RESOLVED - That the application be APPROVED for the reasons and based on the policies contained in the report, subject to the compensatory planting and time frame as referred to above. (Proposed by Councillor Roberts and seconded by Councillor Lea.)
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL PLANNING APPLICATIONS COMMITTEE 19th January 2017
Application SMD/2016/0320 No: Location Former Staffordshire Farmers Site, Cheadle Road, Cheddleton Proposal Variation of Section 106 Agreement dated 29th June 2010 (08/01715/FUL-MJ) Applicant John Pointon and Sons Ltd. Agent Sammons Architectural Parish/ward Cheddleton Date registered 19/05/2016 If you have a question about this report please contact: Jane Curley tel: 01538 395400 x4124 or [email protected] REFERRAL
The application is before committee because it is a request to modify a Section 106 Agreement
1. SUMMARY OF RECOMMENDATION
Approve
2. INTRODUCTION AND BACKGROUND
2.1The applicant, John Pointon and Sons is seeking a variation to a Section 106 Planning Obligation dated 29th June 2010 and Deed of Variation to that agreement dated 22nd November 2012 associated with planning permission 08/01715/FUL-MJ for an Energy Resource Centre at Felthouse Lane Cheddleton. The variation relates only to the phasing set out in the Third Schedule and specifically Phase 4 of the Deed of Variation dated 22nd November 2012 which relates to the former Staffordshire Farmers site. The request is to modify the Deed by removing sections 1, 2 and 3.
2.2The Third Schedule of the Agreement is divided into four phasing stages. Phase 4 reads as follows:-
Phase 4
1. Within 3 years of the Commencement of Development cease all commercial or industrial use of buildings and structures on the Orange Land known as Staffordshire Farmers 2. Within 4 years of the Commencement of Development remove buildings and structures identified on Plan 4 from the Orange Land and clear the site of building materials rubble and hardstanding 3. Restore the Orange Land and plant as forest/woodland area within 1 year of the demolition of the buildings and structures identifed on Plan 4 in accordance with details to be first agreed in writing by the Local Planning Authority. 4. The Energy Resource Centre comprises the land and buildings more particulalry idenitifed on the land edged orange on Plan 2 5. Prior to the construction and completion of the Category 3 Meal Store and the Secure Store all of which are comprised within the Energy Resource Centre the Renewable Energy Power Generation Unit and the Anaerobic Digestion Plant which also form part of the Energy Resource Centre shall be constructed and brought into full use and operation 2.3 In support of the application the applicant makes these points:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.