments and assessments of current and forecast demand for places.
Further information on the subject of this report is available from Karen Knight, Quentin Mee, Tel: 01432 383042, 01432 383043, email: [email protected], [email protected] Recommendation(s) That:
(a) Feasibility studies, within an approved budget of £475K, are commissioned to inform a programme of school capital investment work;
(b) The Assistant Director for Education, Development and Skills be authorised to take all operational decisions necessary to deliver the required schedule of feasibility studies within the approved budget of £475k including fees; and
(c) The Assistant Director for Education, Development and Skills be authorised to take all operational decisions necessary to vary the schedule of feasibility studies should any information received require them to do so.
Alternative options 1. A different set of investment works are prioritised. The works proposed have been determined based on the latest information in terms of the condition, suitability and sufficiency of the children & families establishments. The proposed works are addressing the known priorities and the council’s statutory duties.
Key considerations 2. The 2016 – 2021 Schools Capital Investment Strategy (SCIS) is informed by a set of widely consulted on principles and is applied to a detailed understanding of each of our schools and other establishments to provide clear options for improvement. In some cases the improvement options will be very straight forward and easy to apply, whilst for others there will be more challenging issues to consider. All schools, including academies, trust and faith schools, not just those run by the council, early years and post 16 provision are covered by the strategy. It’s important to ensure that the buildings being used provide high quality learning environments to support the council’s wider education and business ambitions.
3. The council receive various grants from the government. These grants may be annually received, for example, basic need funding (further detail at para 12 & 13) for the creation of additional pupil places, or may be one-off specific grants. As with all government funding, grants come with strict criteria for their use and application.
4. Amongst other areas, the capital investment strategy focuses on condition, suitability (fitness for purpose) and sufficiency (number of pupil places) of schools within the county.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.