Resolved
That Council be recommended to approve the Annual Treasury Management Report 2017/18.
Audit & Regulatory Committee approved this item on Wednesday 25 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That Council be recommended to approve the Annual Treasury Management Report 2017/18.
2.1That the Annual Treasury Management Report 2017/18 is recommended to Council for approval.
3.1The Council is required through regulations issued under the Local Government Act 2003 to produce an annual treasury report reviewing treasury management activities for the year.
3.2The Annual Treasury Management Report for 2017/18 considers the following areas:
The Treasury Management Strategy adopted for 2017/18 and the economic environment during the year; The current treasury position, highlighting the Council’s borrowing and lending position at the year end; The Council’s capital expenditure, overall borrowing need and borrowing outturn during 2017/18; Performance measurements, which look at the returns achieved during the year by the Council on its overall investments; The Council’s investment portfolio, which sets out how and where the Council has invested its money during the year; The interest yield for 2017/18; and Compliance with prudential indicators, showing the outturn against those Indicators formally adopted in the 2017/18 Treasury Management Strategy.
3.3The main headlines include:
Capital expenditure in 2017/18 totalled £6.5 million. This created a borrowing requirement of £2.6 million wholly applicable to General Fund capital expenditure.
Total debt at 31st March 2018 amounted to £72 million including loans from Public Works Loan Board (PWLB), market loans, local authority loans and finance lease arrangements.
There were no loan maturities during the year; no new external borrowing took place; nor was there any debt rescheduling.
Overall borrowing costs were £45,000 underspent against the budget as refinancing of maturing loans from the previous year and new borrowing was anticipated during the year, whereas internal borrowing was used instead. This was split between the General Fund (£30,000 overspend) and HRA (£75,000 underspend).
The average daily investment during 2017/18 was £18.7 million invested with a total of 10 institutions, yielding £92,249 in investment income. There was a surplus achieved against the investment income budget of £27,529 as rates improved following the return in the Bank of England Base Rate to 0.50% in November 2017.
The average return achieved by the Council on its investment portfolio for the year was 0.49%, which compares favourably to short-term industry benchmarks.
Year-end investments totalled £13.7 million all managed by the Council’s Treasury Management Team.
The outturn against the treasury and prudential indicators set within the Treasury Strategy 2017/18 is shown in Annex B.
4. How this report links to Corporate Priorities
4.1An effective Treasury Management function is critical in safeguarding and effectively managing the financial resources at the Council’s disposal. Sufficient financial resources are required to deliver and underpin the Council’s main priorities.
5.1This report sets out the treasury management position for High Peak Borough Council for 2017/18. As such it is a statement of fact and there are no options to consider.
6. Implications
6.1Community Safety – (Crime and Disorder Act 1998) None
6.2Workforce None
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual Treasury Management Report 2017/18Report | 245 KB | DownloadRead as text |
Follow Audit & Regulatory Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jun 2026 | To approve the Minutes of the previous meetingThat the minutes of the previous meeting held on 11 February 2026 be approved as a correct record. | Approved | Open |
| 2 Jun 2026 | High Peak Borough Council Audit Plan 2025 - 2026 (External Audit)That the report be noted. | Noted | Open |
| 2 Jun 2026 | Audit Progress and Sector Update Report (External Audit)That the report be noted. | Noted | Open |
| 2 Jun 2026 | Internal Audit Periodic Report February 2026 to May 2026That the Committee notes the progress information within the report. | Decided | Open |
| 2 Jun 2026 | Internal Audit CharterThat the Council’s Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.