HIF programme Fairfield Roundabout: Project and Costs Review

Noted Executive 4 papers

The Executive noted this item on Thursday 8 October 2020. Below is the council's own wording, with the papers it was decided on.

Item20/80

Resolved

That the progress on delivering the Homes England funded Fairfield roundabout be noted. 2. That the revised construction costs for delivery of the roundabout as set out in Appendix 2 (Part 2 of the report) be noted. 3. That the Executive Director (Place) be authorised to proceed to producing detailed design drawings for the roundabout and related tender documentation and report back to the Executive with results of the procurement exercise and seek approval to draw down HIF funding for construction of the roundabout. 4. That the advanced payment offer from Homes England of up to £500,000 to allow the project to proceed and meet the grant funding deadline be accepted. 5. That the updated project risks and mitigation as set out in the report and Appendix 3 be noted and accepted.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to The Executive

Recommendation

2.1The Executive is recommended to:

2.1.1 Note the progress on delivering the Homes England funded Fairfield roundabout.

2.1.2 Note the revised construction costs for delivery of the roundabout as set out in Appendix 2 (Part 2 of this report).

2.1.3 Authorise the Executive Director ( Place) to proceed to producing detailed design drawings for the roundabout and related tender documentation and report back to the Executive with results of the procurement exercise and seek approval to draw down HIF funding for construction of the roundabout.

2.1.4

2.1.5 Accept the advanced payment offer from Homes England of up to £500,000 to allow the project to proceed and meet the grant funding deadline. 2.1.6 Noting and accepting the updated project risks and mitigation as set out in the report and appendix 3.

Executive summary

Background

3.1Following the submission of a Housing Infrastructure Fund (HIF) bid by the council in Dec 2017, Homes England (HE) has made a grant award to the council of £2m towards the construction of the Fairfield roundabout and link roads. Delivery of this infrastructure will unlock housing sites allocated in the Local Plan at Hogshaw and Granby Road, bringing forward 346 homes (Hogshaw 263 and Granby Road B 83). In addition, it will release and accelerate the development of a privately owned site at Waterswallows, which has the potential to provide an additional 268 homes. Housing delivery on all sites is reliant upon the construction of the roundabout and link roads. The relationship of the roundabout, link roads and housing sites are shown in appendix 1.

3.2Members received an update on this project at the end of July 2020. It was agreed that a further update report would be prepared for the Executive for its 8th October meeting.

Role of Council owned land

3.3The provision of the roundabout and link roads to the east and west provides access to the housing sites at Hogshaw, Waterswallows and Granby Road. With the exception of Granby Road B (which is council owned) the other sites are in a combination of private and council ownership. The acquisition of council land (B3 and B4 on appendix 1) is required to deliver a comprehensive residential scheme at Hogshaw of 263 homes. Disposal of this land is subject to a separate report for Member’s consideration at the October Executive.

3.4Development of the Waterswallows site requires the developer to purchase an area of council owned land (site D on appendix 1). This will be subject to a separate report to the Executive later in the year.

Design and construction of the roundabout

3.5DCC have now completed the advance design works of for the roundabout and have identified the anticipated construction costs to the back of the splitter islands. A detailed breakdown of costs is shown and summarised in appendix 2 (Part 2 of this report). 3.6 Planning approval for the roundabout was secured in July 2020 and the next stage of the process is for DCC to undertake the detailed design drawings for tender purposes. However, they cannot embark upon this next stage of works without advance funding from HE.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
/80Appendix 1 205 KB Download
PDF
/80Appendix 3 46 KB Download
PDF
/80Appendix 4 353 KB Download
PDF
HIF programme Fairfield Roundabout: Project and Costs ReviewReport 135 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 18 attended
AM
Councillor Anthony McKeownChair, present
DG
Councillor Damien GreenhalghVice-Chair, present
AB
Councillor Alan BarrowCommittee Member, present
FS
Councillor Fiona SlomanCommittee Member, present
JT
Councillor Jean ToddCommittee Member, present
AS
Andrew StokesOfficer, expected
NR
Neil RodgersOfficer, expected
SH
Sally HamptonOfficer, expected
MT
Mark TrilloOfficer, expected
LV
Linden VernonOfficer, expected
MD
Member Diary HPBCOfficer, expected
JB
Joanne BrooksOfficer, expected

All 18 on the meeting page

On this subject at High Peak

Search all
  1. HIF programme Fairfield Roundabout: Project and Costs ReviewThis decision
  2. HIF Programme and Fairfield Roundabout UpdateNoted

More from High Peak The Executive

All decisions
MeetingDecisionOutcome
27 Aug 2026 To resolve that the public and press be excluded from the meeting for the following items because there may be disclosure to them of exempt information as defined in Part 1 of Schedule 12A of the Local Government Act 1972.That the public and press be excluded from the meeting for the following items because there may be disclosure to the... Decided Open
6 Aug 2026 To approve the minutes of the previous meetingThat the minutes of the meeting held on 11 June 2026 be approved as a correct record. Approved Open
6 Aug 2026 Forward PlanThat, subject to the above, the be noted. Noted Open
6 Aug 2026 Fourth Quarter Finance, Performance and Procurement UpdateThat the Fourth Quarter 2025/26 financial, procurement and performance position detailed in Appendices A, B and C and... Noted Open
6 Aug 2026 Anti-social Behaviour, Hate and Neighbourhood Management PoliciesThat the Anti-Social Behaviour Policy, Hate Policy and Neighbourhood Management Policy, be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies