That the Late Representations report be noted. 2. That an informative letter be sent to the applicant to express disappointment with the work carried out without the required permissions, and to make them aware of the possibility of enforcement action. 3. That the application be APPROVED for the reasons and based on the policies contained within the report. 4. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal) prior to the decision being issued, the Head of Development Services be delegated authority to do so in consultation with the Chair of the Committee, provided thar the changes do not exceed the substantive nature of the Committee’s decision. (Proposed by Councillor Roberts and seconded by Councillor Hoptroff)
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL PLANNING APPLICATIONS COMMITTEE
15th August 2024
Application SMD/2024/0094 - COLE No: Location Sylvester Farm, Land off Rownall Road, Wetley Rocks Application A claim that the part of the building that had pre-existed before walls and a shutter were installed, is lawful and the Planning Authority could not take enforcement action against that part of the building (consisting of its roof and steel stanchion supports) – the application seeks a certificate of lawfulness in those respects. Applicant John Pointon and Sons Agent Wharfe Rural Planning Parish/ward Cheddleton Date registered: 22nd February 2024 If you have a question about this report please contact: Ben Haywood 01538 395400 EXT 4924 [email protected]
REFERRAL
The application has been brought before Planning Applications Committee because the applicant is related to Cllr Oliver Pointon. The application was deferred before planning committee last April when, the day before planning committee, additional evidence was received from the applicant. Presentation of the application and the updated report and recommendation has been delayed awaiting legal advice from the Council’s solicitor. The following report and recommendation is reflective of that advice.
1. SUMMARY OF RECOMMENDATION
APPROVE
1. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
1.1The application concerns a building that currently stands as a fully enclosed portal frame shed, built without planning permission or approval. The shed has metal profile sheet side, rear and front walls with a single roller shutter door set centrally to the front. The shed roof has a total of 20 roof lights. The shed is 25m by 31m, providing 775 sq m of floor space, and adjoins a larger building to the south. Both buildings have recently been used, without planning permission, for non-agricultural storage.
1.2The application building occupies a site that is described by the applicant as Sylvesters Farm and is also known as Rownall Farm. The site is located in the Green Belt approximately 2 km north of Werrington. The site has a 160m access track that joins with Rownall Road to the east and it is surrounded by farm land. A belt of mature trees along the eastern boundary of the site screen it from Rownall Road.
2. THE APPLICATION
2.1The application is submitted under s.191 of the Town and Country Planning Act 1990 (as amended) for a certificate of lawfulness. If any person wishes to ascertain whether any operations which have been carried out are lawful then they may make an application for the purpose. For the purposes of the Act operations are lawful at any time if no enforcement action could be taken in respect of them (whether because the Planning Authority is out of time to take enforcement action, or for any other reason). In respect of the time limits for taking planning enforcement action, as set out at s.171B of the Act, an authority is out of time to take action against building operations after the end of a period of four years beginning with the date on which the operations were substantially completed (The Act has recently been amended to provide a 10 year time limit for an authority to take action against building operations. However, under transitional arrangements it is still the 4 year time limit that applies to building development that was substantially complete before 25 th April 2024) .
2.2The application relates to the part of the building that consists of its roof and steel stanchion supports - operations which had been carried out prior to the installation of walls and the roller shutter door to the front. The application claims that the Council would be out of time to take action against those operations and that they should therefore be considered lawful.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.