RESOLVED – That the application be APPROVED for the reasons and based on the policies contained in the report, subject to the conditions and informative in the report and the additional condition stated above. FURTHER RESOLVED - In the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal), prior to the decision being issued the Head of Development Services had delegated authority to do so in consultation with the Chairman of the Planning Applications Committee, provided that the changes did not exceed the substantive nature of the Committee’s decision. (Proposed by Councillor Ellis and seconded by Councillor Emery.)
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
«APPLICATION_NUM BER» STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL PLANNING APPLICATIONS COMMITTEE
11th November 2021
Application SMD/2021/0498 No: Location Land South East Of A521, A50 Blythe Bridge Bypass, Blythe Bridge, Staffordshire Proposal Full planning application for a haul road to provide temporary construction access to development at Blythe Vale Applicant St. Modwen Homes Agent [name removed], Turley Associates Parish/ward Forsbrook Date registered 28/07/21 If you have a question about this report please contact: Ben Haywood tel: 01538 395400 ex 4924 [email protected]
REFERRAL
The Application has been referred to committee because it is locally contentious and the Committee has considered previous applications on this site.
1. SUMMARY OF RECOMMENDATION
APPROVE subject to Conditions
2. SITE DESCRIPTION
2.1The Application Site comprises a strip of agricultural land alongside Woodlands Lane at Blythe Bridge as well as the recently constructed spine road through the new housing development at Blythe Vale. The site forms part of a wider site controlled by St Modwen, which in turn forms a significant part of a site allocated in the adopted Development Plan mixed use development and is within the settlement boundary for Blythe Bridge.
2.2The Site is located north of the A50/south east of the A521 at Blythe Bridge. The Application Site is south east of Blythe Bridge, located between this settlement and Forsbrook. To the north and primarily to the west of the Site, the land within the wider St Modwen control, forms fields used for grazing purposes.
2.3The fields comprise grass, with trees and hedgerows predominantly forming the boundaries as opposed to being isolated within the fields themselves. Established tree and hedgerow boundaries in particular form the southern and western edges of the Site.
3 DETAILS OF PROPOSAL
3.1Members may recall that a full planning application was approved on 10/05/2018 (App Ref. SMD/2017/0512). for residential development of 118 dwellings on the first phase of the allocated site at the south western corner adjacent to the A50 / A521 junction. «APPLICATION_NUM BER»
3.2Access to the site to undertake construction was originally intended to be achieved via the junction of the Phase 1 access road and the Uttoxeter Road (A521). This access would then go on to serve the residential development. Whilst planning permission had been granted, the process of the S278 Agreement with Staffordshire County Council took considerably longer to conclude.
3.3St Modwen Homes wished to commence work on site as soon as possible in order to deliver the 118 dwellings permitted under Phase 1 (App Ref. SMD/2017/0512). However, the timescales for the S278 agreement which allows for works to be undertaken within the public highway were relatively lengthy and therefore to ensure that the delivery of new homes within the site could be commenced consecutively, St Modwen sought to secure planning permission for a temporary haul road access that will allow construction traffic to enter the site until such a time as the access works subject to the S278 process were approved and completed. Access could then be achieved via the original access permitted under. SMD/2017/0512.
3.4Accordingly, temporary planning permission was granted in February 2019 for a haul road to provide temporary construction access into Phase 1 (App Ref. SMD/2017/0512) at ‘Land South East of the A521 Uttoxeter Road’, otherwise known as Blythe Vale. The permission was subject to a number of conditions including one condition which limited the consent to a temporary period ending in February 2020 with the road to be removed by 31st July 2020.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.