SMD/2025/0538 and SMD/2025/0539 - 2 Overton Hall Barns, Overton Road, Congleton
NotedPlanning1 paper
AI summaryStaffordshire Moorlands planning committee approved 10 solar panels on a Grade II listed barn at 2 Overton Hall Barns, Congleton, against officers' recommendation, citing carbon reduction and reversibility as public benefits outweighing less than substantial heritage harm.
Written from the decision and the officer reportPDF Pro
OutcomeNotedFull planning and listed building consent both approved
MoneyNot stated
What happens nextConditions to be finalisedHead of Development Services to agree with the Chair
Who it affectsGrade II listed barn ownerApplicant at 2 Overton Hall Barns, Congleton
What was decided
The committee approved both the full planning application SMD/2025/0538 and the listed building consent SMD/2025/0539 for 10 solar PV panels on the south-facing roof of 2 Overton Hall Barns, contrary to officers' recommendation to refuse. Report P8
Members found the harm to the Grade II listed barn would be less than substantial, visual rather than harm to historic fabric, not clearly visible from the public domain, reversible, and outweighed by the public benefit of carbon reduction. Report 6.12
An additional condition requires all external electrical converter equipment to be located at the end of the barn furthest from neighbouring properties.
Why
The committee considered the harm would be visual rather than to historic fabric, and would not be clearly visible from the public domain due to natural screening. Report P6
Members judged the proposal would assist with carbon reduction and be reversible, outweighing the less than substantial heritage harm identified by officers.
The application was brought to committee by Councillor J Garvey, who considered the location and extensive natural screening would make the installation well hidden and supported renewable energy provision in areas prone to mains disruption. Report P6
What happens next
Conditions for both approvals are to be agreed by the Head of Development Services in consultation with the Chair of the Planning Applications Committee.
The Head of Development Services has delegated authority to vary wording in consultation with the Vice-Chairman, provided any changes do not exceed the substantive nature of the committee's decision. Report P89
Options considered
Rejected: Refuse both applications (officer recommendation). Committee judged heritage harm less than substantial and outweighed by public benefits of carbon reduction and reversibility Report P8, 6.12
Chosen: Approve full planning application SMD/2025/0538 with conditions. Less than substantial harm, reversible, assists with carbon reduction
Chosen: Approve listed building consent SMD/2025/0539 with conditions. Same reasoning as planning application
Implications
Legal: Officers identified conflict with Staffordshire Moorlands Local Plan policies DC1 and DC2 and NPPF sections 12 and 16; the committee applied NPPF paragraph 215 to weigh less than substantial harm against public benefits. Report P85, P88
Climate: The committee accepted the proposal would assist with carbon reduction through renewable energy generation.
Risk: Officers raised a precedent concern, noting there are 1,259 listed buildings in the district and that allowing harmful development could lead to similar schemes coming forward. Report 7.2
Other: The solar panel installation is described as completely reversible if circumstances change, with tiles removed and set aside for re-use. Report P15
Equalities: The applicant cited being on the National Grid Priority Register for health reasons and being of retirement age, noting risks of falls during power cuts. Report P17
Who and where
The applicant at 2 Overton Hall Barns, Congleton Report P3
Neighbouring residents at 1 Overton Hall Barns, who did not object but highlighted shared driveway access rights Report P41
Owners of adjacent Grade II listed barn and Overton Hall, given heritage setting concerns Report P44, 6.10
The 1,259 listed buildings across Staffordshire Moorlands, given precedent concerns Report 7.2
Timeline
06.01.2026: Both applications registered Report P3
28.01.2026: Neighbour notification for full planning application expired Report P39
29.01.2026: Neighbour notification for listed building consent expired Report P39
05.02.2026: Biddulph Chronicle site notice expired Report P38
23.07.2026: Planning Applications Committee approved both applications contrary to officer recommendation Report P2
Plain English for the jargon
Grade II Listed: A building of special interest placed on the statutory list in England, warranting preservation efforts.
PV panels: Photovoltaic solar panels that convert sunlight into electricity.
Less than substantial harm: NPPF category for harm to the significance of a heritage asset that does not amount to substantial harm or total loss.
DC2: Staffordshire Moorlands Local Plan policy on the historic environment, requiring conservation and enhancement of heritage assets.
Green Belt: Designated land around built-up areas where development is restricted to prevent urban sprawl.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item22
Resolved
That the Late Representations report be noted; 2. That contrary to officers’ recommendation the planning application SMD /2025/0538 be APPROVED with CONDITIONS to be agreed by the Head of Development Services in consultation with the Chair; for the following reasons: - The harm to the designated heritage asset would be less than substantial. The harm would be visual rather than harm to historic fabric and would not be clearly visible from the public domain. The proposal would assist with carbon reduction and would be reversible and therefore the harm would be outweighed by public benefits. 3. That a condition be added to the decision requiring all external electrical converter equipment to be located at the end of the barn furthest from neighbouring properties; 4. That contrary to officers’ recommendation the listed building consent SMD/2025/0539 be APPROVED with CONDITIONS to be agreed by the Head of Development Services in consultation with the Chair; for the following reasons: - The harm to the designated heritage asset would be less than substantial. The harm would be visual rather than harm to historic fabric and would not be clearly visible from the public domain. The proposal would assist with carbon reduction and would be reversible and therefore the harm would be outweighed by public benefits. (Proposed by Councillor Parkes and seconded by Councillor L Swindlehurst)
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL PLANNING APPLICATIONS COMMITTEE
23rd July 2026
Application SMD/2025/0538 and SMD/2025/0539 No: Location 2 Overton Hall Barns, Overton Road, Congleton Proposal 10. No Solar PV panels fitted to south facing roof Applicant H. Judge. Agent Andrew Dukesell Parish/Ward Biddulph Date registered 06.01.2026.
If you have a question about this report please contact: [name removed] [email protected]
REFERRAL
The application is brought to committee by Councillor J. Garvey who considers that the location of the property and its extensive natural screening would make the installation well hidden and not inappropriate. Councillor Garvey notes that were this on a more modern property it would be permitted development, in line with the district council's policies and commitment to climate change mitigation. There should be support for the provision of reliable energy supply in the more rural areas, prone to mains disruption to the overhead power cables; particularly for our more vulnerable residents.
1.1A detached, two-storey barn, which has already been converted to a dwellinghouse. The dwelling sits on the southern side of the Overton Hall complex and to the south of Overton Hall which is Grade II Listed. The application barn is Listed in outs own right, separately from the main Overton Hall dwelling house. It is also a Grade II building, listed in 1987. The dwelling benefits from off-road parking and a generously sized garden.
1.2In addition to its listed status, the dwelling is located within the Green Belt and a low-risk coal development area. The site is not within any Conservation area or identified flood zone and there are no protected trees which need to be considered.
1 2. DESCRIPTION OF THE PROPOSAL
2.1The proposal is for the addition of 10 Solar PV panels to the southern facing roof slope, both Full Planning and Listed Building Consent are sought. This report considers both applications. The application is accompanied by a Design, Access and Heritage Statement which includes the following information.
The building is orientated with the ridge almost east-west, having the planes of the roof facing north – south, which is the ideal orientations for solar panels mounted on the south facing roof, maximising the available daylight exposure.
The south facing roof slopes will have 10no. Aiko Stellar 1N+ 645W N-Type ABC, 72 Cell, black Frame Dual Glass solar panels. dark matt finished panels fitted, each panel being approx. 2.278m tall and 1.134m wide, only 30mm high, fitted on an MCS approved system. The installation system would require a tile to be removed where the fixing for the frame is located and set aside for future re-use. A bracket fixed to the rafter beneath would be specially flashed to retain weather proofing and allow the solar panel framing to the secured. The installation is completely reversible if circumstances were to change. A single battery with Off Grid capable Gateway and Intelligent Charging shall be installed on the external gable and hidden from view inside the bin store wall which will allow the storage of electrical energy for peak time usage and off-peak charging. The system will also supply power to the house in the event of a mains failure.
2.2The applicants have advanced the following reasons for the requirement of the solar panels.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.