The Executive - Individual Executive Decisions approved this item on Friday 6 December 2024. Below is the council's own wording, with the papers it was decided on.
That the implementation of an initial rent increase from £90 p.a. (plus VAT, apart from council tenants who do not pay VAT) to £200 p.a. (plus VAT, apart from Council tenants who do not pay VAT) from 1 January 2025 be approved; 2. That the implementation of an increase of the annual rent for garage plots on Elnor Lane, Whaley Bridge SK23 7HA garage plots to bring them into line with the Council’s other garage plots be approved; and 3. That the amendment of the garage licence so that there is an annual upwards only increase in the licence fee licence with the RPI every two years that takes place on 1 April each year, be approved. ANY DECLARATION OF INTEREST RECEIVED None A NOTE OF ANY DISPENSATION GRANTED None
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
Report to The Executive - Individual Executive Decisions
Recommendation
2.1That the portfolio holder considers the content of the report and approves the changes to the charging regime, being: 2.2 Implement an initial rent increase from £90p.a. (plus VAT, apart from Council tenants who do not pay VAT) to £200p.a. (plus VAT, apart from Council tenants who do not pay VAT) from 1 January 2025. 2.3 Implement an increase of the annual rent for garage plots on Elnor Lane, Whaley Bridge, SK23 7HA garage plots to bring them in line with the Council’s other garage plots. 2.4 Amend the garage licence so that there is an annual upwards only increase in the licence fee line with the RPI every two years that takes place on 1 April each year.
Executive summary
3.1High Peak Borough Council provides licences for plots of land at garage sites it owns. Tenants can install their own approved garage structure or continue to use the installed concrete pad to park a motor vehicle on. 3.2 There are 31 garage sites across the High Peak with some having a single plot and others having up to 32 plots on them.
3.3The Council is responsible for the maintenance of the wider garage site whilst tenants are responsible for their plot and any structure that has been installed on it. 3.4 The majority of garage plots have an annual licence fee of £90p.a. (plus VAT, apart from Council tenants who do not pay VAT).
3.5Garage plots at Elnor Lane, Whaley Bridge, SK23 7HA have an annual licence fee of £50p.a. (plus VAT, apart from Council tenants who do not pay VAT). It is not known why Elnor Lane is cheaper than other sites.
3.6There is not a mechanism in place to automatically increase the licence fee and the last time it was increased was in 2006.
4. How this report links to Corporate Priorities
4.1The proposals contribute to the Borough Plan 2023-27 aim of a responsive, smart, financially resilient and forward thinking Council.
5. Options and Analysis
5.1With effect from 1 January 2025, implement an increase in the garage plot licence fee; from £90p.a. to £200p.a. (+122%). (recommended)
5.2With effect from 1 January 2025, implement a change to the garage plot licence so that there is an annual upwards only increase in the licence fee in line with the RPI that occurs on 1 April each year. (recommended)
5.3Make no change to the licence fee for garage plots. (not recommended)
6. Implications
6.1Community Safety - (Crime and Disorder Act 1998) There are no specific implications to this report.
6.2Workforce There are no specific implications to this report.
6.3Equality and Diversity/Equality Impact Assessment Underpayment of fair rates for licenses of garage plots means the maintenance, upkeep, management, and all other costs of their provision are being subsidised by non-users. 6.4 Financial Considerations The proposed changes will have a positive effect on receipts for the Council and contribute to the Council’s efficiency programme: fees and charges.
6.5Legal Additional income will allow for closer scrutiny of the application of the leases to ensure all requirements are being met.
6.6Sustainability There are no specific implications to this report as there are no changes proposed to the use of the garage plots in the short term. However, longer- term, a review of the plots should also consider their contribution to sustainability goals.
6.7Internal and External Consultation No statutory requirement to consult.
6.8Risk Assessment There are no specific implications to this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow The Executive - Individual Executive Decisions at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
Visit Peak District & Derbyshire SLAThat the signing of the High Peak Visit Peak District & Derbyshire SLA 2026 – 2029 to allocate a total of £30,000 (£1...
Alliance MyActive Wellbeing LimitedRESOLVED 1. That the appointment of [name removed] as an Independent Director of Alliance MyActive Wellbeing Ltd. be ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.