SMD/2025/0346 - Lilac Grove Farm, Folly Lane, Cheddleton, ST13 7DA
NotedPlanning1 paper
AI summaryHigh Peak Planning Applications Committee approves revised plans for seven-dwelling scheme at Lilac Grove Farm, Cheddleton, with 27 conditions covering drainage, ecology, highways and contamination.
Written from the decision and the officer reportPDF Pro
OutcomeNotedFollowing earlier permission SMD/2023/0550 dated 29 January 2024
MoneyNot stated
What happens nextDevelopment must begin within 3 yearsOf 29 January 2024, the date of permission SMD/2023/0550
Who it affectsSeven residential plots at Lilac Grove Farm. Folly Lane, Cheddleton, ST13 7DA
What was decided
The application was approved subject to 27 conditions covering plans, drainage, landscaping, ecology, highways, contamination, lighting, the orchard area, dry-stone walls, solar panels and chimneys. Report P1, P2, P3
The Head of Development Services was given delegated authority, in consultation with the Chair, to make minor wording changes to conditions or reasons before the decision is issued. Report P34
The decision was proposed by Councillor Roberts and seconded by Councillor Swindlehurst.
Why
The application was found to accord with the policies and conditions set out in the officer report, including the original permission SMD/2023/0550 dated 29 January 2024. Report P1, P2
Conditions address drainage on Plots 4 and 5, landscaping, biodiversity, tree protection, ecology, highway safety, contamination, lighting, the orchard, dry-stone walls, solar panels and chimneys. Report P6, P8, P12, P14, P16, P25, P28, P30, P31, P32, P33
What happens next
The developer must begin the development before the three-year period from 29 January 2024 expires, or the permission will lapse. Report P2
Several matters must be agreed in writing before plots are occupied, including a revised drainage strategy for Plots 4 and 5, visibility splays, accesses, footway widening, surface water drainage, bat and bird boxes, lighting, dry-stone walls, solar panels and chimneys. Report P6, P16, P17, P18, P20, P15, P28, P31, P32, P33
The Head of Development Services may finalise minor wording changes to the decision in consultation with the Chair of the Planning Applications Committee. Report P34
Options considered
Chosen: Approve with the 27 conditions in the officer report. Recommended as the planning application was approved for the reasons and policies in the report. Report P1
Rejected: Refuse the application
Implications
Legal: A new planning permission is granted, requiring development to begin within three years of 29 January 2024, otherwise the permission expires under Section 91(1) of the Town and Country Planning Act 1990. Report P2
Environment and climate: The site must deliver a Net Biodiversity Gain, retain trees, follow a Preliminary Ecological Report, install bat and bird boxes, and use approved external lighting that does not increase illuminance at adjoining properties. Report P6, P8, P12, P14, P15, P28
Risk: Unexpected contamination found during construction must be reported and remediated; imported top soil must be tested and approved before use. Report P25, P27
Environment and climate: Solar panels must be installed on all south-facing roof slopes before any dwelling is first brought into use, in the interests of energy efficiency. Report P32
Other: The area marked 'Orchard' on the site plan must remain an ecological enhancement area and cannot form part of any residential curtilage, also to safeguard the openness of the Green Belt. Report P30
Other: A dry-stone wall 1.0 metre in height must be provided before the development is first brought into use, and chimneys must be built onto all bungalow dwellings. Report P31, P33
Who and where
The applicant and developer of Lilac Grove Farm, Folly Lane, Cheddleton Report P1, P2
Future residents of the seven dwellings on Plots 1 to 7 Report P4, P11
Neighbouring residential properties, including the adjoining property to Plot 3 and Plot 6 rooflight elevations Report P11
Timeline
29 January 2024: Date of the original planning permission SMD/2023/0550, from which the three-year commencement period runs. Report P2
2025-12-11: Date of the Planning Applications Committee meeting that approved revised application SMD/2025/0346.
Before Plots 4 or 5 are developed: A revised drainage strategy must be submitted to and approved in writing by the Local Planning Authority. Report P6
Before the development is first brought into use: Landscaping, access, parking, turning, footway widening, visibility splays, bat and bird boxes, lighting, the orchard access gate, dry-stone wall, solar panels and chimneys must all be provided. Report P8, P15, P16, P17, P18, P19, P20, P21, P28, P29, P31, P32, P33
Plain English for the jargon
CEMP: Construction and Environmental Management Plan, setting out how building works will be carried out to protect the surrounding area.
