The information contained within the Late Representations report was noted. 2 That the application be APPROVED for the reasons and based on the policies contained in the report, subject to the conditions and informatives in the report. 3 Amendment to Condition 4 to include anti- reflective coatings on the panels as per the Late Representations report. 4 That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal) prior to the decision being issued, the Head of Development Services be given delegated authority to do so in consultation with the Chair of the Planning Applications Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision. (Proposed by Councillor Flunder and seconded by Councillor Hoptroff)
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL PLANNING APPLICATIONS COMMITTEE
26th January 2023
Application SMD/2022/0160 No: Location Upper Newton Farm Draycott Road Upper Tean Staffordshire ST10 4JN Proposal Installation of solar farm with battery storage facility and associated works. Applicant Novus Renewable Services Ltd Agent Corylus Planning & Environmental Ltd Parish/ward Draycott Date registered If you have a question about this report please contact: Jane Curley tel: 01538 395400 ex 4124 [email protected]
REFERRAL
This is a major application and locally contentious
1. SUMMARY OF RECOMMENDATION
Approve with conditions
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2.1This site extends to approximately 42 hectares. It consists of a series of pasture and arable fields bounded by hedges within which are many mature trees. The ground generally slopes from the north east to south west. It includes several ponds and a small water course which emerges from a culvert under the A50 and flows through the site eventually connecting with the River Blythe.
2.3The application site wraps around the existing Lower Newton solar farm which lies to the south. To the north/north east it is bound by the A50 and to all other sides by agricultural fields, occasional farms (Newton House Farm to the west; Blythe House Farm to the east) and access roads. On three of its four sides there are public footpaths as follows:-
Checkley FP5 set to the east side (albeit on a different alignment on Site) Checkley FP7 set to the long south side which then morphs into Draycott in the Moors FP 14 Draycott in the Moors FP 15 set to the west which follows the access track to Upper Newton Farm and would act as the construction access to the PV park.
2.4Blythe House farmhouse, a Grade II Listed building lies to the south east of the site and an overhead 132 KV electricity line crosses the site in the south 3. DESCRIPTION OF THE PROPOSAL
3.1This is a full application which seeks consent for a solar farm and battery storage. The solar panels would have an export capacity of approx. 27.7MWp and the battery store an import/export of 30MWp.
3.2The solar panels are dark in colour and tilted by 20-25 degrees to absorb as much light as possible. They have a maximum height of 3.1m above ground and positioned to face south.
3.3In addition to the solar panels the proposal includes a relatively small battery storage area. It is sited close to the northern boundary. The battery modules will be stored within container type structures with an internal monitoring and fire suppression system. These sit on concrete plinths. Palisade fencing (approx. 3m in height) is proposed around the battery storage area with planting bunding enclosing the whole compound.
3.4Adjacent to the battery storage area is the customer and DNO compound/substation which is the main point of connection between the solar farm and the National Grid. Electricity from the solar farm will be exported to the Grid via a connection to the existing overhead electricity line. The substation includes a ‘switch’ mechanism to shut the Solar Installation off from the network in the event of a fault (much like a household fuse box). The substation compound will house the switch room, transformers, capacitor banks, relay rooms and storage area, within palisade security fencing. Buildings/equipment in this area include:-
DNO substation - 6.9m by 5.6m by 4.5m Customer substation – 6.51m by 7.49m by 4.5m DNO plant/electrical infrastructure – maximum height shown at 6.3m
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.