CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
High Peak Borough Council
Growth and Economy Committee, Wednesday 19 November 2025 at 6.00pm

Increasing the supply of affordable and supported housing

Decided Committee 1 paper

AI summaryHigh Peak's Growth and Economy Committee received a presentation on increasing affordable and supported housing, which identified a partnership with an existing Registered Provider and a Joint Venture as the most suitable delivery options.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedNo further decision or action taken
MoneyNot stated
What happens nextNot stated
Who it affectsNot stated

What was decided

The committee received the presentation on increasing the supply of affordable and supported housing.

Why

The presentation was provided by an officer and set out background, options appraisal and a recommended shortlist of delivery mechanisms. Report P3, P7, P8, P9, P10

What happens next

The committee did not decide on any next steps; no further action was agreed beyond receiving the presentation.

Options considered

  • Rejected: Delivery through traditional market approaches (disposal of sites with a Development Agreement). Not among the two options identified as most suitable Report P11, P19
  • Chosen: Partnership with an existing Registered Provider (nomination rights on identified stock). Good strategic fit and alignment with affordable housing goals Report P12, P19
  • Rejected: Financial incentives to the Private Rented Sector. Not among the two options identified as most suitable Report P13, P19
  • Rejected: Investing in existing property acquisitions via a development fund. Not among the two options identified as most suitable Report P14, P19
  • Rejected: Delivery through a Housing Revenue Account (HRA). Not among the two options identified as most suitable Report P15, P19
  • Chosen: Joint venture. Good strategic fit, simple to set up, could be implemented at pace, and provides access to additional skills Report P15, P19, P20
  • Rejected: Setting up a wholly owned company for housing development. Not among the two options identified as most suitable Report P16, P19
  • Rejected: Setting up a wholly owned company for acquisition and management. Not among the two options identified as most suitable Report P16, P19

Implications

  • Other: The presentation content refers throughout to Staffordshire Moorlands District Council (SMDC), not High Peak Borough Council, suggesting the material is drawn from a parallel review for SMDC. Report P3, P4, P5, P6, P19
  • Financial: No costs, funding sources or financial commitments were decided or set out in the papers.
  • Legal: No legal decisions were made; the presentation flagged that legal, financial and procurement considerations would need to be developed for the preferred mechanism. Report P10

Who and where

  • Households in the Leek, Cheadle and Biddulph areas (as referenced in the SMDC context of the presentation) Report P4

Plain English for the jargon

  • HRA: Housing Revenue Account, a local authority ring-fenced account for council housing
  • RP: Registered Provider, a provider of social housing registered with the social housing regulator
  • SMDC: Staffordshire Moorlands District Council
  • Local Partnerships: A public sector consultancy commissioned to review options
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item58

Resolved

That the presentation be received.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Growth and Economy Committee

Growth & Economy Committee - 19th November 2025

Supply of affordable and supported housing

Lorraine Wright Background

• SMDC transferred its Local Authority housing stock to Moorlands Housing in 2001, 3,700 properties principally located in the Leek, Cheadle and Biddulph areas.

• The council did have a joint venture partnership with a private sector partner, which developed around 400 homes – Ascent

• Local Plan has an annual target of 320 homes per annum. New method of calculation gives a figure of 482 homes per annum Scope

• The Council commissioned Local Partnerships to review its options to achieve its affordable housing objectives.

• This utilised Local Partnerships’ housing delivery vehicle toolkit to identify, at a high level, the optimum solution or solutions for the councils to achieve their housing objectives. Approach • Provide external critical challenge to assess the local context and potential solutions with the goal of creating a shortlist of options, each with a clear rationale, benefits, and risks.

• Define a means of appraising and selecting the preferred mechanism (or mechanisms) for identifying and meeting your objectives applying agreed criteria.

• Support officers to develop a plan for the practical implementation of the preferred mechanism, including any legal, financial and procurement considerations. Work Stages

• Stage 1: Data and document review Desktop research • Stage 2: Workshops • Stage 3: High level options assessment • Stage 4: Finalising the report and reporting back Stage 2 Workshop • Strategy: getting agreement on a clear, prioritised set of objectives which are understood by stakeholders and partners. • Resources and asset management: understanding the resources – land, reserves, powers, staff time – which can be leveraged into the project, whether internal, external, or through public funding streams. • Innovation and flexibility: considering how innovation can be used to achieve pace, scale, and value for money. • Potential partners: identifying the opportunities of working with other local authorities or housing associations. • Governance and risk: understanding the council’s risk appetite and understanding the preferred level of involvement in controlling the identified solution. Stage 3 - Options Approaches under consideration: • Developing through the General Fund • Opening a Housing Revenue Account • Housing Delivery Vehicle • Establishing a delivery vehicle for acquisition and management • Partnership with Registered Housing Providers; or • Establishment of a joint venture Options / Features No Option Features Option 1 Delivery through traditional • Disposal of its sites with a Development Agreement. market approaches • Offers a degree of control over the development and where land ownerships may be split between the council, developer and others.

Option 2 Partnership with an • Council agrees nomination rights on identified stock with existing RP a housing provider.

Option 3 Financial incentives to • Council provides financial incentives direct to Private private rented sector Rented Sector operators in return for identified households. • Offering long-term leases, rental guarantees, or co- investment models can attract build-to-rent developers and pension funds Options / Features No Option Features Option 4 Investing in existing • Council invests grant into an existing development fund. property acquisitions via • Private sector partner acquires and manages the development fund properties in line with agreed specification. • Typically used in larger housing markets.

Option 5 Delivery Through HRA • Re-open a HRA, • Delivers additional housing through direct delivery or acquisition. • Stock becomes Council housing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Increasing the supply of affordable and supported housingReport 319 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 26 attended
SB
Sarah BeechOfficer, expected
JG
Councillor Jim GarveyChair, present
GT
Councillor Gareth TaylorVice-Chair, present
PB
Councillor Philip BarksCommittee Member, present
AC
Councillor Andrew ChurchCommittee Member, apologies, sent representative
MD
Councillor Mark DeavilleCommittee Member, present
BE
Councillor Ben EmeryCommittee Member, present
MH
Councillor Mike HainesCommittee Member, apologies, sent representative
IH
Councillor Ian HerdmanCommittee Member, present
TH
Councillor Tony HolmesCommittee Member, present
CS
Councillor Charlie SmithCommittee Member, apologies
LW
Lorraine WrightOfficer, expected

All 26 on the meeting page

More from High Peak Growth and Economy Committee

All decisions
MeetingDecisionOutcome
8 Jul 2026 To approve the minutes from the previous meetingThat the minutes of the previous meeting held on 6 May 2026 be approved as a correct record. Approved Open
8 Jul 2026 Work ProgrammeThat the work programme for 2026-2027 be received. Decided Open
8 Jul 2026 Growth Strategy/Local Plan Steering Group UpdateThat the update be received. Decided Open
8 Jul 2026 Local Skills Needs and Provision - Rapiscan & Newcastle and Stafford Colleges Group (Leek Campus)That the presentations be received. 2. That the contact details of the speakers be circulated to all attendees by Dem... Decided Open
8 Jul 2026 Investment ProspectusThat the prospectus be received. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies