REVISION OF CAPITAL PROGRAMME BUDGET FOR PRIORITY FLOOD WORKS

Approved Committee 1 paper

Council approved this item on Friday 8 October 2021. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

RESOLVED – that: a) Council approves in year adjustments to the capital programme set out in paragraph 11 below to allow realignment of capital spend to flood repair projects that require the allocation of budget within the programme budget of £4.027m as follows: Fownhope Landslip Budget reduced from £1.565m to £0.510m Fownhope Retaining Wall Collapse budget increased from £1m to £1.15m Unallocated budget of £905k from combined Fownhope budgets remains as contingency for remaining flood works; and b)The Cabinet member for infrastructure and transport is delegated authority (in consultation with the Section 151 officer) to realign the Whitney on Wye and/or the Various Damage site budgets as costs for these works are confirmed. (There was an adjournment at 1:07 p.m.; the meeting reconvened at 1:41 p.m.)
Word for word from the decision Herefordshire published for this meeting. Source: councillors.herefordshire.gov.uk

Follow this further

Built from Herefordshire's papers

What the report saysPro

Report to Council

Title of report: Revision of Capital Programme Budget for Priority Flood Works Meeting: Council

Meeting date: Friday, 8 October 2021

Report by: Cabinet Member Infrastructure and Transport

Classification Open

Decision type

Budget and policy framework

Wards affected (All Wards);

Purpose To consider the approval of in year adjustments to the capital programme to allow the realignment of capital spend to priority flood projects that require the reallocation of budget.

Recommendation(s) That: a) Council approves in year adjustments to the capital programme set out in paragraph 11 below to allow realignment of capital spend to flood repair projects that require the allocation of budget within the programme budget of £4.027m as follows: Fownhope Landslip Budget reduced from £1.565m to £0.510m Fownhope Retaining Wall Collapse budget increased from £1m to £1.15m

Unallocated budget of £905k from combined Fownhope budgets remains as contingency for remaining flood works b) The Cabinet member for infrastructure and transport is delegated authority (in consultation with the Section 151 officer) to realign the Whitney on Wye and/or the Various Damage site budgets as costs for these works are confirmed.

Further information on the subject of this report is available from Clive Hall, Tel: 01432 260786, email: [email protected] Alternative options 1. Not to approve the proposed amendments. This is not recommended as: a. This would mean that sums certified as due for works that were required to complete the Fownhope repairs could not be paid. The council would be in breach of contract and have acted contrary to the requirements of the Housing Grants, Construction and Regeneration Act 1996. b. It may not be possible to complete all remaining Priority Flood Repair Works. 2. Not to seek a delegation to make the in-year amendments to the capital budget. This is not recommended as the re-alignment of the capital budget is within the overall programme budget envelope of the £4.027m allocated by Council for the repair of the Priority Flood Repair Works and therefore does not adversely impact on the council’s financial position.

Key considerations 3. Storm Dennis hit Herefordshire during the weekend of 15 and 16 February 2020, resulting in significant damage and flooding, from both runoff and river overspill, with many of the rivers reaching their highest levels in 200 years. As part of a multi-agency response and recovery group the council successfully mobilised all resources to respond to the event. 4. The Bellwin scheme did not fund all repair needs following flooding in February 2020. With no further funding having been specifically made available by Government for recovery from Storm Dennis, the significant gap between what the Bellwin schemes provided and the cost of all necessary repairs, had to be met from within the capital programme. 5. A decision to progress priority flood repair works was taken under emergency powers at section 3.7.9 of the council’s constitution on 30 April 2020. 6. Subsequently on 23 July 2020 cabinet considered funding options and made recommendations to Council for funding of the high priority repair works. On 4 August 2020 at an extraordinary council meeting council confirmed that the priority flood repair works project be added to the capital programme. 7. The decision taken by the Council on 4 August 2020 was that £4.027m (Priority Flood Repair Works) be added to the capital programme as a new programme; and that they were to be funded by extended prudential borrowing. 8. The £4.027m was made up from the following estimates:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
REVISION OF CAPITAL PROGRAMME BUDGET FOR PRIORITY FLOOD WORKSReport 301 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

49 of 63 attended
GA
Councillor Graham AndrewsMember, present
PA
Councillor Paul AndrewsMember, present
PA
Councillor Polly AndrewsMember, present
JB
Councillor Jenny BartlettMember, present
CB
Councillor Chris BartrumMember, present
CB
Councillor Christy BoldersonMember, present
DB
Councillor Dave BoulterMember, apologies
SB
Councillor Sebastian BowenChairperson, present
TB
Councillor Tracy BowesMember, present
KC
Kate CharltonOfficer, expected
EC
Councillor Ellie ChownsMember, present
KC
Kate CoughtrieCouncil Staff, expected

All 63 on the meeting page

On this subject at Herefordshire

Search all
  1. REVISION OF CAPITAL PROGRAMME BUDGET FOR PRIORITY FLOOD WORKSThis decision
  2. Revision of Capital Programme Budget for Priority Flood WorksApproved

More from Herefordshire Council

All decisions
MeetingDecisionOutcome
9 Oct 2026 MINUTESThat the minutes of the meeting held on 24 July be confirmed as a correct record and signed by the Chairman. Decided Open
9 Oct 2026 Constitutional updatesRESOLVED – a. That Council notes the requirements to change the terms of the Planning and Regulatory Committee in res... Approved Open
9 Oct 2026 Notices of motion under standing ordersRESOLVED – that: Statutory Council meetings to which the public have access are held during the normal working day. T... Decided Open
24 Jul 2026 MINUTESThat the minutes of the meeting held on 22 May 2026 be confirmed as a correct record and signed by the Chairman. Decided Open
24 Jul 2026 Notices of motion under standing ordersRESOLVED – that: Council notes that: 1. Herefordshire has demonstrated its solidarity with the people of Ukraine sinc... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies