Cabinet - Legacy Plan (2026 – 2028) and Refreshed Corporate Plan (2023-2028)

Approved Committee 2 papers

AI summaryCouncil approves Legacy Plan 2026-2028 and refreshed Corporate Plan, setting out priorities until the new unitary council takes over on 1st April 2028.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedBoth run until 31st March 2028
MoneyContract consent thresholds set by governmentAssets over £100,000, capital contracts over £1,000,000
What happens nextDetailed Delivery Plan implementation beginsSix locality plans to be developed alongside unitary transition
Who it affectsNot stated

What was decided

Council approved the Legacy Plan 2026-2028 to deliver remaining priorities before reorganisation and to inform the new unitary council. Report P11

Council adopted the refreshed Corporate Plan 2023-2028, with revised Priority Actions and an updated Transformation Programme. Report P141

Several existing Priority Actions were discontinued, including the Alliance Shared Services work, the Community Leadership Scheme refresh, and Scrutiny and Constitution Reviews. Report P24

Why

The council is being reorganised. The Secretary of State invited principal councils in two-tier areas to submit proposals in February 2025, and SMDC submitted its final proposal in November 2025. Report P11

The plan is needed to ensure remaining Corporate Plan priorities are delivered up to 31st March 2028, when the council will cease to exist and a new unitary council will take over. Report P11, P12

Government has warned that major decisions now could fetter future councils, and Section 24 directions are expected after the Structural Changes Order, requiring successor council consent for large disposals and contracts. Report P13

What happens next

A Detailed Delivery Plan covering each legacy project, lead officer, expected outcome by 31st March 2028 and capital project cost implications will be implemented. Report P132, P133

LGR preparation will be delivered in six phases from planning and definition through to shadow authority, go-live and extended transformation to 1st April 2028. Report P52, P54

Town Centre and Locality Partnerships will be established for each of the six Staffordshire Moorlands localities, with member Locality Champions supporting the work. Report P116, P118

The money

  • £100,000 Threshold for written consent on land or asset disposals under expected Section 24 directions Report P13
  • £1,000,000 Threshold for written consent on capital contracts under expected Section 24 directions Report P13
  • £100,000 Threshold for written consent on non-capital contracts (whole life costs) under expected Section 24 directions Report P13

Options considered

  • Chosen: Approve the Legacy Plan. Required to focus remaining council work up to 31st March 2028 and to influence the new unitary council's design. Report P11
  • Rejected: Continue all current Corporate Plan Priority Actions unchanged. LGR means some actions are no longer appropriate or feasible in the council's remaining lifespan. Report P12, P24
  • Chosen: Refresh the Digital, Access to Services and Organisational Development Strategies in 2026/27. Needed to reflect LGR transition requirements. Report P52

Implications

  • Legal: After the Structural Changes Order, the council is expected to need written consent from the successor council for land or asset disposals over £100,000, capital contracts over £1,000,000 and non-capital contracts over £100,000. Report P13
  • Financial: Most Legacy Plan actions will be funded from existing revenue budgets, capital programme and earmarked reserves. Additional capital provision will be needed once cost certainty is reached for projects still at design stage. Report P133
  • Governance: There will be no changes to existing overview and scrutiny arrangements and no significant constitution amendments, given the council's limited remaining lifespan. Report P24
  • Staffing: Permanent appointments to senior positions have been paused, and major organisational restructures and changes to staff terms will require careful handling as LGR progresses. Report P13
  • Risk: The ability of the council to take major decisions will diminish as LGR progresses, and the disaggregation of the strategic alliance with High Peak Borough Council will be required. Report P13, P51

Who and where

  • Residents of Staffordshire Moorlands Report P11, P97
  • Local businesses and developers Report P46, P98
  • Town and parish councils across the district Report P116, P119
  • Voluntary, community and social enterprise organisations Report P118, P119
  • The nine other principal authorities in Staffordshire and Stoke-on-Trent involved in LGR preparation Report P52
  • Council staff and senior management during reorganisation Report P13, P51

Timeline

  • 5th February 2025: Government invitation to submit LGR proposals issued Report P11
  • 21st March 2025: Submission of interim LGR plan Report P11
  • 28th November 2025: Submission of final LGR proposals to government Report P11
  • 3rd February 2026 to 26th March 2026: Government consultation on LGR proposals Report P11
  • As soon after 1st April 2026 as practical: Weekly food waste collection introduced under Simpler Recycling Report P48
  • July 2026 (expected): Government decision on LGR proposals following consultation Report P11
  • September 2026 to December 2026 (expected): LGR legislation prepared and laid (Structural Changes Order) Report P11
  • 6th May 2027: Shadow unitary elections Report P11
  • 1st April 2028: New unitary councils go-live and SMDC ceases to exist Report P11, P131

Plain English for the jargon

  • LGR: Local government reorganisation, the process of restructuring councils into new unitary authorities in two-tier areas.
  • Section 24 directions: Directions the Secretary of State can issue to councils being reorganised, expected to require successor council consent for major financial decisions.
  • Structural Changes Order: The legislation that formally creates the new unitary council.
  • Simpler Recycling: New statutory arrangements for waste collection, including weekly food waste collections.
  • PSDS: Public Sector Decarbonisation Scheme, government funding for carbon reduction work on public buildings.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item60a

