ADDITION OF CAPITAL BUDGET TO DELIVER IT CAPITAL PROGRAMME

Approved Committee 3 papers

Council approved this item on Friday 6 December 2024. Below is the council's own wording, with the papers it was decided on.

Item39

Resolved

RESOLVED – That Council: a) Approves the addition of £368,000 in this year’s capital programme, to deliver Wide Area Network (WAN) replacement project and Telephony Contact Centre project, funded from underspends in the capital programme.
Word for word from the decision Herefordshire published for this meeting. Source: councillors.herefordshire.gov.uk

Follow this further

Built from Herefordshire's papers

What the report saysPro

Report to Council

Addition of Capital Budget to deliver IT Capital Programme Meeting: Council

Meeting date: Friday 6 December 2024

Report by: Cabinet Member Finance and Corporate Services

Classification Open

Decision type

Budget and policy framework

Wards affected All Wards

Purpose To approve an amendment to the capital programme to utilise underspends to fund two new projects, at a total of £368,000 for delivery of IT projects within this financial year.

Recommendation(s) That Council a) Approves the addition of £368,000 in this year’s capital programme, to deliver Wide Area Network (WAN) replacement project and Telephony Contact Centre project, funded from underspends in the capital programme.

Alternative options 1. Do not request Telephony Contact Centre and Wide Area Network Replacement projects funding is reallocated within the 2024/25 capital programme, instead progress for approval in the 2025/26 capital programme. Not recommended. This would delay implementation and in turn delay opportunities to modernise our services and implement transformational change to customer services delivery. In addition, delaying implementation will incur additional licencing and supplier costs to the organisation for only a short period, which does not present a cost- effective solution.

Further information on the subject of this report is available from Amy Swift, , email: [email removed] Key considerations 2. The 2024/25 IT capital programme is on track to deliver a projected underspend in the region of £260,000. This underspend could be utilised to fund other IT projects. The underspend is as a result of projected costs within several IT projects being lower than anticipated.

3. Funding for the Wide Area Network Replacement project and Telephony Contact Centre project have been requested in the 2025/26 capital programme. This report requests to bring the funding for these projects into the 2024/25 capital programme.

4. The existing Wide Area Network contract ends in January 2025. Moving to a new solution will enable a revenue saving of £18,000 per annum in 2025/26, then £32,000 in subsequent years.

5. Renewing the contract with the current provider presents a risk of a significant price increase of 23% (approximately £39,500) as it is only a short-term renewal for one year. Inclusion within the 2024/25 capital programme means we can implement a new solution prior to the existing contract end date.

6. The existing contract for the Telephony Contact Centre ends on 31 March 2025. Bringing the decision forward will enable the council to transfer to a new provider and be live with like-for- like functionality before 31 March 2025. This will save £32,000 in licence fees and allow us to build on this foundational work to realise transformation opportunities to support customer service delivery. This will also negate the need to replace current hardware (which is nearing end of life) to run the current telephony platform

Community impact

7. The Council Plan 2024-2028 sets out the ambition to improve the way we use technology across our services by embracing new technologies, test ideas and develop a culture of innovation to improve services and deliver value for money. The council has committed to deliver against bold and ambitious plans and, by working with our local and national partners, we seek to continue to improve the quality of life for the county’s residents. Connected to this plan is a stated aim to further embrace digital technology to save costs and improve flexible working practice and service delivery, which directly supports our Transformation priority.

Environmental Impact 8. Herefordshire Council provides and purchases a wide range of services for the people of Herefordshire. Together with partner organisations in the private, public and voluntary sectors we share a strong commitment to improving our environmental sustainability, achieving carbon neutrality and to protect and enhance Herefordshire’s outstanding natural environment.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ADDITION OF CAPITAL BUDGET TO DELIVER IT CAPITAL PROGRAMMEReport 257 KB DownloadRead as text
PDF
Outline Strategic Business Case: WAN ReplacementAppendix 1 412 KB Download
PDF
Outline Strategic Business Case: Telephony Contact CentreAppendix 2 415 KB Download

At this meeting

Whole meeting

Who was there

52 of 59 attended
PA
Councillor Polly AndrewsMember, apologies
BB
Councillor Bruce BakerMember, present
JB
Councillor Jenny BartlettMember, present
CB
Councillor Chris BartrumMember, present
GB
Councillor Graham BiggsMember, present
DB
Councillor Dave BoulterMember, present
HB
Councillor Harry BramerMember, present
JC
Councillor Jacqui CarwardineMember, present
SC
Councillor Simeon ColeMember, present
RC
Ross CookOfficer, present
FC
Councillor Frank CornthwaiteMember, present
PC
Councillor Pauline CrockettMember, present

All 59 on the meeting page

On this subject at Herefordshire

Search all
  1. ADDITION OF CAPITAL BUDGET TO DELIVER IT CAPITAL PROGRAMMEThis decision
  2. Addition of capital budget to provide an acquisition fund for housing provisionApproved

More from Herefordshire Council

All decisions
MeetingDecisionOutcome
9 Oct 2026 MINUTESThat the minutes of the meeting held on 24 July be confirmed as a correct record and signed by the Chairman. Decided Open
9 Oct 2026 Constitutional updatesRESOLVED – a. That Council notes the requirements to change the terms of the Planning and Regulatory Committee in res... Approved Open
9 Oct 2026 Notices of motion under standing ordersRESOLVED – that: Statutory Council meetings to which the public have access are held during the normal working day. T... Decided Open
24 Jul 2026 MINUTESThat the minutes of the meeting held on 22 May 2026 be confirmed as a correct record and signed by the Chairman. Decided Open
24 Jul 2026 Notices of motion under standing ordersRESOLVED – that: Council notes that: 1. Herefordshire has demonstrated its solidarity with the people of Ukraine sinc... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies