Resolved
That the First Quarter 2025/26 Finance, Procurement and Performance position detailed in Appendices A, B and C and summarised as 3.3 of this covering report be noted.
AI summaryHigh Peak councillors noted the first quarter 2025/26 position, with a forecast £845,280 underspend on the General Fund and 71% of key performance indicators on track.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
That the First Quarter 2025/26 Finance, Procurement and Performance position detailed in Appendices A, B and C and summarised as 3.3 of this covering report be noted.
2.1It is recommended that the Committee note the First Quarter 2025/26 Finance, Procurement and Performance position detailed in Appendices A, B and C and summarised as 3.3 of this covering report.
3.1This report essentially summarises the Council’s financial, procurement and performance position after considering service activity throughout the first quarter of the year.
3.2Detailed analysis is provided in Appendix A (Finance), Appendix B (Procurement) and Appendix C (Performance).
3.3The position can be summarised as follows: Subject Headline Reference Finance The Finance headlines at the first update are: Appendix A Performance against Budget The General Fund provisional outturn for 2025/26 is forecast as a £845,280 underspend Efficiency Programme £122,180 in efficiencies have been identified so far in the year – there remains a further £286,380 to be found to meet the cumulative target at the end of this second year of the plan Capital Programme The General Fund Capital Programme budget for 2025/26 as revised is £21.991million. The provisional outturn forecasts a £0.720 million underspend compared to budget Treasury Management Cash investments held at the end of the first quarter totalled £14million and external borrowing was £11.1million A £61,860 shortfall on net interest income is forecast Revenue Collection at 30 June 2025 Council Tax 28.44 % (28.66% previous year) Business Rates 29.88% (29.02% previous year) Sundry debt over 60 days old £71,937 for 93 invoices (£32,030 previous year, 48 invoices)
Procurement The Procurement headlines for the First Quarter are: Appendix B 45 procurement activities were completed The Procurement forward plan includes 75 procurement activities for completion/start in 2025/26 (including HPBC and or Joint (SM/HP) activity) Procurement performance during the period 1 April to 30 June 2025 was 96% Performance The Performance headlines for the First Quarter are: Appendix C 71% of the key performance indicators were on track to be met, with 79% maintained or performing better than in the previous year The Council closed 38 complaints and received 36 comments, 10 MP comments and 6 compliments in the year
4. How this Report Links to Corporate Priorities
4.1The successful delivery of all corporate priorities is dependent upon the effective management of performance and financial resources, which is the subject of this report.
5. Options and Analysis
5.1Detailed Analysis is contained within the main body of the Report. 6. Implications
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
First Quarter Financial, Procurement and Performance Review 2025/26Report | 404 KB | DownloadRead as text |
PDF |
SM Finance Report 1st update 2025-26 APP AAppendix | 614 KB | Download |
PDF |
SM Performance Report Q1 2025-26 APP CAppendix | 874 KB | Download |
PDF |
SM Procurement Report 1st 2025-26 APP BAppendix | 340 KB | Download |
Follow Finance and Performance Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Feb 2026 | To approve the minutes of the previous meetingThat the minutes of the meeting held on 17 December 2025, be approved as a correct record. | Approved | Open |
| 4 Feb 2026 | Work ProgrammeThat the work programme be bought to the next meeting. | Decided | Open |
| 4 Feb 2026 | 2025/26 Medium Term Financial Plan & Budget SettingThat members recommended the following to Council: · Approves the General Fund Budget for 2026/27 as detailed in Appe... | Approved | Open |
| 4 Feb 2026 | Third Quarter Finance, Procurement & PerformanceThat the report be received. | Decided | Open |
| 17 Dec 2025 | To approve the minutes of the previous meetingThat the minutes of the meeting held on 15 October 2025, be approved as a correct record. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.