The Executive - Individual Executive Decisions, Friday 19 October 2018 at 10.00am

River Bank / Wall Re-instatement 84 - 86 Buxton Road, Whaley Bridge

Noted Executive 1 paper

The Executive - Individual Executive Decisions noted this item on Friday 19 October 2018. Below is the council's own wording, with the papers it was decided on.

Item19/8

Resolved

That the report be noted and the recommendations in Section 8 of the report be approved. Any declaration of interest None A note of any dispensation granted, if any None
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to The Executive - Individual Executive Decisions

Recommendation

2.1That the Executive Councillors be requested to note the contents of the report and approve the recommendations in Section 8.

Executive summary

3.1The Authority is the owner of a field and access way adjacent to 84 / 86 Buxton Road Whaley Bridge, this includes the wall that runs along side the river Goyt. In December 2016 the wall adjacent to the access pathway collapsed into the river. As an interim measure, and to try and limit further damage to the base of the wall, several tonne bags of stone were placed at the base of the wall in the river to provide some protection and stop further erosion.

3.2Officers have retained specialists RAB Consultants to identify a means to reinstate the wall for the future. By its nature, location and proximity of third party properties the anticipated work will be extremely difficult to access and undertake in a safe manner.

3.3The preferred method to secure the wall is by way of a specialist underpinning process using soil nails, the costs of which are anticipated to be in the order of £360,000, for which there is not sufficient current budget allocation.

3.4The report outlines the options considered and identifies suitable sources of Capital Funds to meet the costs.

4. How this report links to Corporate Priorities

4.1To protect and improve the environment.

5. Options and Analysis

5.1Options are not considered applicable in the context of this procurement.

6. Implications

6.1Community Safety - (Crime and Disorder Act 1998)

There are no specific community safety concerns. Safeguarding protocols are observed and implemented.

6.2Workforce

There are no specific workforce implications

6.3Equality and Diversity/Equality Impact Assessment

The report has been prepared in accordance with the Council’s Diversity and Equality Policy

6.4Financial Considerations

The report outlines other projects where funding can be gained to meet the project costs.

6.5Legal

The contractor would be appointed under a Design and Build contract given the specialist nature of the works.

The procurement exercise will be compliant to the requirements as set out in the Public Contract Regulations 2015 and the Council’s Procurement Procedure Rules.

6.6Sustainability

There are no specific sustainability issues 6.7 Internal and External Consultation

Consultation was not required.

6.8Risk Assessment

There are clear risks with not addressing the works with potential damage to neighbouring properties over time, further slippage to the bank making the field inaccessible and further risks to the river becoming blocked should the wall further collapse.

The option of re building the wall would potentially provide a temporary solution but repeated failure is extremely likely. This would put added pressure on the remaining wall where it is also observed that the wall is cracking and bulging.

Re building the wall with added structural support would potentially ensure that the wall remained sound for circa 30 years or more.

7. Background and Detail

7.1The Authority is the owner of a field and access way adjacent to 84 / 86 Buxton Road Whaley Bridge, this includes the wall that runs along side the river Goyt.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
River Bank / Wall Re-instatement 84: 86 Buxton Road, Whaley BridgeReport 86 KB DownloadRead as text

At this meeting

Whole meeting
19/8River Bank / Wall Re-instatement 84 - 86 Buxton Road, Whaley BridgeThis decision

More from High Peak The Executive - Individual Executive Decisions

All decisions
MeetingDecisionOutcome
18 Aug 2026 Asset of Community Value nomination - Hockerley Meadow, Whaley BridgeThat the nomination for land lying to the Northwest of Hockerley Lane, Whaley Bridge, High peak be declined for the r... Decided Open
4 Aug 2026 Request for additional capital Funds towards the Gamesley Play Improvement ProjectsThat the allocation of £100,000 from the Council’s capital funds to ensure that improvements at both play areas meet ... Approved Open
4 Aug 2026 Request for Capital Funding to Support Improvements to Manor Park CaféThat the allocation of £30,000 from the Council’s capital funds to undertake essential refurbishment and improvement ... Approved Open
4 Aug 2026 Visit Peak District & Derbyshire SLAThat the signing of the High Peak Visit Peak District & Derbyshire SLA 2026 – 2029 to allocate a total of £30,000 (£1... Approved Open
28 Jul 2026 Alliance MyActive Wellbeing LimitedRESOLVED 1. That the appointment of [name removed] as an Independent Director of Alliance MyActive Wellbeing Ltd. be ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies