Heritage Regeneration Grants

Approved Committee 1 paper

Corporate Select Committee approved this item on Monday 20 March 2017. Below is the council's own wording, with the papers it was decided on.

Item17/78

Resolved

That the Executive be recommended to: 1. Approve a 50% grant of up to £3265 (ex VAT) for eligible work totalling £6530 (ex VAT) towards the repair of an original shop front in Chinley Conservation Area 2. Approve a 75% grant of up to £6570 (ex VAT) for eligible works totalling £8,760 (ex VAT) towards the restoration of a traditional shop front in Hadfield Town Centre.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Corporate Select Committee

Recommendation

That the Executive be recommended to:

2.1consider and approve a 50 % grant of up to £3265 (exc VAT) for eligible works totalling £6530 (exc VAT) towards the repair of an original shop front in the Chinley Conservation Area.

2.2consider and approve a 75% grant of up to £6,570 (exc VAT) for eligible works totalling £8,760 (exc of VAT) towards the restoration of a traditional shop front in Hadfield town centre.

Executive summary

3.1Heritage Regeneration Grants promote the repair and restoration of historic buildings within the High Peak Local Plan area. The scheme operates with a budget of £45,000 per annum. Given the limited budget, grant awards are restricted to a maximum of £10,000 per property. Under this scheme, Councillors are asked to consider 2 grant applications that seek to repair or reinstate traditional shopfront details within the borough’s town and village centres. Officers have assessed the applications against the funding criteria and conclude that each application will make a positive impact on the appearance of the building and area.

4. How this report links to Corporate Priorities

4.1This report concerns publicly funding the restoration and repair of historic properties that are either listed, identified heritage assets or located within one of the Council's conservation areas. This, in turn, is related to the Council’s corporate aim 3:

• To support Economic Development & Regeneration – measured by sustainable town and rural communities.

5. Options and Analysis

5.1Option 1 - Approve the recommendations outlined in this report to enable officers to offer grant aid totalling £9,635 towards the repair and restoration of 2 historic buildings within the borough. The repair and restoration works to each shop frontage will enhance the heritage value of the building and locality and act as an exemplar to positive repair and restoration. Recommended

5.2Option 2 – Officers do not allocate grant aid totalling £9,635 towards 2 historic buildings within the borough and the opportunity to enhance and preserve historic buildings in commercial use within town and village centres is missed. Not recommended.

6. Implications

6.1Community Safety - (Crime and Disorder Act 1998)

No implications

6.2Workforce

No implications

6.3Equality and Diversity/Equality Impact Assessment

This report has been prepared in accordance with the Council's Diversity and Equality Policies.

6.4Financial Considerations

There are allocations within the capital programme for the Heritage Regeneration Grant scheme. There is £35,000 remaining to make the grant recommended in this report. Budget for 2016/17 - £45,000 Remaining unallocated budget- £25,165

6.5Legal

Local authorities are empowered to give grants towards improvements in conservation areas under Section 57 of the Planning (Listed Buildings and Conservation Areas) Act 1990.

6.6Sustainability

Repairing, restoring and in some cases bringing back into use the historic building stock for future generations is a sustainable activity.

6.7Internal and External Consultation

The relevant ward Members have been consulted on the grant applications and have offered their support to the grant applications.

6.8Risk Assessment

No implications.

Dai Larner Executive Director

Web Links and Location Contact details Background Papers Heritage Regeneration Grants Files held electronically Joanne Brooks ext 3654

7. Background and Detail

7.1There have been no previous Heritage Regeneration grants approved previously, for these buildings.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Heritage Regeneration GrantsReport 189 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 21 attended
AB
Councillor Alan BarrowChair, present
JD
Councillor Jamie DouglasVice-Chair, present
GC
Councillor Godfrey ClaffCommittee Member, present
AF
Councillor Andrew FoxCommittee Member, present
LG
Councillor Linda GroobyCommittee Member, present
PH
Councillor Paul HardyCommittee Member, present
SH
Councillor Sarah HelliwellCommittee Member, present
DL
Councillor David LomaxCommittee Member, apologies, sent representative
AM
Councillor Anthony McKeownCommittee Member, present
RM
Councillor Robert McKeownCommittee Member, present
JP
Councillor John PritchardCommittee Member, present as substitute
KS
Councillor Kath SizelandCommittee Member, present

All 21 on the meeting page

On this subject at High Peak

Search all
  1. Heritage Regeneration GrantsThis decision
  2. Heritage Regeneration GrantsApproved
  3. Heritage Regeneration GrantsApproved
  4. Heritage Regeneration GrantsApproved

More from High Peak Corporate Select Committee

All decisions
MeetingDecisionOutcome
20 Jul 2026 To approve the minutes of the previous meetingThat the minutes of the meeting held on 8 June 2026 be approved as a correct record. Approved Open
20 Jul 2026 Select Committee Work ProgrammeThat, subject to the above, the Select Committee Work Programme, be noted. Noted Open
20 Jul 2026 Fourth Quarter Finance, Performance and Procurement UpdateThat the Fourth Quarter 2025/26 financial, procurement and performance position detailed in Appendices A, B and C and... Noted Open
20 Jul 2026 Performance Framework 2026/27That the proposed set of performance indicators and targets, and contextual indicators as set out in Appendix A be no... Noted Open
20 Jul 2026 Exclusion of Press and PublicThat the press and public be excluded from the meeting during the following item of business as there may be disclosu... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies