CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Herefordshire Council
Cabinet, Thursday 24 February 2022 at 2.30pm

Maylord Orchard Library and Learning Resource Centre (Detailed Design)

Approved Executive 2 papers

Cabinet approved this item on Thursday 24 February 2022. Below is the council's own wording, with the papers it was decided on.

Item92

Resolved

It was resolved that: a) The redevelopment of Maylord Orchards to create a new library and learning resource centre project is approved; b) Expenditure of up to £0.45m of the Maylord Orchard Library and Learning Resource Centre project capital programme allocation be approved to complete the detailed design stage of the project including seeking planning permission,; and c) The Corporate Director for Community and Wellbeing, following consultation with the Deputy Section 151 Officer and in consultation with the Cabinet member commissioning, procurement and assets, be authorised take all operational decisions necessary to complete the detailed design stage and seek planning approval within the £0.45m approved budget.
Word for word from the decision Herefordshire published for this meeting. Source: councillors.herefordshire.gov.uk

Follow this further

Built from Herefordshire's papers

What the report saysPro

Report to Cabinet

The Stronger Towns Fund – Maylord Orchard Library and Learning Resource Centre (Detailed Design) Meeting: Cabinet

Meeting date: Thursday 24 February 2022

Report by: Cabinet member commissioning, procurement and assets;

Classification Open

Decision type

Key

This is a key decision because it is likely to be significant having regard to: the strategic nature of the decision; and / or whether the outcome will have an impact, for better or worse, on the amenity of the community or quality of service provided by the authority to a significant number of people living or working in the locality (two or more wards) affected.

Notice has been served in accordance with Part 3, Section 9 (Publicity in Connection with Key Decisions) of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012.

Wards affected Central

Purpose

To approve up to £0.45m of the expenditure required to instruct the technical project manager and design team to complete the detailed design stage and works required to develop the full business case of the Maylord Orchard Library and Learning Resource Centre project including seeking planning and all related regulatory approvals.

Further information on the subject of this report is available from Roger Allonby, Johnathan Pritchard, Tel: 01432 260330, Tel: 01432 261885, email: [email protected], [email removed] Recommendation(s) That: a) The redevelopment of Maylord Orchards to create a new library and learning resource centre project is approved;

b) Expenditure of up to £0.45m of the Maylord Orchard Library and Learning Resource Centre project capital programme allocation be approved to complete the detailed design stage of the project including seeking planning permission,; and

c) The Corporate Director for Community and Wellbeing, following consultation with the Deputy Section 151 Officer and in consultation with the Cabinet member commissioning, procurement and assets, be authorised take all operational decisions necessary to complete the detailed design stage and seek planning approval within the £0.45m approved budget.

Alternative options 1. Do nothing – The council could choose to not approve the expenditure. However, this would mean we would be unable to seek the technical support such as architects, and building condition surveys required to seek the Stronger Towns grant. Failure to meet the required timescales or information requirements for the Stronger Towns funds would prevent the proposed project from progressing.

Key considerations 2. In 2020 government selected Hereford to be one of 101 towns/ cities from across England who were eligible to seek up to £25m of funding to support regeneration and enable economic growth. As required by the funding guidance, a Hereford Stronger Towns Partnership Board was formed including wide ranging representation across the public, private and community sectors. The Board oversaw the development of a Town Investment Plan through extensive local community engagement, and inviting people to put forward project proposals for submission to government in the Plan. The council submitted three project proposals to the Board, including the significant redevelopment of Hereford Museum and Art Gallery, the relocation of the current library and the creation of a Learning Resource Centre in the Maylord Orchard Centre, and a project focussed on greening the city improving active travel measures and providing digital visitor information points. The Board submitted the Town Investment Plan to government at the end of January 2021, and in June 2021 they announced a £22.4m allocation to Hereford, including in principle support for the three proposed council led projects. Each selected project now needs to develop a Full Business case by June 2022.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Feasibility_Study-Final IssueAppendix 1 8.8 MB Download
PDF
Maylord Orchard Library and Learning Resource Centre (Detailed Design)Report 266 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 26 attended
DH
Councillor David HitchinerChairperson, present
EC
Councillor Ellie ChownsMember, present
PC
Councillor Pauline CrockettMember, in attendance
GD
Councillor Gemma DaviesMember, apologies
JH
Councillor John HarringtonMember, in attendance
LH
Councillor Liz HarveyVice-Chairperson, present
DT
Councillor Diana ToynbeeMember, present
AT
Councillor Ange TylerMember, in attendance
JH
Councillor John HardwickCabinet support, present
ES
Councillor Elissa SwinglehurstScrutiny, present
JL
Councillor Jonathan LesterScrutiny, present
PH
Councillor Phillip HowellsScrutiny, present

All 26 on the meeting page

On this subject at Herefordshire

Search all
  1. Maylord Orchard Library and Learning Resource Centre (Detailed Design)This decision
  2. Maylord Orchards Interim Management PlanApproved

More from Herefordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. Approved Open
24 Sep 2026 MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. Approved Open
30 Jul 2026 MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. Approved Open
25 Jun 2026 MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. Approved Open
21 May 2026 MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies