That approval be given for the installation of two accessible items of play equipment at Manor Park Play Area; 2. a. that the allocation of £13,000 in the Capital Programme for the installation of accessible play equipment items at Manor Park Area be approved. This is to be funded from an application to the Awards 4 All Lottery Fund for £10,000 if successful and £3,000 from the Council’s Capital Programme for Play Facilities; b. Should the Awards 4 All application be unsuccessful, the funding of the full £13,000 costs via the Council’s Capital Programme for Play Facilities in its February 2019 iteration be approved. Any declaration of interest received None A note of any dispensation, if any None
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
Report to The Executive - Individual Executive Decisions
Recommendation
2.1That approval is given for the installation of two accessible items of play equipment at Manor Park Play Area.
2.2a) to seek approval to allocate £13,000 in the Capital Programme for the installation of accessible play equipment items at Manor Park Play Area. This is to be funded from an application to the Awards 4 All Lottery Fund for £10,000 if successful and £3,000 from the Council’s Capital Programme for Play Facilities.
b) Should the Awards 4 All application be unsuccessful then approval is sought, in advance, to fund the full £13,000 costs via the Council’s Capital Programme for Play Facilities, in its February 2019 iteration. 3. Executive Summary
3.1Manor Park is Glossop's destination site and attracts visitors across the High Peak area as well neighbouring Tameside, due to its beautiful setting, excellent facilities and varied local events. It is very popular and used all year round and is intrinsic to the strong, diverse, and growing local community
3.2The Friends of Manor Park are very active group, and have been consulting with park users over the last 12 months, regarding the suitability of provision of facilities in the park. Through this consultation, the group were approached directly by some local families whose children have disabilities and who feel that the park is extremely important to their child’s development. Their concern is that their children are excluded from the play experience.
3.3After raising these concerns with the council, further discussions with the Friends group and the families took place around the existing play area and different types of equipment available and which would be most suitable and appropriate.
3.4The aim of this project is therefore to create a new free ‘active space’ with an enhanced play area, and linking space for outdoor fitness opportunities, which allows participation together by families of all ages.
3.5It was agreed that two specific items would be appropriate and fit well into the existing place, and these would be an accessible flush roundabout and a set of high backed mirage swings seats; similar to those installed at Pavilion Gardens in Buxton in 2016
3.6It was also agreed that due to limited existing resources, an external funding application would be submitted by the Council as the lead applicant, with the support of the Friends Group. An Awards 4 All Lottery Fund grant application was submitted at the beginning of November for £10,000 (maximum grant). The costs already obtained for this project are approximately £13,000 which means there would be a shortfall of £3,000.
3.7This report seeks approval for the Council to fund the project shortfall from its Capital Programme, to be included in February 2019, if the external grant application is successful, and in its entirety if the application is unsuccessful.
3.8The turnaround for assessment of applications by Awards 4 All is usually 10 weeks, so the outcome will not be known until mid/end January 2019. If approval is given for this report, then a procurement exercise to appoint a supplier can be undertaken whilst the application is under assessment by Awards 4 All.
3.9This will allow for the project to be delivered depending on either funding outcome, in early spring 2019. 4. How this report links to Corporate Priorities
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow The Executive - Individual Executive Decisions at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
Visit Peak District & Derbyshire SLAThat the signing of the High Peak Visit Peak District & Derbyshire SLA 2026 – 2029 to allocate a total of £30,000 (£1...
Alliance MyActive Wellbeing LimitedRESOLVED 1. That the appointment of [name removed] as an Independent Director of Alliance MyActive Wellbeing Ltd. be ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.