RESOLVED – that: a) Council approves in year adjustments to the capital programme set out in paragraph 11 below to allow realignment of capital spend to flood repair projects that require the allocation of budget within the programme budget of £4.027m as follows: Fownhope Landslip Budget reduced from £1.565m to £0.510m Fownhope Retaining Wall Collapse budget increased from £1m to £1.15m Unallocated budget of £905k from combined Fownhope budgets remains as contingency for remaining flood works; and b)The Cabinet member for infrastructure and transport is delegated authority (in consultation with the Section 151 officer) to realign the Whitney on Wye and/or the Various Damage site budgets as costs for these works are confirmed. (There was an adjournment at 1:07 p.m.; the meeting reconvened at 1:41 p.m.)
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Title of report: Revision of Capital Programme Budget for Priority Flood Works Meeting: Council
Meeting date: Friday, 8 October 2021
Report by: Cabinet Member Infrastructure and Transport
Classification Open
Decision type
Budget and policy framework
Wards affected (All Wards);
Purpose To consider the approval of in year adjustments to the capital programme to allow the realignment of capital spend to priority flood projects that require the reallocation of budget.
Recommendation(s) That: a) Council approves in year adjustments to the capital programme set out in paragraph 11 below to allow realignment of capital spend to flood repair projects that require the allocation of budget within the programme budget of £4.027m as follows: Fownhope Landslip Budget reduced from £1.565m to £0.510m Fownhope Retaining Wall Collapse budget increased from £1m to £1.15m
Unallocated budget of £905k from combined Fownhope budgets remains as contingency for remaining flood works b) The Cabinet member for infrastructure and transport is delegated authority (in consultation with the Section 151 officer) to realign the Whitney on Wye and/or the Various Damage site budgets as costs for these works are confirmed.
Further information on the subject of this report is available from Clive Hall, Tel: 01432 260786, email: [email protected] Alternative options 1. Not to approve the proposed amendments. This is not recommended as: a. This would mean that sums certified as due for works that were required to complete the Fownhope repairs could not be paid. The council would be in breach of contract and have acted contrary to the requirements of the Housing Grants, Construction and Regeneration Act 1996. b. It may not be possible to complete all remaining Priority Flood Repair Works. 2. Not to seek a delegation to make the in-year amendments to the capital budget. This is not recommended as the re-alignment of the capital budget is within the overall programme budget envelope of the £4.027m allocated by Council for the repair of the Priority Flood Repair Works and therefore does not adversely impact on the council’s financial position.
Key considerations 3. Storm Dennis hit Herefordshire during the weekend of 15 and 16 February 2020, resulting in significant damage and flooding, from both runoff and river overspill, with many of the rivers reaching their highest levels in 200 years. As part of a multi-agency response and recovery group the council successfully mobilised all resources to respond to the event. 4. The Bellwin scheme did not fund all repair needs following flooding in February 2020. With no further funding having been specifically made available by Government for recovery from Storm Dennis, the significant gap between what the Bellwin schemes provided and the cost of all necessary repairs, had to be met from within the capital programme. 5. A decision to progress priority flood repair works was taken under emergency powers at section 3.7.9 of the council’s constitution on 30 April 2020. 6. Subsequently on 23 July 2020 cabinet considered funding options and made recommendations to Council for funding of the high priority repair works. On 4 August 2020 at an extraordinary council meeting council confirmed that the priority flood repair works project be added to the capital programme. 7. The decision taken by the Council on 4 August 2020 was that £4.027m (Priority Flood Repair Works) be added to the capital programme as a new programme; and that they were to be funded by extended prudential borrowing. 8. The £4.027m was made up from the following estimates:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Notices of motion under standing ordersRESOLVED – that: Statutory Council meetings to which the public have access are held during the normal working day. T...
Notices of motion under standing ordersRESOLVED – that: Council notes that: 1. Herefordshire has demonstrated its solidarity with the people of Ukraine sinc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.