Resolved
1) That the presentation be received; 2) For the figures (split between HPBC & SMDC) on the capital programme income and expenditure to be provided to the Panel.
Resources Overview & Scrutiny Panel decided this item on Wednesday 7 February 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
1) That the presentation be received; 2) For the figures (split between HPBC & SMDC) on the capital programme income and expenditure to be provided to the Panel.
A partnership between Staffordshire Moorlands District Council, High Peak Borough Council and Norse Group Alliance Norse provides the following services in partnership with High Peak Borough Council and Staffordshire Moorlands District Council:
• Cleaning and Caretaking • Planned and Responsive building maintenance • Management and delivery of capital projects • Compliance management, technical and project staff • Disabled adaptations (N-Able)
Employing 98 staff in the local area THE TEAM Tony Taylor Operations Director
Peter Chadwick Richard Howard Jade Seddon Kim Taylor Tracey Whittle Lucy Brookes Head of Capital Head of Repairs Compliance Manager Operations Support Area Cleaning Manager Senior Occupational Projects Manager Therapist
Mark Walster Russell Donnelly Darren Beale Capital Project Operations Operations Officer Manager Manager Martin Green Cleaning Supervisor Kate Nicol John Waller Andy Horbatchewskyj Debs Ellis Capital Project Repairs Supervisor Repairs Supervisor Senior Planner Officer Cleaners Suzi Hughes Richard Warvell Sam Longbone Errol Potter Caitlin Richardson Caretakers • Rebecca Huxley Case Worker Sean O’Connor Charge Hand Planner Compliance Data Business Admin • Andrew • Lucie Nixon Electricians Capital Project Analyst Goodwin • Nigel Foxton • Barrie Knowles Officer • Peter Hilton • Elizabeth Hacking Debra McMylor • Sam Leah Christopher Electricians Lucy Newell • John Fuga • Jackie Hambleton Case Worker Planner Vacancy Ditchfield Antony Ballone Plumber • Patrick Sludds • Nick Ratcliffe • Jennifer Flavell Technical Assistant Business Admin Capital Project • Nick Knowles • Stuart McHale • Mark Riley • Sharon Robinson Emma Tyler Officer • Simon Herbert • Paul Newbury Simon Davies • Ian Beresford • Catriona Davies Case Worker • Blake Greggory William Hills • John Rhodie • Matthew Planner (Apprentice) Business Admin • Davie Law Flemming Helen Ashworth General Builder Joiners Multi-trade • Richard Glancey Case Worker (AGENCY) Technical Assistant • Nick King • David Robbins Thomas • Chris Barow • Frank Peach • Magill Downs Goldstraw Business Admin • David Waine Joiner • Gareth Stobbart Planner Vacancy • Jon Preece • Ewen Peters Roofers • Jonathan Knowles • Kayla Pogmore • Dean Allen • Roy Wilkinson • Chris Boam • Susan Watts • Tom Goley • Brian Holland Plasterer • Natalie Simcox • Callum Tune • Simon Basile • Nathan Fowler • Mandy Walmsley • Matthew Cash • Tom O’brien Caretakers • Karen Webb Property • Geoff Higginbottom • Shane Hodgson Maintenance • Martyn Land • Geoff Brassington Plasterer • Matthew • James Ravenscroft • Janice Bajalen • Mike Rodgerson • Jack Naylor • Layla Marsh Richmond • Sam Thorpe • Steve Morgan • Shelby Marsh • Tony Jones • Vera Nottage FINANCE OVERVEIW FINANCE OVERVEIW
Q3 ended with revenue slightly behind budget by £89k at £4.4m. Income 2023-24 by Quarter Delivery in Housing Capital is continuing as planned, work streams including major voids, kitchens, bathrooms, windows and heating. £5.0
Millions Q3 Housing Capital budget £1.6m, actual £1.3m. £4.5
Through this quarter, predominantly within housing which was underspent £4.0 by £15k at £1.6m. General capital works low in the quarter at £44k overall. £3.5 Original budgets for General Capital funds for both councils were £3.3m but £3.0 have been revised down substantially to £670k. Housing Capital spend has increased from £6.5m to £6.7m. £2.5
High Responsive demand continued through Q3, with revenue of £1.7m £2.0 resulting in a £500k overspend. HRA is responsible for 93% of the £1.5 overspend (£466k) – it is important to recognise that the continuing £1.0 recruitment drive and increased volumes maintains reliance on subcontractors. Q3 subcontractor spend within HRA was £567k, £230k over £0.5 budget for the quarter. £0.0 Q1 Q2 Q3
Budget Actual 2023/24 Actual Q3 2023/24 YTD (P9) 2023/24 Budget
FINANCE Income £4,458,344 £12,205,509 £18,188,058
OVERVEIW Materials -£361,675 -£664,469 -£577,085
Supplies & Services -£1,534 -£12,171 -£10,107
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Alliance Norse Annual Review of Performance: Tony Taylor, Operations Director (Presentation)Report | 658 KB | DownloadRead as text |
Follow Resources Overview & Scrutiny Panel at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 May 2026 | Minutes of the previous meetingThat the minutes of the previous meeting held on 25 March 2026, be approved as a correct record. | Approved | Open |
| 20 May 2026 | Work ProgrammeThat the work programme for 2026-2027 be approved. | Approved | Open |
| 20 May 2026 | Communications StrategyThat the report be received. | Decided | Open |
| 20 May 2026 | Devolution and LGR UpdateThat the update be received. | Decided | Open |
| 20 May 2026 | Staff RetentionThat the update be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.