Allocation of S106 monies from the Hyde Bank Mill development for a public access project in New Mills
ApprovedExecutive1 paper
The Executive - Individual Executive Decisions approved this item on Tuesday 27 June 2017. Below is the council's own wording, with the papers it was decided on.
That approval is given to utilise existing s106 funding to assist New Mills Town Council Town Council deliver a public access project at The Torrs in New Mills. A note of any conflict of interest declared None A note of any dispensation if granted None
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
Report to The Executive - Individual Executive Decisions
Recommendation
2.1That approval is given to utilise existing s106 funding to assist New Mills Town Council Town Council deliver a public access project at The Torrs in New Mills.
Executive summary
3.1The Council has responsibility for spending planning contributions arising from s106 agreements relating to open space, play and recreational facility improvement projects. Derbyshire County Council (DCC) are also able to request contributions for highway improvements and in such circumstances the funding is currently held by the council until such time that DCC submit an acceptable scheme for the spend. At this point the funding is passed to DCC to undertake the works. 3.2 In some cases DCC are not able to provide suitable schemes for this spend, and the s106 funds therefore remain unspent.
3.3In 2007 the council received £15,000 as part of s106 agreement from the Hyde Bank Mill development in New Mills (HPK/2004/0190) for the construction or improvement of pavements or parts thereof for pedestrian use in Meal Street, New Mills.
3.4Derbyshire County Council were asked to provide a scheme for the works in 2008 which came in far in access of the funds available, in the main due to the current conditions of the road and existing retaining wall. Discussions with DCC have resulted in them confirming that they are not able provide a suitable scheme within budget, and therefore do not want to accept the s106 monies.
3.4As a result, the money has remained unutilised with the council and the repayment date is 31st October 2017. After this time, there is a risk that the council will face a legal challenge by the developer to re-pay the funding.
3.5It is proposed that the £15,000 s106 made as a contribution to New Mills Town Council to assist them with a historically important public access project at The Torrs Open Space, as outlined in Section 7 below.
4. How this report links to Corporate Priorities
4.1Delivering an important public access project in this open space will contribute towards helping to create a safer and healthier environment for our Resident’s to live and work. It will enable the development of a positive relationship with communities and the different organisations in the area, which will be engaged and involved throughout the project process, and will quite clearly see the benefits within the local community. With s106 contributions focussed on improvements to publicly accessible open space, these projects create leisure opportunities with emphasis on improving health in free outdoor provision.
4.2This project is about utilising the opportunities provided by the s106 funding to release external funding grants which will assist fully in the delivery of the project. Options are increased to provide a wider range of facilities, rather than just through the s106 funds. This contributes to meeting financial challenges and providing value for money. These s106 funds can be utilised towards a public access project which is very much needed but is currently unfunded, and this will also significantly reduce the risk of any funds having to be paid back.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow The Executive - Individual Executive Decisions at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
Visit Peak District & Derbyshire SLAThat the signing of the High Peak Visit Peak District & Derbyshire SLA 2026 – 2029 to allocate a total of £30,000 (£1...
Alliance MyActive Wellbeing LimitedRESOLVED 1. That the appointment of [name removed] as an Independent Director of Alliance MyActive Wellbeing Ltd. be ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.