That the details of the consultation be noted and the proposed approach to the Council’s response as set out at paragraph 5.16 of the report be agreed. 2. That the Executive make any comments around the proposals in response to the consultation.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
2.1That the Executive note the details of the consultation and proposed approach to agree the Council’s response as set out at paragraph 5.16 of this report. 2.2 That the Executive make any comments around the proposals in response to the consultation.
Executive summary
3.1A public consultation on the A57 Link Roads scheme will run until 17th December. The consultation proposes a series of design changes from the scheme published in 2018 alongside an updated assessment of environmental impacts. 3.2 High Peak Borough Council and Derbyshire County Council submitted a joint holding objection to the 2018 consultation due to a lack of supporting information in terms of impacts such as the implications for air quality. On the basis of an initial review of the current consultation by officers, it is not clear if the Council’s previous concerns have been adequately addressed. If not, the current holding objection may need to be sustained until such time that any outstanding issues are resolved. Officers are in the process of liaising with Highways England and Derbyshire County Council to investigate these matters further. Given the circumstances and timescales, it is suggested that the Council’s response is delegated to the Executive Director for Place in consultation with the Leader of Council with regard given to feedback from Councillors.
3.3Following the consultation, Highways England expect to submit the Development Consent Order application to the Planning Inspectorate in Spring 2021. If the application is accepted for consideration, the examination itself will take around 18 months through to a decision by the Secretary of State. Subject to approval, construction is expected to start in 2023.
4. How this report links to Corporate Priorities
4.1The A57 Link Roads scheme has direct implications for the following aims of the Corporate Plan; Aim 1 Supporting our communities to create a healthier, safer, cleaner High Peak, Aim 2 Protect and create jobs by supporting economic growth, development and regeneration and Aim 3 Protect and improve the environment including responding to the climate emergency.
Neil Rodgers Executive Director (Place)
Web Links and Contact details Background Papers Consultation website: Mark James https://highwaysengland.co.uk/our-work/north-west/a57- Principal Planning Officer link-roads/ [email protected]
Planning Inspectorate Advice Note: The role of local authorities in the DCO process https://infrastructure.planninginspectorate.gov.uk/wp- content/uploads/2015/03/Advice_note_2.pdf
5. Detail
Background
5.1A public consultation on the “A57 Link Roads” scheme was published by Highways England on 5th November and will run until 17th December. The consultation follows on from previous engagement on the “Trans-Pennine Upgrade” project in 2018 which also included the proposals for the A57 Link Roads as well as upgrades to Westwood roundabout near Sheffield and associated improvements to the east of the Pennines which have since been split off into a separate project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.