The information contained within the Late Representations report was noted. 2. That the application be APPROVED for the reasons and based on the policies contained in the report, subject to the conditions and informatives in the report. 3. That an informative be added in relation to the lowering of the tree canopy to allow the exposure of the Flag Tower and the restoration of other heritage assets such as the Orangery to be included in the next stage of the development of the gardens. Details to be finalised via planning condition. 4. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal) prior to the decision being issued, the Head of Development Services be given delegated authority to do so in consultation with the Chair of the Planning Applications Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision. (Proposed by Councillor Davies and seconded by Councillor Emery) (Councillors Hart and Flunder abstained from the vote)
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL PLANNING APPLICATIONS COMMITTEE
16th February 2023
Application SMD/2022/0556 No: Location Alton Towers, Farley Lane, Farley, Staffordshire, ST10 4DB Proposal Removal of existing structures and construction of new building to house indoor attraction, associated ground works, infrastructure and landscaping Applicant Merlin Attractions Operations Ltd Agent Sophie Bisby - Lichfields Parish/ward Farley/Alton Date registered21st October 2021 If you have a question about this report please contact: Jo Gregory tel: 01538 395400 or e-mail [email protected]
1. REFERRAL
The application is referred to Committee as it is a major development
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2.1The application site forms part of the Alton Towers Resort accessed off Farley Lane, Alton. It is located within the open countryside and within the Alton and Farley Conservation Area. The application site is located in the south western corner of the resort. It comprises 0.9ha of land that is currently used for general storage that currently has no access for the resort’s visitors. The land is relatively level to the north but steps down to the south and gently slopes overall to the east. There are some existing storage containers occupying the site. 2.2 The application site is located within an area that has been ‘cut out’ of the Registered Park and Garden designation. Located to the north west of the site is the Grade II listed Flag Tower. Wrapping around the west and southern site boundary are remains of the Bunbury Hillfort, a Scheduled Monument. The site is south west of the Grade II* listed Alton Towers house. Wrapping around the site to the west and south is Abbey Wood, an ancient woodland designated as a Site of Biological Importance (SBI).
3. DESCRIPTION OF THE PROPOSAL
3.1This full application seeks permission for the removal of existing structures and the erection of a new building / structure to house an indoor attraction with associated ground works, infrastructure and landscaping. Public access (pedestrian only) to the new attraction will be created between the existing Alton Towers ‘Dungeons’ and ‘The World of David Walliams’ entrances. The proposal includes an entrance portal, plaza area, queue line(s) and a new portal framed building that will house the attraction. A proposed cable run is located parallel to the northern boundary of the application site and can be seen clearly on the proposed site plan as an extended part of the site boundary. 3.2 Proposed plans and elevations have been provided for the attraction building and the entrance portal. The theming, elevational treatment and internal layout of the attraction remains withheld, due to commercial sensitivity, and so the proposed plans seek permission for the position, height, scale and mass of the structures. 3.3 The main portion of the proposed building measures 71m in length and 51m in width. It has an additional attached element to the east that has a footprint of a further 40m by 9m. The main building and attached element measure 20m and 14m in height respectively. The entrance portal is located to the far east of the application site and acts as a gateway to the attraction. It will measure 7m by 1m with a height of 5m. The queue line will consist of timber raised platforms and fencing that traverse an area of existing woodland on the site.
3.4The proposed attraction building would be built into the existing topography of the site. This will require a significant amount of excavation – up to 4m to the northern end. Therefore in relation to the existing topography, the structure measures 16m to the ridge to the north and 20m to the south. The roof has a partially hipped form which further reduces the appearance of the building’s height to the south.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.