Resolved
That the minutes of the meeting held on 25 March 2025 be confirmed as a correct record and signed by the chairman.
Audit and Governance Committee decided this item on Tuesday 10 June 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the meeting held on 25 March 2025 be confirmed as a correct record and signed by the chairman.
Minutes of the meeting of the Audit and Governance Committee held in Conference Room 2, Herefordshire Council Offices, Plough Lane, Hereford, HR4 0LE on Tuesday 25 March 2025 at 2.00 pm
Committee members Councillors: David Hitchiner (Chairperson), Mark Woodall (Vice- present in person Chairperson), Chris Bartrum, Frank Cornthwaite, Robert Highfield and and voting: Aubrey Oliver
Non-Voting K Diamond Committee Person: [Note: Committee members participating via remote attendance, i.e. through video conferencing facilities, may not vote on any decisions taken.]
Others in attendance:
J Bollen Principal Auditor, South West Audit Partnership G Hawkins Senior Manager, Grant Thornton R Sanders Director of Finance Cllr P Stoddart Cabinet Member Finance and Corporate Services J Preece Democratic Services Officer A Probert Head of Internal Audit, South West Audit Partnership C Smith Public Sector Audit Manager. Grant Thornton R Taggar Senior Auditor, South West Audit Partnership
43. APOLOGIES FOR ABSENCE
There were no apologies for absence.
44. NAMED SUBSTITUTES (IF ANY)
There were no named substitutes.
45. DECLARATIONS OF INTEREST
There were no declarations of interest.
46. MINUTES
RESOLVED:
That the minutes of the meeting held on 28 January 2025 be confirmed as a correct record and signed by the chairman.
47. QUESTIONS FROM MEMBERS OF THE PUBLIC
There were no questions received from members of the public.
48. QUESTIONS FROM COUNCILLORS
There were no questions received from councillors. 49. EXTERNAL AUDITOR'S DRAFT ANNUAL PLAN 2024/25
The Senior Manager (SM), Grant Thornton (GT) introduced the report of which the following principal points were noted: 1. The report outlined the significant risk areas and audit approach for both the financial statements and the value for money audit. 2. Significant risks for the audit approach were outlined on pages 36-39 of the report and were consistent with what the committee had seen in prior years. 3. GT’s approach to materiality was outlined on page 45 , It was noted that the percentage applied had increased since the prior year due to an update in their internal guidance. A maximum 2% had been applied as they did not consider there to be any specific risks in the control environment at Hereford. 4. Risks of significant weakness in Value For Money (VFM) arrangements were outlined on pages 55 and 56. 3 risks of significant weakness had been identified within the financial sustainability and improving economy, efficiency and effectiveness criteria. These linked back to the prior year’s recommendations that were raised around the budget gap, Designated Schools Grant deficit and improvements need in the Children's Social Care Services. These would remain under review and would be followed up as part of GT’s work and report alongside the audit findings report to be delivered in September. 5. The audit logistics and team were outlined on page 58. A consistent team is in place to deliver the audit, logistics and the time frame. It was confirmed that the audit would be going into Phase 1 audit running from mid-June until late September, hoping for a timely sign off, of the accounts towards the end of September early October.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 235 KB | DownloadRead as text |
Follow Audit and Governance Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | MinutesThat the minutes of the meeting held on 29 September 2026 be confirmed as a correct record and signed by the chairman. | Decided | Open |
| 3 Nov 2026 | Work programmeThat, subject to the updates made by the committee, the work programme be noted. | Noted | Open |
| 29 Sep 2026 | MinutesThat the minutes of the meeting held on 21 July 2026 be confirmed as a correct record and signed by the chairperson. | Decided | Open |
| 29 Sep 2026 | External Audit Findings ReportThat the report of the external auditor having been considered agreed that no issues raised in the report be added to... | Agreed | Open |
| 29 Sep 2026 | Final Annual Governance StatementThat the Annual Governance Statement for 2025/26 properly reflects the council’s internal control environment and the... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.