CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
High Peak Borough Council
The Executive - Individual Executive Decisions, Tuesday 12 August 2025 at 5.00pm

Approval of Capital Funding to support the High Peak Play Investment and Delivery Plan 2025-27

Approved Executive 2 papers

The Executive - Individual Executive Decisions approved this item on Tuesday 12 August 2025. Below is the council's own wording, with the papers it was decided on.

Item25/10

Resolved

That the capital funding required to deliver the remaining projects (2025-27) identified in the updated Play & Outdoor Sports Investment and Delivery Plan 2024-27 be approved. ANY DECLARATION OF INTEREST None A NOTE OF ANY DISPENSATION GRANTED None
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to The Executive - Individual Executive Decisions

Recommendation

2.1That the capital funding required to deliver the remaining projects (2025-27) identified in the updated Play & Outdoor Sports Investment and Delivery Plan 2024-27, is approved.

Executive summary

3.1Play and outdoor sports facilities are important assets in many of our parks and green spaces. They are key attractions that help children, young people and adults keep active, build confidence, physical literacy and social skills.

3.2In 2021, the Play & Outdoor Sports Investment and Delivery Plan was approved by the Executive, along with the High Peak Parks Strategy. The purpose of the plan is to provide a more strategic view on the quality and play value of the Council’s play facilities, identifying priority sites requiring future investment and securing the funding needed to deliver these improvements, over a three year period.

3.3An updated plan has was developed in 2024 and proposes a continued programme of refurbishment or/and replacement of selected facilities over a 3 year rolling period (see Appendix 1).

3.4Four key projects were identified for year 1 (2024/25) including Pavilion Gardens cableway replacement and mound resurfacing, Newshaw Lane climbing unit replacement, Manor Park Toddler Play Area refurbishment and Ashwood Park Sports Courts refurbishment. Approval for these projects was secured in April 2024.

3.5The first two projects were delivered in 2024 and Manor Park Toddler Play tender has just been awarded with work to start in March this year. Designs are currently being produced for Ashwood Park Sports Court.

3.6The overall cost to deliver the remaining two years of the plan is estimated to be £560,000 and this amount has been added to the recently approved medium term financial plan (MTFP). If approved, the delivery of the remaining 2 year projects will continue to be managed by the Leisure and Environmental Services team during 2025/26 and 2026/27.

3.7There is scope to offset these costs by utilising section 106 monies that have been secured from housing developments where improvements to play or outdoor sports facilities is required. Where section 106 monies have been received by the Council, budget estimates take this into account and the request for funds has been reduced accordingly.

3.8It also may be possible in some cases to secure external funding towards some of these projects and by doing so, budgets could be adjusted down accordingly. Whilst there are no guarantees external funding can be secured at this stage, and full costs are included on that basis, the Council does have an excellent track record in partnership working and securing external funding to develop improvements to open space and sports facilities.

3.9As part of the review process, Leisure and Environmental Services will be producing information to showcase the projects delivered and this will be shared with Members in the future.

4. How this report links to Corporate Priorities

4.1Aim 1 of the Borough Plan is “Supporting our communities to create a healthier and safer High Peak” a key objective of which is the “Provision of high quality leisure facilities both in formal leisure centres and out in our communities”.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Combined /10Appendix A 347 KB Download
PDF
Approval of Capital Funding to support the High Peak Play Investment and Delivery Plan 2025-27Report 251 KB DownloadRead as text

At this meeting

Whole meeting
25/10Approval of Capital Funding to support the High Peak Play Investment and Delivery Plan 2025-27This decision

Who was there

0 of 1 attended
SC
Sally CurleyOfficer, expected

On this subject at High Peak

Search all
  1. Approval of Capital Funding to support the High Peak Play Investment and Delivery Plan 2025-27This decision
  2. Approval of Capital Budget to extend Buxton CemeteryApproved
  3. Approval of Capital Funding for the High Peak Play Investment & Delivery Plan 2024Approved

More from High Peak The Executive - Individual Executive Decisions

All decisions
MeetingDecisionOutcome
18 Aug 2026 Asset of Community Value nomination - Hockerley Meadow, Whaley BridgeThat the nomination for land lying to the Northwest of Hockerley Lane, Whaley Bridge, High peak be declined for the r... Decided Open
4 Aug 2026 Request for additional capital Funds towards the Gamesley Play Improvement ProjectsThat the allocation of £100,000 from the Council’s capital funds to ensure that improvements at both play areas meet ... Approved Open
4 Aug 2026 Request for Capital Funding to Support Improvements to Manor Park CaféThat the allocation of £30,000 from the Council’s capital funds to undertake essential refurbishment and improvement ... Approved Open
4 Aug 2026 Visit Peak District & Derbyshire SLAThat the signing of the High Peak Visit Peak District & Derbyshire SLA 2026 – 2029 to allocate a total of £30,000 (£1... Approved Open
28 Jul 2026 Alliance MyActive Wellbeing LimitedRESOLVED 1. That the appointment of [name removed] as an Independent Director of Alliance MyActive Wellbeing Ltd. be ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies