Resolved
That Council be recommended to approve the Annual Treasury Management Report 2016/17.
Audit & Regulatory Committee approved this item on Wednesday 26 July 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That Council be recommended to approve the Annual Treasury Management Report 2016/17.
2.1That the Annual Treasury Management Report 2016/17 is recommended to Council for approval.
3.1The Council is required through regulations issued under the Local Government Act 2003 to produce an annual treasury report reviewing treasury management activities for the year.
3.2The Annual Treasury Management Report for 2016/17 considers the following areas:
The Treasury Management Strategy adopted for 2016/17 and the economic environment during the year; The current treasury position, highlighting the Council’s borrowing and lending position at the year end; The Council’s capital expenditure, overall borrowing need and borrowing outturn during 2016/17; Performance measurements, which look at the returns achieved during the year by the Council on its overall investments; The Council’s investment portfolio, which sets out how and where the Council has invested its money during the year; The interest yield for 2016/17; and Compliance with prudential Iidicators, showing the outturn against those Indicators formally adopted in the 2016/17 Treasury Management Strategy.
3.3The main headlines include:
Capital expenditure in 2016/17 totalled £5 million. The majority was funded via revenue contributions. There was a borrowing requirement of £965,895 during the year wholly applicable to General Fund capital expenditure.
Total debt at 31st March 2017 amounted to £72 million including loans from Public Works Loan Board, Market Loans, Local Authority Loans and finance lease arrangements.
There were loan maturities of £9,748,100 during the year – none of this was refinanced; no new external borrowing took place; nor was there any debt rescheduling.
General Fund borrowing costs were £54,340 underspent against the budget as this anticapted both refinancing of maturing loans and new borrowing during the year; there was also a larger net charge to the HRA than anticipated due to the effect of the proportional split of the one pool approach.
The average daily investment during 2016/17 was £23.3 million invested with a total of 16 institutions, yielding £119,330 in investment income. This represented a shortfall of £11,330 against the 2016/17 budgeted investment income following the cut in the Bank of England Base Rate to 0.25% on 4th August 2016.
The average return achieved by the Council on its investment portfolio for the year was 0.51%, which compares favourably to short-term industry benchmarks.
Year-end investments totalled £13.7 million all internally managed by the Council’s treasury management team.
The outturn against the treasury and prudential indicators set within the Treasury Strategy 2016/17 is shown in Annex B.
4. How this report links to Corporate Priorities
4.1An effective Treasury Management function is critical in safeguarding and effectively managing the financial resources at the Council’s disposal. Sufficient financial resources are required to deliver and underpin the Council’s main priorities. 5. Options
5.1This report sets out the treasury management position for High Peak Borough Council for 2016/17. As such it is a statement of fact and there are no options to consider.
6. Implications
6.1Community Safety – (Crime and Disorder Act 1998) None
6.2Workforce None
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual Treasury Management Report 2016/17Report | 1 MB | DownloadRead as text |
Follow Audit & Regulatory Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jun 2026 | To approve the Minutes of the previous meetingThat the minutes of the previous meeting held on 11 February 2026 be approved as a correct record. | Approved | Open |
| 2 Jun 2026 | High Peak Borough Council Audit Plan 2025 - 2026 (External Audit)That the report be noted. | Noted | Open |
| 2 Jun 2026 | Audit Progress and Sector Update Report (External Audit)That the report be noted. | Noted | Open |
| 2 Jun 2026 | Internal Audit Periodic Report February 2026 to May 2026That the Committee notes the progress information within the report. | Decided | Open |
| 2 Jun 2026 | Internal Audit CharterThat the Council’s Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.