RESOLVED – 1. That the application be APPROVED for the reasons and based on the policies contained in the report, subject to the conditions contained in the report. 2. In the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal), prior to the decision being issued the Head of Development Services had delegated authority to do so in consultation with the Chairman of the Planning Applications Committee, provided that the changes did not exceed the substantive nature of the Committee’s decision. (Proposed by Councillor Davies and seconded by Councillor Coleman.)
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL PLANNING APPLICATIONS COMMITTEE
27 June 2019
Application SMD/2019/0052 No: Location 18 Essex Drive, Biddulph Proposal Two-storey rear/side extension and single-storey carport extension Applicant Mr and [name removed] Design Associates Ltd Parish/Ward Biddulph Date registered 29/01/2019 If you have a question about this report please contact: [name removed][email protected]
SUMMARY OF RECOMMENDATION
APPROVE subject to conditions
REFERRAL
1. The application is brought before Planning Committee to due a call-in from Councillor Hart, to assess the impact on residential amenity.
1. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
1.1The application site is within the development boundary of Biddulph and lies within the Gillow Heath area of the town to the north-west of the town centre. It comprises a two-storey brick-and-tile detached dwelling on a 1960s/70s housing estate. It has a front gable design. The dwelling faces the bend in Essex Drive, a cul-de-sac to the north- west of the site. There are rows of houses facing Essex Drive either side of the site and to the other side of the road. There are also dwellings further away to the rear of the site to the east to the other side of Biddulph Brook. The rear garden slopes downwards towards the brook and is largely within a flood zone but the dwelling itself is not within this. Unlike many plots on Essex Drive, the site is not a uniform shape. It narrows towards the bend in the road and widens outwards towards the rear. As a result, the dwelling is placed at a diagonal angle to the neighbouring dwelling (semi-detached) at No.20 to the north and also to the neighbouring dwelling (detached) at No.16 to the south- west. 2. DESCRIPTION OF THE PROPOSAL
2.1This is a full householder planning application for extensions. The main extension would be a two-storey extension attached to the rear wall of the house, spanning its whole width and beyond towards the side boundary. It would project 5.05 metres from the rear wall and to the side would project 2.6 metres beyond the existing side wall of the house, creating an L-shaped dwelling.
2.2These are amended plans which replace the plans originally submitted which showed the side projection as a “lean-to” with catslide roof.
2.3A car port structure with fully hipped roof is proposed to be attached to the south-west side wall of the house. A rear raised terrace area with five steps from the garden (which slopes downwards towards the rear) would be built along with a glass balustrade.
2.4The application, the details attached to it, including the plans, any comments made by residents and the responses of consultees can be found on the Council’s website at:- http://publicaccess.staffsmoorlands.gov.uk/portal/servlets/Application SearchServlet?PKID=128101
3. RELEVANT PLANNING HISTORY
None.
4. PLANNING POLICIES RELEVANT TO THE DECISION
4.1The Development Plan comprises:-
Saved Staffordshire Moorlands Local Plan Proposals Map/Settlement Boundaries (Adopted 1998); The Staffordshire Moorlands Core Strategy Development Plan Document (Adopted 26th March 2014)
Staffordshire Moorlands Core Strategy Development Plan Document (Adopted March 2014)
4.2The following Core Strategy policies are relevant to the application:-
SS1 Development Principles SS1a Presumption in Favour of Sustainable Development DC1 Design Considerations Emerging Staffordshire Moorlands Local Plan
Local Plan Process
The Council agreed to publish the Local Plan Submission Version for representations in February 2018. At this point, the Council agreed that the Local Plan was “sound”. Formal representations were then invited from residents, businesses and other stakeholders to provide them with the opportunity to support or challenge the soundness or legal compliance of the Local Plan. This stage in the process followed three previous public consultations since 2015 which had informed the preparation of the Local Plan alongside a comprehensive evidence base.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.