Resolved
That Andy Gerrish be thanked for his presentation, which was noted; 2. That updates be provided to the Working Group on the progress of the installations and roll out of the scheme.
Climate Change Working Group (HPBC) noted this item on Tuesday 13 February 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That Andy Gerrish be thanked for his presentation, which was noted; 2. That updates be provided to the Working Group on the progress of the installations and roll out of the scheme.
Mayoral Retrofit Programme
High Peak Borough Council 2024 Why are we doing this?
§ Will deliver energy efficiency enhancements to 43 homes in the borough § Enhances energy efficiency § Supports Councils Drive to Tackle fuel poverty § Provides a platform to assess measures that can be delivered § We could eventually roll this out across the Councils wider portfolio § Needs to be a ‘Turnkey Project’ Where does it all start?
• The PAS 2035 survey • PAS 2035 retrofit assessments • PAS 2035 retrofit coordination • Energy use monitoring and evaluation • Retrofit installer services What is PAS 2035? • Defines specialist roles • All operatives to be adequately qualified • Establishes a robust process for project delivery. • Sets and measures intended outcomes • Educates customers • Conducts detailed surveys for high-quality design and end products. • Minimizes the "performance gap" in energy savings • Residents given a realistic view • It emphasises a fabric-first approach • Ensures appropriately sized and efficient low carbon heating systems Ensuring Residents are Central to the Process Significant milestone for residents Residents should feel engaged, informed and central to the development process Dedicated Retrofit Advisor Detailed customer journey plan from inception to build The Five Stages • Face-to-face engagement day for all residents • Introduction of teams and opportunity for residents to seek advice • Open forum to explain customer journey • Direct benefits of Retrofit 1) Community Engagement Day 2) Retrofit Assessments Following the engagement day, we will directly schedule 1 to 1 visits with all residents
Pre-assessment checks The benefits of the energy improvement measures Provide energy efficiency advice 3) PIBI Surveys (pre-installation building inspections)
Advisor-led communication and appointments with customers during surveys Results communication with an outline of implications for the home and options available Undertaking the works
• Pre-entry surveys before works commence • Seven, three, and one-day countdown notifications to customers
• Daily home visits during works and a 24/7 helpline • Advisor support for specific elements, e.g., clearing loft space Handover & Completion
Detailed O&M manuals with QR codes to demonstration videos In-person live demonstrations Resident feedback survey to evaluate retrofit against intended outcomes Further 1-2-1 visits post-completion at weeks 2, 6, and 12 ensure residents are happy with the works and understand how to maximise benefits Fee Schedule
Stage 1 – Initial Desktop £FOC* Assessment *assumes desk-top assessment with no surveys
required
Stage 2 - Retrofit £12k Assessment Stage 3 - Undertake £12k PAS2035 MTIP & IOE Stage 4 - Undertake £14k Measure Model Stage 5 – Undertake £12.5k PAS2035 compliant design
Total survey costs £50,500 Any Questions?
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Mayoral Combined Authority Funding for Social Housing (Andy Gerrish)Report | 24 MB | DownloadRead as text |
Follow Climate Change Working Group (HPBC) at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Feb 2025 | Minutes of the previous meetingThat the minutes of the meeting held on 14 January 2025 be approved as a correct record. | Approved | Open |
| 25 Feb 2025 | Climate Change Projects for High Peak Borough CouncilThat the report be noted. | Noted | Open |
| 25 Feb 2025 | Potential implications from LGR and devolutionThat a network map of key organisations and individuals be devised. 2. That a joint group with Staffordshire Moorland... | Decided | Open |
| 14 Jan 2025 | Minutes of the previous meetingThat the minutes of the meeting held on 26 November 2024 be approved as a correct record. | Approved | Open |
| 14 Jan 2025 | Nature Update - Gillian Wright (verbal)That the update be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.