Resolved

That the Legacy Plan be approved. 2. That the refreshed Corporate Plan 2023-2028 be adopted.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Council (SMDC)

Legacy Plan 2026-2028 Background and Introduction Background and Introduction

Progress with Delivery of Corporate Plan 2023-27

Legacy Plan

Locality Profiles, Plans & Partnerships

Detailed Delivery Photo: Greg Walker

Plan & Outcomes

APPENDIX A Corporate Plan 2023-27 – Priority Actions by Portfolio

APPENDIX B Detailed Legacy Delivery Plan

APPENDIX C Refreshed Corporate Plan 2023-28 – Priority Actions by Portfolio

Staffordshire Moorlands District Council Legacy Plan 2026-2028 Development of a Legacy Plan Background and Introduction

Progress with In the Devolution White Paper, published in December 2024, the Alongside the development of the proposal for LGR it was agreed that Delivery of Government announced a programme of local government reorganisation there would be a programme to identify and deliver legacy priorities for Corporate Plan (LGR) for all remaining two-tier local authority areas in England. In the Council. 2023-27 February 2025, within the provisions of the Local Government and Public Involvement in Health Act 2007, the Secretary of State invited any of the The Legacy Plan will ensure that the priorities set out in the Corporate Plan 2023-27 are effectively delivered up until 31st March 2028 when Legacy Plan principal authorities in each of the two-tier areas of England to submit a proposal to form a single tier of local government. the Council will cease to exist and the new unitary council will be in place. The plan will also establish the Council’s readiness to inform and Locality Profiles, The LGR planning timelines in Staffordshire and Stoke-on-Trent are: influence the new unitary council that is established for the area. Plans & Partnerships Date Event The programme of work to develop the Legacy Plan has included: 5th February 2025 Invitation to submit proposals • Reviewing all scheduled transformation activity projects to assess and Detailed Delivery prioritise all current and planned transformation. Plan & Outcomes 21st March 2025 Submission of interim LGR plan • Appraising the desirability, viability and feasibility of proposed capital APPENDIX A 28th November 2025 Submission of final LGR proposals and revenue projects that were scheduled to be delivered / completed Corporate Plan prior to LGR 2023-27 – 3rd February 2026 to Government led consultation on LGR 26th March 2026 proposals Priority Actions by • Designing a process and schedule that enables the Council to engage Portfolio July 2026 (expected) Government decision on proposals and consult with residents, businesses, town and parish councils, third following consultation sector organisations and place-based public services, to understand September 2026 - LGR legislation prepared and laid their priorities and ‘what good looks like’ in 5-10 years’ time. APPENDIX B December 2026 (expected) (Structural Changes Order) Detailed Legacy 6th May 2027 Shadow unitary elections As part of this work, a ‘place leadership narrative’, is being developed to Delivery Plan assist discussions with other councils during the development of the new 1st April 2028 New unitary councils go-live unitary councils. This will be informed by ‘place-based profiles’ for each of the localities in the Staffordshire Moorlands. APPENDIX C Refreshed The Legacy Plan will be used to inform a refresh of the Council’s Corporate Plan The Council developed and submitted its LGR proposal in Corporate Plan and associated Priority Actions which will run through to 2023-28 November 2025. 31st March 2028. – Priority Actions by Portfolio

Background and Introduction Staffordshire Moorlands District Council Legacy Plan 2026-2028 Impact of LGR Background and Introduction

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cabinet: Legacy Plan (2026: 2028) and Refreshed Corporate Plan (2023-2028)Report 1.8 MB DownloadRead as text
PDF
Corporate Plan 2026-2028Report 1.8 MB Download

At this meeting

Whole meeting

Who was there

50 of 66 attended
AP
Councillor Adam ParkesChairman, present
LM
Councillor Linda MalyonVice-Chair, present
JA
Councillor James AberleyCommittee Member, present
CA
Councillor Charlotte AtkinsCommittee Member, present
PB
Councillor Philip BarksCommittee Member, present
GB
Councillor Gary BentleyCommittee Member, present
CB
Councillor Callum BeswickCommittee Member, present
CB
Councillor Crecy BooneCommittee Member, present
CB
Councillor Connor BradyCommittee Member, present
BC
Councillor Bill CawleyCommittee Member, present
AC
Councillor Andrew ChurchCommittee Member, present
JC
Councillor Jo CoxCommittee Member, apologies

All 66 on the meeting page

More from High Peak Council (SMDC)

All decisions
MeetingDecisionOutcome
13 May 2026 Election of Chairman of the Council.That Councillor L. Malyon be appointed as Chairman of the Council until the next Annual Meeting. Decided Open
13 May 2026 Appointment of Vice-Chairman of the Council.That Councillor L. Swindlehurst be appointed as Vice-Chairman of the Council until the next Annual Meeting. Decided Open
13 May 2026 Minutes of the previous meetingThat the Minutes of the meeting of the Council held on 25 February 2026 be approved as a correct record and signed by... Approved Open
13 May 2026 Standards Committee - Annual ReportThat the Standards Committee Annual Report be noted. Noted Open
13 May 2026 Amendment to the Members' Allowance SchemeThat the consequential amendment to the Members’ Allowance Scheme be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies