It was resolved that: a) Cabinet approve the submission of the Herefordshire Addendum to government, in order to secure up to £1,705,669 of funding for the county; b) Authority to make any final technical amendments to the Addendum submission is delegated to the Corporate Director for Economy and Environment following consultation with the Cabinet Member for Economy and Environment; c) Should the Addendum be approved, the Council agrees to be the accountable body for the implementation of the RPF allocation and the resulting projects; and d) Authority is delegated to the Chief Executive Officer and the Section 151 Officer to formally submit the bids by the 30 November 2022 deadline.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Report by: Cabinet member environment and economy;
Classification Open
Decision type
Key
This is a key decision because it is likely to result in the council incurring expenditure which is, or the making of savings which are, significant having regard to the council’s budget for the service or function concerned. A threshold of £500,000 is regarded as significant.
This is a key decision because it is likely to be significant having regard to: the strategic nature of the decision; and / or whether the outcome will have an impact, for better or worse, on the amenity of the community or quality of service provided by the authority to a significant number of people living or working in the locality (two or more wards) affected.
Notice has been served in accordance with Part 3, Section 9 (Publicity in Connection with Key Decisions) of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012.
Wards affected (All Wards);
Purpose To seek cabinet approval to submit the Rural England Prosperity Fund (RPF) Addendum (Appendix A) to the UK Shared Prosperity Fund (UKSPF) Investment Plan to government on 30 November 2022. Government has allocated Herefordshire £1,705,669 of RPF, subject to the submission, and approval, of an Addendum.
Further information on the subject of this report is available from Nadine Kinsey, , email: [email removed] Recommendation(s) That: a) Cabinet approve the submission of the Herefordshire Rural England Prosperity Fund Addendum to government, in order to secure up to £1,705,669 of funding for the county;
b) Authority to make any final technical amendments to the Addendum submission is delegated to the Corporate Director for Economy and Environment following consultation with the Cabinet Member for Economy and Environment;
c) Should the Addendum be approved, the Council agrees to be the accountable body for the implementation of the RPF allocation and the resulting projects; and
d) Authority is delegated to the Chief Executive Officer and the Section 151 Officer to formally submit the bids by the 30 November 2022 deadline.
Alternative options 1. Do nothing – The council could choose not to submit the RPF Addendum to Government by 30 November 2022 deadline. However, this would result in the council being unable to access the £1.7m of capital funding allocated to the county, which is critical to supporting the rural economy of Herefordshire. This option is not recommended.
2. Alternative priorities in the Addendum – the council could choose to submit an alternative range of projects to those in the Addendum (as set out in Appendix 2), identifying different priorities for the county. As required by the national guidance, the Addendum has been developed against a clear evidence base, in consultation with rural partners and agreement with the Herefordshire Sustainable Growth Strategy Board (HSGSB). Alternative options may not meet Herefordshire’s rural needs and priorities and are unlikely to meet the Government’s requirements for approval. This option is not recommended.
3. The council could choose not to be the accountable body for the funding. There is no other suitable organisation in the county to fulfil this role, so it is likely that Herefordshire would not be able to access the funding. This option is not recommended.
Key considerations 4. On 5 September 2022, the Government launched the RPF, seen as a replacement for the previous ‘LEADER’ and national ‘Growth Programme’ grant schemes, delivered through the Rural Development Programme for England. Herefordshire has been allocated £1,705,669 capital funding to be spent between April 2023 and end of March 2025. The RPF national prospectus can be found here: Rural England Prosperity Fund: prospectus - GOV.UK (www.gov.uk)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.