Net Biodiversity Gain: A requirement that development leaves the natural environment in a measurably better state than before, through habitat creation or enhancement.
GPDO: Town and Country Planning (General Permitted Development) Order 2015, which sets out householder and other development rights that can be carried out without a fresh planning application.
Visibility splay: A triangular area at a road access kept clear of obstructions so that drivers and pedestrians can see oncoming traffic.
Curtilage: The land immediately surrounding and used with a house, normally treated as part of the property for planning purposes.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item254
Resolved
That the Late Representations Report be noted; 2. That the application be granted for the reasons and based on the policies contained within the report; 3. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal) prior to the decision being issued, the Head of Development Services be delegated authority to do so in consultation with the Chair of the Committee, provided thar the changes do not exceed the substantive nature of the Committee’s decision. (Proposed by Councillor Roberts and seconded by Councillor Swindlehurst)
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL PLANNING APPLICATIONS COMMITTEE
11th December 2025
Application SMD/2025/0346 No: Location Lilac Grove Farm, Folly Lane, Cheddleton, ST13 7DA Proposal Variation of Condition application in relation to permission SMD/2023/0550 for redevelopment of the site to provide seven dwellings. Applicant Upperdales Developers Ltd Agent Sammons Architectural Ltd Parish/ward Cheddleton Date registered 24/07/2025 If you have a question about this report please contact: Chris Johnston tel: 01538 395400 ext 4123 or [email protected]
REFERRAL
This application is referred to the Committee because the applicant is a relative of Cllr Pointon.
1. SUMMARY OF RECOMMENDATION
APPROVE, subject to conditions.
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2.1The site is within the development boundary of Cheddleton i.e. excluded from the Green Belt and lies to the south of the main part of the village, between rows of dwellings/ribbon development on the east side of Folly Lane, a country lane attached to A520 to the north-west.
2.2It comprises a redundant farm plot which used to have single-storey brick and grey render/pebble-dash clad farm buildings and a single-storey farm dwelling in the north part of the site with similar materials and a tiled pitched roof. However, the site has now been cleared of all buildings. There is an access off Folly Lane. As well as there being housing to the north and south sides which face Folly Lane, there are also dwellings which face the lane on the opposite side of the road from the site. To the rear of the site (east) lies open fields within the Green Belt. The site has also largely been cleared of trees which were mainly in front of the former farm dwelling, but there are some large front boundary trees remaining. The site and surrounding land rises slightly towards the north away from the road slightly towards the east before flattening along the fields to the east. The site has an area of 0.4 hectares.
1 3. DESCRIPTION OF THE PROPOSAL
3.1This is a variation of condition application which seeks to vary conditions 2, 11 and 14 of a full planning permission for seven dwellings approved at Planning Applications Committee in January 2024 (ref: SMD/2023/0550).
3.2Condition 2 requires the development to be carried out in accordance with the drawings listed in that condition. Condition 11 requires visibility splays at the access to be provided before the development is brought into use, in accordance with one of the approved drawings. Condition 14 requires the access, parking, servicing and turning areas to be provided before the development is brought into use, in accordance with the same drawing listed in Condition 11.
3.3The reason for the variations is so that the previously approved publicly adopted highway is substituted for a shared private drive arrangement as shown on the amended drawings accompanying this application.
3.4The only notable change on the site plan submitted with this new application is the removal of the proposed footway that existed one side of the cul-de-sac and at the rear edge of the turning head. Also, the access width opening out onto Folly Lane is slightly narrower.
3.5On 20th August 2025, details of the proposed dropped kerbs on Folly Lane were submitted, required for the entrance to the new cul-de-sac and also to two of the plots (two of the seven dwellings would be accessed via separate driveways off Folly Lane with the remaining five served by the approved new cul-de-sac) and also at the entrance to the existing field access drive to the side of the development. A drainage drawing was also submitted. These were sent in response to additional conditions recommended by the local highways authority in their first consultation response to this new application.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.