Resolved that: a) The risks to the Council, as lender, were confirmed as being reasonable and appropriate having regard to the risks typically assumed by long term senior funders to waste projects in the United Kingdom and best banking practice; and b) Arrangements for the administration of the loan were reviewed and confirmed as satisfactory.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Title of report: Energy from waste loan update Meeting: Audit and Governance Committee
Meeting date: Tuesday 12 December 2023 Report by: Head of Strategic Finance (Deputy S151 Officer)
Classification Open
Decision type
This is not an executive decision
Wards affected (All Wards);
Purpose To update the committee on the current status of the energy from waste loan arrangement to enable the committee to fulfil its delegated functions.
Recommendation(s) That: a) The risks to the council, as joint lender, are confirmed as being reasonable and appropriate having regard to the risks typically assumed by long term senior funders to waste projects in the United Kingdom and best banking practice; and
b) Arrangements for the administration of the loan are reviewed and confirmed as satisfactory.
Alternative options 1. None; the loan arrangement was contractually agreed in May 2014, no breaches or areas of concern have taken place during the reporting period. This report provides an update on the arrangement to the Audit and Governance Committee in its role as the waste loan governance committee which entails reviewing risks to the lender and monitoring administration of the loan.
Further information on the subject of this report is available from Rachael Hart, Tel: 01432 261867, email: [email protected] Key considerations 2. In 1998, the council, in partnership with Worcestershire County Council, entered into a 25 year contract with Mercia Waste Management Limited (Mercia) for the provision of an integrated waste management system using the Private Finance Initiative. In 2014, a variation to the contract was signed, to build, finance and operate an energy from waste plant in Hartlebury.
3. The councils (the Lenders) provided a total of £163.5 million to Mercia (the Borrower) as a long term loan split across two facilities (Facility A £35.45 million and Facility B £128.05 million). Herefordshire Council provided 24.2% of the loan value £39.57 million.
4. Facility A was fully repaid in December 2022. The repayments for Facility B have been extended for 5 years until January 2029 in line with the extension to the Waste Management Services contract.
5. This report enables the committee to fulfil the functions delegated to it in relation to the governance of the waste loan arrangement; specifically to review the risks to the council as lender and to monitor administration of the loan.
6. Since the last report to the committee in October 2022, the loan arrangement has continued to be repaid in line with expectations and risks to the council are considered to be reasonable and appropriate.
Update to loan balance 7. During the last year, since the previous report to the committee, the following loan repayments have been made:
Interest £m Principal £m Total £m
Loan balance (principal) at 31.8 October 2022
December 2022 repayment 1.0 0.8 1.8
June 2023 repayment 1.0 1.3 2.3
Loan balance (principal) at 29.7 November 2023
Loan Agreement Ratios 8. The ratios are a financial covenant imposed by Lenders (in this case the council and Worcestershire County Council together as Lenders) as a monitoring mechanism to provide early warning of project distress and potential Borrower (in this case Mercia) default on their repayment obligations. The ratios provide a measure of the project’s historic and future performance in relation to its ability to service current and upcoming debt liabilities. The ratios are reported every 6 months in June and December. 9. The ratios reported at June 2023 were as follows:
Ratio Calculation Reason Compliance Actual value value at June 2023
The Historic Preceding 12 months To assess the ability 1.35 1.58 Annual Debt actual cashflows/ to service current Service debt obligation over Cover Ratio Loan principal and interest the preceding 12 repayments over the month period preceding 12 months
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Final Annual Governance StatementThat the Annual Governance Statement for 2025/26 properly reflects the council’s internal control environment and the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.