Annual Treasury Management Report 2018/19

Approved Licensing 2 papers

Audit & Regulatory Committee approved this item on Wednesday 24 July 2019. Below is the council's own wording, with the papers it was decided on.

Item20/12

Resolved

That Council be recommended to approve the Annual Treasury Management Report 2018/19.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Audit & Regulatory Committee

Recommendation

2.1That the Annual Treasury Management Report 2018/19 is recommended to Council for approval.

Executive summary

3.1The Council is required through regulations issued under the Local Government Act 2003 to produce an annual treasury report reviewing treasury management activities for the year.

3.2The Annual Treasury Management Report for 2018/19 considers the following areas:

 The Treasury Management Strategy adopted for 2018/19 and the economic environment during the year;  The current treasury position, highlighting the Council’s borrowing and lending position at the year end;  The Council’s capital expenditure, overall borrowing need and borrowing outturn during 2018/19;  Performance measurements, which look at the returns achieved during the year by the Council on its overall investments;  The Council’s investment portfolio, which sets out for Members how and where the Council has invested its money during the year;  The interest yield for 2018/19; and  Compliance with prudential indicators, showing the outturn against those indicators formally adopted in the 2018/19 Treasury Management Strategy.

3.3The Executive Director & Chief Finance Officer confirms that borrowing was only undertaken for a capital purpose and the statutory borrowing limit (the authorised limit) was not breached.

3.4The main headlines include:

 Capital expenditure in 2018/19 totalled £7.4 million. This created a borrowing requirement of £2.6 million wholly applicable to General Fund capital expenditure.

 Total debt at 31st March 2019 amounted to £66.8 million including loans from Public Works Loan Board (PWLB) and market loans. All existing finance lease arrangements were repaid during the year.

 There was £5 million of loan maturities during the year. No new external borrowing or refinancing took place; nor was there any debt rescheduling.

 Overall borrowing costs were £86,500 underspent against the budget as internal borrowing continued. This was split between the General Fund £51,800 and HRA £34,700.

 The average daily investment during 2018/19 was £20 million invested with a total of 10 institutions, yielding £145,400 in investment income. There was a small surplus achieved against the investment income budget of £5,470.

 The average return achieved by the Council on its investment portfolio for the year was 0.73%, which compares favourably to short-term industry benchmarks.

 Year-end investments totalled £14.4 million all internally managed by the Council’s treasury management team.

 The outturn against the treasury and prudential indicators set within the Treasury Strategy 2018/19 is shown in Annex B. 4. How this report links to Corporate Priorities

4.1An effective treasury management function is critical in safeguarding and effectively managing the financial resources at the Council’s disposal. Sufficient financial resources are required to deliver and underpin the Council’s main priorities.

Options

5.1This report sets out the treasury management position for High Peak Borough Council for 2018/19. As such it is a statement of fact and there are no options to consider.

6. Implications

6.1Community Safety – (Crime and Disorder Act 1998) None

6.2Workforce None

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Annual Treasury Management Report 2018/19Report 75 KB DownloadRead as text
PDF
Annual Treasury Management Report 2018/19 /12Appendix A 208 KB Download

At this meeting

Whole meeting

Who was there

8 of 25 attended
ET
Councillor Emily ThraneChair, present
OC
Councillor Ollie CrossVice-Chair, present
JD
Councillor Jamie DouglasCommittee Member, apologies, sent representative
DK
Councillor David KerrCommittee Member, present
EL
Councillor Edith LongdenCommittee Member, present
RQ
Councillor Rachael QuinnCommittee Member, present
KS
Councillor Keith SavageCommittee Member, present
GW
Councillor George WharmbyCommittee Member, expected
TA
Councillor Tony AshtonCommittee Member, present as substitute
AB
Councillor Alan BarrowAdvisory Member, in attendance
HG
Helen GaleOfficer, expected
CH
Claire HazeldeneOfficer, expected

All 25 on the meeting page

On this subject at High Peak

Search all
  1. Annual Treasury Management Report 2018/19This decision
  2. Audit and Accounts Committee - Treasury Management UpdateNoted
  3. Audit and Accounts Committee - Treasury Management Strategy Statement (TMSS) 2026/27Approved
  4. Treasury Management UpdateDecided
  5. Treasury Management Strategy Statement (TMSS) 2026/27Approved
  6. Treasury Management UpdateNoted

More from High Peak Audit & Regulatory Committee

All decisions
MeetingDecisionOutcome
2 Jun 2026 To approve the Minutes of the previous meetingThat the minutes of the previous meeting held on 11 February 2026 be approved as a correct record. Approved Open
2 Jun 2026 High Peak Borough Council Audit Plan 2025 - 2026 (External Audit)That the report be noted. Noted Open
2 Jun 2026 Audit Progress and Sector Update Report (External Audit)That the report be noted. Noted Open
2 Jun 2026 Internal Audit Periodic Report February 2026 to May 2026That the Committee notes the progress information within the report. Decided Open
2 Jun 2026 Internal Audit CharterThat the Council’s Internal Audit Charter be approved. Approved Open