High Peak UKSPF 2022-2025 Programme Overview UKSPF Investment 2022-2025
UKSPF Total Spend £2,132,814 (Capital £889,338, and Revenue £1,243,476) REPF Total £375,453 (Capital only)
£2,508,267 funding directly invested into High Peak UKSPF Investment Priorities Communities & Place Investment Priorities • Improvements to town centres and high streets, including better accessibility • Creation of and improvements to local green spaces • Support for local arts, cultural, heritage and creative activities • Support for active travel enhancements • Funding for the development and promotion of wider campaigns which encourage people to visit • Investment in capacity building and community infrastructure • Community measures to reduce the cost of living • Funding to support relevant feasibility studies Community Infrastructure Projects £375,156 grants awarded 17 Community buildings improved
• Building renovations • Energy projects • Sports club facilities • Theatre enhancements • Community gardens • Accessibility Arts, Culture & Heritage Grant £68,775 of grants awarded to support local Events & Activities.
Supported 21 Arts, Cultural, Heritage and Creative Events / Activities
Reaching audiences of over 20,000
£50,168 UKSPF / £18,607 REPF Improvements to Local Green Spaces Over £60,000 invested in Parks & Greenspaces • Manor Park – New Climbing Frame/Equipment • Simmondley Play Area – Access Improvements • Conduit Street Play Area, Tintwistle – New Slide / Access Active Travel & Accessibility
£90,000 invested in improving travel routes and accessibility
• Temple Fields Pathway • Whaley Bridge Park footpath • Shirebrook footpath • Whaley Bridge Footpath • Whaley Bridge Incline • Edale Road, Hope • Eccles Road, Hope High Street £37,232 awarded for Shop frontage and accessibility improvements Improvement 7 High Street Shops improved Grant (2 Buxton, 2 Castleton, 2 Glossop & 1 Chapel) Enhanced Tourism Activities
Town Centre & Village Promotion – Video Show Reels
Social media posts Overall reach Jan-Jun 2024 Buxton 587,800 Chapel-en-le-Frith 106,000 Glossop 198,000 Hayfield 88,000 New Mills 1,600,000 Whaley Bridge 31,000 General High Peak 685,000 (Ladybower etc) Promotional Campaigns
Reaching over 6 million people Promotional Campaigns – Get Involved
New – Cycling and Walking leaflets highlighting walking and cycling activities, to draw visitors into nearby towns and villages. All routes accessible from nearby bus stops and train stations. Cost of Living Energy Efficiency Programme
• Supported 3777 Council properties to reduce energy costs (LED Lighting) • Estimated cost reduction of £20 – 25 per household per annum • Installed new cavity wall insulation in 24 council properties in New Mills & Tintwistle • Installed new PVS energy system (solar panels) on sheltered accommodation in Buxton • Improved 17 sheltered flats with new heating and boilers systems (Buxton) • 400 Households provided with energy efficiency advice • 250 Households provided with small energy measures Cost of Living support
4178 People Supported 4035 Households benefiting from energy efficiency measures
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
UKSPF 2022: 2025 Programme OverviewReport | 15 MB | DownloadRead as text |
Follow Economy and Growth Select Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Aug 2026 | Exclusion of Press and PublicThat the press and public be excluded from the meeting during consideration of the following item of business as ther... | Decided | Open |
| 27 Apr 2026 | Exclusion of Press and PublicThat the press and public be excluded from the meeting during consideration of the following item of business as ther... | Decided | Open |
| 19 Mar 2026 | Exclusion of Press and PublicThat the press and public be excluded from the meeting during consideration of the following item of business as ther... | Decided | Open |
| 19 Mar 2026 | To approve the minutes of the previous meetingThat the minutes of the meeting held on 26 November 2025 be approved as a correct record. | Approved | Open |
| 19 Mar 2026 | Select Committee Work ProgrammeThat, subject to the above, the Select Committee Work Programme, be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.