The Executive - Individual Executive Decisions approved this item on Tuesday 18 May 2021. Below is the council's own wording, with the papers it was decided on.
That the submission of a proposal to the Midlands Energy Hub for the Local Authority Delivery scheme as outlined in this report (below 7.13) be approved; 2. That the entering into the legal agreement for the Council to access the ‘Dynamic Purchasing System’ managed by Midlands Energy Hub be approved; 3. That the changes to the Housing Revenue Account (HRA) Capital programme to allow the Council to contribute 33% of the costs of the project as set out in section 6.4 be approved; and 4. Authority be delegated to the Executive Director (Place) in consultation with the Leader of the Council to award the works contract(s) to deliver the energy efficiency measures ANY DECLARATION OF INTEREST None A NOTE OF ANY DISPENSATION RECEIVED None
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
Report to The Executive - Individual Executive Decisions
Recommendation
2.1That the Executive Councillors: Approve the submission of a proposal to the Midlands Energy Hub for the Green Homes Grant Local Authority Delivery scheme as outlined in this report (below 7.13) Approve entering into the legal agreement for the Council to access the ‘Dynamic Purchasing System’ managed by Midlands Energy Hub. Approve the changes to the Housing Revenue Account (HRA) Capital programme to allow the Council to contribute 33% of the costs of the project as set out in section 6.4. Delegate authority to the Executive Director (Place) in consultation with the Leader of the Council to award the works contract(s) to deliver the energy efficiency measures 3. Executive Summary
3.1The Green Homes Grant Local Authority Delivery (GHG LAD) scheme was launched in August 2020. The Government allocated £500 million to the scheme to fund energy efficiency and low carbon heating projects for low income households across England. The aim of the scheme is to reduce fuel poverty in England, support the UK’s pathway to net zero by 2050 as well as stimulating the economic recovery following COVID-19, supporting and creating green jobs.
3.2A total of around £9.4m GHG LAD funding has been allocated amongst 15 district councils across Nottinghamshire and Derbyshire. This is made up of £8.7m capital funding to retrofit at least 871 properties, and an additional £0.7m of revenue funding.
3.3High Peak Borough Council have been awarded a Capital Grant amount of £445,000 and a Capitalisation Allocation of £40,050; giving a total grant award of £485,050. The Council was required to confirm its acceptance of the grant by 15th April 2021, which has been done, and to submit a detailed proposal for decision by 24th May 2021.
3.4Council officers have considered the feasibility of the scheme within the delivery deadline of 31st December 2021 and believe that, by focusing on the Council’s own housing stock, a successful scheme could be delivered by the deadline.
3.5A capital works project has been scoped by the Assets Service focusing on delivering a mixture of energy efficiency measures to the Council’s least energy efficient homes. In total, 110 homes have SAP band ratings of E, F and G which is the main focus of the funding.
3.6The project has also been scoped in terms of what is potentially deliverable within the tight timescales and with a value for money focus delivering fuel efficiencies to some of the poorest homes in the Borough. All 110 EFG rated properties will be surveyed initially to determine the most appropriate measures to install for the maximum positive effect. As tenants’ permission and engagement into the project is required, the least disruptive measures will be prioritised such as:
Loft Insulation New or replacement cavity wall insulation Triple glazing Alternative forms of low carbon heating
3.7Each property will require a bespoke set of measures to ensure the best outcome and improvement in its SAP band rating within the £5,000 funding cap per property. The funding will require the Council to evidence the improvement in the SAP rating following the installation of the measures.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow The Executive - Individual Executive Decisions at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
Visit Peak District & Derbyshire SLAThat the signing of the High Peak Visit Peak District & Derbyshire SLA 2026 – 2029 to allocate a total of £30,000 (£1...
Alliance MyActive Wellbeing LimitedRESOLVED 1. That the appointment of [name removed] as an Independent Director of Alliance MyActive Wellbeing Ltd. be ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.