Resolved
Decision that t he Executive’s response to the Scrutiny Review of the Implementation of Section 106 monies and the Community Infrastructure Levy be approved as set out in Appendix 1 of the Executive Report EX/22/44. Reasons for the Decision The Operations Review Committee had made a number of recommendations. The Executive’s response sought to resolve all the issues raised, except in one case (Recommendation 6) where this was not considered possible due to the unpredictable nature of CIL receipts. Alternative Options Considered and Rejected There was no alternative option to addressing the recommendations. Action: Head of Planning & Economic Development
Word for word from the decision Hertsmere published for this meeting.