AI summaryHerefordshire Council's Audit and Governance Committee has unanimously approved updates to the Contract Procedure Rules to reflect new procurement thresholds from 1 January 2026, with no changes to Finance Procedure Rules.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedUnanimous vote; no Finance Procedure Rules changes
MoneyNot stated
What happens nextUpdated rules to be embeddedTraining and toolkit updates to follow
Who it affectsCouncil procurement and contractingOfficers and members undertaking procurement activity
What was decided
The committee approved updates to the Contract Procedure Rules set out in Appendix 1 of the constitution. Report P11, P39
The committee noted that no changes were recommended to the Finance Procedure Rules or Finance Procedure Guidance Notes. Report P21, P22
The vote was carried unanimously.
Why
New UK threshold amounts under the Procurement Act 2023 take effect on 1 January 2026, and above-threshold values for goods, services and works have reduced slightly, with the Light Touch Regime unchanged. Report P8, P12
A regular review of the rules is needed to keep them up to date with statutory responsibilities, the constitution, legislation and the Procurement Act 2023 and Procurement Regulations 2024, which came into effect on 24 February 2025. Report P6, P8, P34
Officers consider the Finance Procedure Rules and associated guidance remain fit for purpose and do not require modification at this time. Report P21, P22
What happens next
The updated Contract Procedure Rules will be incorporated into the constitution and embedded across the organisation through training, an updated contracting toolkit and a communication plan. Report P35, P36
Oversight of compliance with the revised legislative and procedural requirements will continue through established governance and monitoring processes. Report P35
Officers will continue to use online facilities rather than paper-based processes, in line with the council's Environmental Policy. Report P28
Options considered
Chosen: Approve the updates to the Contract Procedure Rules and note no changes to Finance Procedure Rules. Updates are needed to reflect new procurement thresholds and learning from the Procurement Act 2023, and to keep rules fit for purpose. Report P1, P8, P34
Rejected: Continue with the current financial and contract procedure rules. Risks the rules becoming unfit for purpose and not aligned with new threshold amounts under the Procurement Act 2023 effective 1 January 2026. Report P1
Implications
Legal: The council must keep its constitution up to date under section 37 of the Local Government Act 2000; the updated CPRs meet the Local Government Act (Constitutions) (England) Direction 2000. Report P9, P33
Financial: There are no specific resource implications from updating the rules. Report P32
Equalities: An equality screening found no impact for equality, so a full Equality Impact Assessment is not required. Report P31
Climate: The procedural update has minimal environmental impact, but encourages online rather than paper-based working. Report P28
Risk: Risks include officers applying the rules incorrectly and officers or members being unaware of updates; mitigations are training, a communication plan, an updated contracting toolkit and ongoing oversight. Report P35, P36
Other: The rules support transparency, accountability, best value and compliance with the Procurement Act 2023 and Procurement Regulations 2024. Report P10, P25, P34
Who and where
Council officers and members responsible for procurement and contract management Report P3, P10, P35
Suppliers and contractors seeking to do business with the council Report P9, P12
Service users, particularly in social care, where User Choice Services allow direct award to a chosen supplier Report P20
Herefordshire residents, as taxpayers, through the council's duty to manage public resources openly and accountably Report P25
Timeline
28 January 2025: Contract Procedure Rules and Finance Procedure Rules were last reviewed, updated and approved by the Audit and Governance Committee. Report P7
24 February 2025: Procurement Act 2023 and Procurement Regulations 2024 came into effect. Report P8, P34
1 January 2026: New UK above-threshold amounts under the Procurement Act 2023 take effect; thresholds for goods, services and works reduced slightly, Light Touch Regime unchanged. Report P1, P12
27 January 2026: Audit and Governance Committee approved the updated Contract Procedure Rules and noted no changes to the Finance Procedure Rules.
Plain English for the jargon
Contract Procedure Rules (CPRs): The council's policy for procurement, setting out how contracts for goods, works, services, concessions and utilities are put in place and managed.
Finance Procedure Rules: The framework the council uses to manage its financial affairs, setting out responsibility and authority for Cabinet Members and officers.
Procurement Act 2023 (PA23): UK law governing public procurement, requiring open, fair and transparent contract procedures, with new threshold amounts from 1 January 2026.
Teckal exemption: Exemption for contracts between public authorities and a controlled body, and for horizontal arrangements between public authorities under Schedule 2 of the Procurement Act 2023.
Light Touch Regime: A procurement regime under the Procurement Act 2023 for certain services, whose threshold has remained the same for 2026.
User Choice Services: Circumstances, often social care related, where a contract may be directly awarded to a supplier chosen by the service user or their carer.
PPN 023: Procurement Policy Notice 023, the government publication setting out the updated 2026 threshold amounts.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item117
Resolved
That the committee approves the updates to the Contract Procedure Rules in Appendix 1 in the constitution and notes that there are no changes recommended to the Finance Procedure Rules or Finance Procedure Guidance Notes. The vote was carried unanimously.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
1. The council could continue with its current financial and contract procedure rules. This is not recommended as this introduces the risk that they would not be fit-for-purpose and provide clarity of roles and processes for those charged with undertaking financial and procurement activity. Further this would mean that the contract procedure rules were not in accordance with new threshold amounts which govern the procedures for the award of public contracts for goods, works and services as set out in the Procurement Act 2023 (PA23) that come into force on 1 January 2026.
Further information on the subject of this report is available from Carrie Christopher, , email: [email protected] OFFICIAL
Key considerations 2. The council’s Contract Procedure Rules (CPRs) provide the policy for procurement activity across the council, setting out how contracts for goods, works, services, concessions and utilities should be put in place and managed, and detailing the record keeping and reporting requirements related to procurement activity.
3. The Financial Procedure Rules set out the framework which the council will use in managing its financial affairs. They set out levels of responsibility and give authority to the Cabinet Members and Officers and are intended to promote good practice in the use of public funds.
4. The Financial Procedures Rules give detailed guidance on how the overarching framework is implemented.
5. In line with good practice, a regular review of these rules is important to ensure that they remain up-to-date with any changes to the council’s statutory responsibilities, relevant legislation, the council’s constitution and/or how the council conducts its business.
6. Both the contract procedure rules and finance procedure rules were last reviewed, updated and approved by the Audit and Governance Committee on Tuesday 28 January 2025.
Contract Procedure Rules 7. The 2026 updates to the CPRs are to reflect the updated 2026 threshold amounts as published in Procurement Policy Notice (PPN) 023 and to take account of the learning following the introduction of the Procurement Act 2023 and Procurement Regulations 2024, which came into effect on 24 February 2025.
8. The Local Government Act 1972 requires the Council to have standing orders governing how it enters into contracts. The CPRs satisfy this requirement. The Council is subject to UK law with regard to public procurement which requires all contract procedures to be open, fair and transparent. The CPRs provide a basis for fair competition, with clear and auditable procedures.
9. The CPRs ensure a clear and consistent approach to procurement, set the minimum standard of best practice and assurance of good contract management practice within the organisation. The amendments enable officers and members to demonstrate best value and best practice.
10. A final copy of the updated CPRs is attached at Appendix 1. The key amendments include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Final Annual Governance StatementThat the Annual Governance Statement for 2025/26 properly reflects the council’s internal control environment and the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.