Economy and Growth Select Committee noted this item on Thursday 7 February 2019. Below is the council's own wording, with the papers it was decided on.
That, subject to the above, the contents of the report be noted; 2. That the Executive be recommended to accept the two late representations received; and 3. That the Executive be recommended to approve the Statement of Community Involvement, subject to the proposed modifications as set out in the report, and that the final version of the report be considered for adoption by full Council on 20 February 2019.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
2.1That the Economy and Growth Select Committee notes the contents of the report and makes any recommendations prior to the report going to the Executive on 14th February 2019.
2.2That the Committee recommends acceptance of the two late representations received.
2.3That the Committee recommends that the Executive approves the Statement of Community Involvement - subject to the proposed modifications set out in this report - such that a final version of the document can be considered for adoption by full council on 20th February 2019.
3. Executive Summary 3.1 The Statement of Community Involvement (SCI) is a statutory planning document which describes how the Council will engage with residents, businesses and other organisations in decision making on planning policy documents and planning applications. Its scope is that part of the High Peak that lies outside the Peak District National Park.
3.2The Council's most recent Statement of Community Involvement was adopted in May 2006. There have been a number of changes to the planning system since this date. In addition, a number of new opportunities to engage with the public (such as social media) have arisen. For these reasons it has been considered appropriate to update the SCI, bringing it in line with current legislation and public engagement methods.
3.3A six week period of public consultation was undertaken on the updated draft SCI, between 6th November and 19th December 2018. Twelve responses were received. These responses are set out in Appendix two to this report, with officer recommendation on any resultant modifications required. In addition, two late responses were received – these are also set out in Appendix two.
3.4A summary of the responses received is provided from paragraph 6.7 of this report. It is recommended that as a consequence of the public consultation, the following amendments to the SCI are made before the document is considered for adoption. In the table below, proposed additional text is shown underlined and text proposed for deletion is shown as crossed through.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.