Resolved
That the minutes of the meeting held on 8 July 2025 be confirmed as a correct record and be signed by the Chairperson.
Connected Communities Scrutiny Committee decided this item on Tuesday 9 September 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the meeting held on 8 July 2025 be confirmed as a correct record and be signed by the Chairperson.
Minutes of the meeting of the Connected Communities Scrutiny Committee held in Conference Room 1 - Herefordshire Council, Plough Lane Offices, Hereford, HR4 0LE on Tuesday 8 July 2025 at 2.00 pm
Committee members Councillors: Bruce Baker, Frank Cornthwaite (Vice-Chairperson), present in person Elizabeth Foxton, Ed O'Driscoll (Chairperson) and Diana Toynbee and voting:
Others in attendance:
Councillor B Durkin Cabinet Member Roads and Herefordshire Council Regulatory Services B Evans Engineering Manager Herefordshire Council S Hodges Directorate Services Team Leader Herefordshire Council H Merricks-Murgatroyd Democratic Services Officer Herefordshire Council Councillor P Price Cabinet Member Transport and Herefordshire Council Infrastructure A Rees-Glinos Democratic Services Support Officer Herefordshire Council D Webb Statutory Scrutiny Officer Herefordshire Council
61. APOLOGIES FOR ABSENCE
No apologies for absence were received.
62. NAMED SUBSTITUTES
There were no named substitutes.
63. DECLARATIONS OF INTEREST
No declarations of interest were made.
64. MINUTES
The minutes of the previous meeting were received.
Resolved: That the minutes of the meeting held on 3 June 2025 be confirmed as a correct record and be signed by the Chairperson.
65. QUESTIONS FROM MEMBERS OF THE PUBLIC
No questions had been received from members of the public.
66. QUESTIONS FROM MEMBERS OF THE COUNCIL
No questions had been received from councillors.
67. GULLY CLEANSING The committee considered a report on Gully Cleansing.
The Engineering Manager introduced a presentation and welcomed the opportunity to update the committee on Gully Cleansing.
The principal points of the subsequent discussion are summarised below:
1. In response to a question regarding progress on mapping all drains, gullies, and culverts under the responsibility of Herefordshire Council, the Engineering Manager acknowledged that the process is not yet complete and will remain challenging until inspections have been carried out across the entire county. However, progress has been made in developing a clearer understanding of the network. The report also includes a link to the full map of gullies, as well as a link to this year’s programme of works.
2. The Chairperson stressed the importance of knowing when a high percentage of the county's drains will be mapped, along with a clear strategy for achieving this goal to enable progress tracking.
3. The Cabinet Member Roads and Regulatory Services reported that progress is advancing quickly, and a significant amount of information is being gathered. It was also suggested that a progress report may be provided in the future.
4. The Engineering Manager added that an update can be brought back to the committee to highlight what progress has been made.
5. In response to a question about how a parish lengthsman can deal with gullies for their area, the Engineering Manager noted that some lengthsmen have their own jetting machine or can bring in the council’s.
6. In response to a question about how the repairs from last year’s flooding gone, the Directorate Services Team Leader noted that in terms of where assets had been identified for repair, they had been repaired using existing drainage budgets and there was an additional investment made available to last year and this year of £2m in investment. In terms of some of the locations, work had been done closely with Balfour Beatty to ensure that the right locations were prioritised.
7. The Engineering Manager added that a performance update of what’s been delivered and the programme for delivery can be brought to committee in the future.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 148 KB | DownloadRead as text |
Follow Connected Communities Scrutiny Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | MinutesThat the minutes of the meeting held on 7 July 2026 be confirmed as a correct record. | Decided | Open |
| 7 Jul 2026 | MinutesThat the minutes of the meeting held on 15 April 2026 be confirmed as a correct record. | Decided | Open |
| 7 Jul 2026 | Work Programme 2026-7It was agreed that consideration of the item be deferred to the next meeting of the committee. | Agreed | Open |
| 15 Apr 2026 | MinutesThat the minutes of the meeting held on 17 February 2026 be confirmed as a correct record and be signed by the Chairp... | Decided | Open |
| 17 Feb 2026 | MinutesThat the minutes of the meeting held on 9 September 2025 be confirmed as a correct record and be signed by the Chairp... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.