Resolved
That the Audit Service’s 2019/20 year end performance information contained within the report be noted. 2. That the opinion on the overall adequacy and effectiveness of the Council’s internal control environment be noted.
Audit & Regulatory Committee noted this item on Tuesday 24 November 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Audit Service’s 2019/20 year end performance information contained within the report be noted. 2. That the opinion on the overall adequacy and effectiveness of the Council’s internal control environment be noted.
2.1That the committee note the Audit Service’s 2019/20 year end performance information contained within this report.
2.2That the committee note the opinion on the overall adequacy and effectiveness of the Council’s internal control environment.
3.1The purpose of this report is to summarise year end performance information for financial year 2019/20. This includes a breakdown of audits undertaken and completed to date, the number and classification of recommendations made, agreed and where applicable, implemented by management, external review results, developments in the service and an assessment of the Council’s internal control environment. 3.2 The strategic audit plan covered the period 1st April 2019 to 31st March 2020 and the year end performance information referred to above is outlined in the detailed part of this report. Due to a combination of unplanned investigative work and the effects of the Covid-19 pandemic including diversion of audit resources to support the corporate response to the administration of the Governments various business grants support schemes, the Audit Plan for 2019/20 took longer than usual to complete. In addition, the follow up of audit recommendation implementation was temporarily paused until 31st May. This lack of data collection is reflected in this report but is expected to return to normal levels over the coming months.
3.3All audit recommendations have been agreed, and to date 71% of 2019/20 audit recommendations that are due have been implemented (see paragraph 3.2). Where deficiencies in internal control have been identified and not corrected, Internal Audit are satisfied that they will be resolved in an appropriate manner and they will continue to monitor such cases.
3.4Internal Audit can provide reasonable assurance that the Council’s governance arrangements including risk management and systems of internal control were operating adequately and effectively.
4. How this report links to Corporate Priorities
4.1The assurance provided by the work of Internal Audit informs the Annual Governance Statement and therefore helps to ensure our future financial resilience can be financially sustainable whilst offering value for money.
5.1There are no options to consider.
6. Implications
6.1Community Safety - (Crime and Disorder Act 1998)
None.
6.2Workforce
None.
6.3Equality and Diversity/Equality Impact Assessment
This report has been prepared in accordance with the Council's Diversity and Equality Policies. 6.4 Financial Considerations
None.
6.5Legal
None.
6.6Climate Change
None.
None.
6.8Risk Assessment
None.
ANDREW P STOKES Chief Executive
Web Links and Contact details Background Papers None John Leak Head of Audit [email protected] 7. Detail
7.1Introduction
7.1.1 The purpose of this report is to summarise year-end performance information for the Council’s Internal Audit service for the 2019/20 financial year.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
/8Appendix 1 | 70 KB | Download |
PDF |
/8Appendix 2 | 45 KB | Download |
PDF |
Internal Audit Annual ReportReport | 107 KB | DownloadRead as text |
Follow Audit & Regulatory Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jun 2026 | To approve the Minutes of the previous meetingThat the minutes of the previous meeting held on 11 February 2026 be approved as a correct record. | Approved | Open |
| 2 Jun 2026 | High Peak Borough Council Audit Plan 2025 - 2026 (External Audit)That the report be noted. | Noted | Open |
| 2 Jun 2026 | Audit Progress and Sector Update Report (External Audit)That the report be noted. | Noted | Open |
| 2 Jun 2026 | Internal Audit Periodic Report February 2026 to May 2026That the Committee notes the progress information within the report. | Decided | Open |
| 2 Jun 2026 | Internal Audit CharterThat the Council’s Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.