Cabinet Delegated Decisions, Thursday 6 August 2026 at 5.00pm

Leisure Facilities Capital Improvement

Approved Executive 1 paper

AI summaryHigh Peak's Leisure and Tourism Portfolio Holder approves £390,000 of capital funds for MyActive Biddulph fitness suite and reception upgrades, and Birchall Sports Pavilion cafe conversion.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCapital funds allocated to three leisure projects
Money£390,000.00Total from MTFP 2026/27 capital allocation
What happens nextProjects deliveredBefore Local Government Reorganisation in March 2028
Who it affectsLeisure centre usersBiddulph gym members, Birchall visitors, families

What was decided

The Portfolio Holder for Leisure and Tourism approved the use of capital funds from the Medium-Term Financial Plan 2026/27 for the projects at MyActive Biddulph and Birchall Sports Pavilion, Leek. Report 2.1

The £390,000.00 is split as £195,000.00 for MyActive Biddulph fitness equipment, spin bikes and fitness suite works, up to £180,000.00 for MyActive Biddulph reception and old cafe area improvements, and up to £15,000.00 for Birchall Sports Pavilion improvements. Report P28

The £390,000.00 was already included in the Capital Programme approved in February 2026 for Leisure Transformation projects across the estate. Report P26, 12.2

Why

A larger refurbishment of MyActive Biddulph will not be delivered before Local Government Reorganisation in March 2028, so a smaller, quicker project is being brought forward to improve the customer experience. Report 3.3, 8.1

The existing fitness suite equipment is end of life with frequent breakdowns, and the suite itself is described as tired and dated, putting membership retention at risk against local competitors. Report 9.1, 9.2, 3.13

Improving the reception and old cafe area is expected to encourage customers to dwell and create secondary spend, while a cafe at Birchall Sports Pavilion would serve increased footfall including around 100 new park runners and walkers each Saturday. Report 3.7, 10.1, 3.10, 11.3

What happens next

New fitness equipment has a 12 week lead time, with the fitness suite refurbishment expected to take around 3 to 4 weeks and requiring short closures of the space. Report 9.3

A business case and return on investment assessment for the Biddulph cafe and dwell space will be reviewed by the Leisure Team and Programme Board, with a further Delegated Decision required from the Portfolio Holder for Leisure before that project proceeds. Report 3.8, 3.14, 12.3

Existing fitness and indoor cycling equipment will be sold through an approved contractor, with the income used to complement the project. Report 9.3

The money

  • £390,000.00 Total capital allocation in MTFP 2026/27 for Leisure Transformation projects Report P26, 3.12, 12.2
  • £195,000.00 MyActive Biddulph new fitness equipment, spin bikes and improvements to fitness suite Report P28
  • £180,000.00 Up to, for MyActive Biddulph reception and old cafe area improvements Report P28
  • £15,000.00 Up to, for Birchall Sports Pavilion conversion of function room and kitchen to a cafe Report P28, 11.4

Options considered

  • Chosen: Approve allocation of capital funds to improve the leisure facilities at Biddulph and Birchall Sports Pavilion, Leek. Recommended option to deliver the Leisure Transformation Plan and address deteriorating equipment and customer experience. Report 5.1, 2.1
  • Rejected: Do not approve allocation of capital funds towards the improvements at Biddulph and/or Birchall Sports Pavilion, Leek. Not recommended. Report 5.2

Implications

  • Other: Community safety: an improved leisure centre and sports pavilion may help provide activities that divert people away from anti-social behaviour. Report 6.1
  • Equalities: All improvements and equipment will give open access to every customer and a range of options for those with restrictions to exercise, and a Birchall community hub would strengthen the local offer, including for people with disabilities, older adults and those needing adaptive activity. Report P25, 11.2
  • Risk: Works and equipment installation will be managed through external contract teams or MyActive maintenance staff, with risk assessments, method statements and insurance in place to protect workforce, staff and customers. Report P33
  • Financial: If the business plan for the cafe and dwell space at Biddulph does not show the required return on investment, or project costs exceed the maximum Leisure Transformation Plan budget, a further Delegated Decision must be sought from the Portfolio Holder for Leisure or the project will not proceed. Report 3.14, 12.3

Who and where

  • Existing and prospective MyActive Biddulph gym members, including those who use the spin bike fleet Report 3.5, 9.1
  • Visitors to Birchall playing fields, including around 100 new park runners and walkers plus families each Saturday Report 3.10, 11.3
  • Families with young children aged 5 and under, who could use a proposed small soft play area at MyActive Biddulph Report 3.7, 10.2
  • People with disabilities, older adults, and those requiring gentler or adaptive activity who may use the Birchall community hub Report 11.2
  • Displaced members of MyActive Leek (Brough Park LC) who have used the Birchall function room and kitchen Report 11.4

Timeline

  • 6 August 2026: Cabinet Delegated Decision approving the allocation of £390,000.00 of capital funds
  • 12 weeks lead time after approval: New fitness equipment delivery before major site work begins Report 9.3
  • Approximately 3 to 4 weeks: Expected duration of MyActive Biddulph fitness suite refurbishment, with short closures Report 9.3
  • Summer 2026: Multi-million pound refurbishment of MyActive Leek due to open Report 7.3
  • Before March 2028: Aim to bring the larger MyActive Biddulph refurbishment to RIBA 4 (Cost Certainty) before Local Government Reorganisation Report 3.2, 8.1

Plain English for the jargon

  • MTFP: Medium-Term Financial Plan, the council's multi-year budget document.
  • LGR: Local Government Reorganisation, planned for March 2028.
  • MyActive: Alliance MyActive Wellbeing Ltd, the council's controlled company that runs the leisure centres since October 2024.
  • RIBA 4: Royal Institute of British Architects Stage 4, the cost certainty stage of design.
  • ROI: Return on Investment, used to assess the business case for the cafe and dwell space.
  • Move More: Staffordshire Moorlands physical activity strategy referenced in the report.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item2

Resolved

DECISION: That the Portfolio Holder for Leisure and Tourism approved the use of capital funds that had been included in the Council’s Medium-Term Financial Plan (MTFP) for 2026/27 for allocation to the projects at MyActive Biddulph and Birchall Sports Pavilion, Leek, as detailed in the report. A RECORD OF ANY CONFLICT OF INTEREST DECLARED: None A NOTE OF ANY DISPENSATION, IF GRANTED: None
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Cabinet Delegated Decisions

Recommendation

2.1That capital funds that have been included in the Council’s Medium-Term Financial Plan (MTFP) for 2026/27 be approved for allocation to the projects at MyActive Biddulph and Birchall Sports Pavilion, Leek, as detailed in the report.

Executive summary

3.1As part of the programme to deliver the Leisure Transformation Plan, Staffordshire Moorlands District Council have been working with colleagues from Alliance MyActive Wellbeing Ltd (MyActive), to identify and bring forward improvements to our leisure facilities.

3.2MyActive Leek is nearly complete having had an extensive rebuild and refurbishment and work to complete the design phase of MyActive Cheadle is currently taking place. At MyActive Biddulph work to design a larger refurbishment project are currently being reviewed as part of the agreed Legacy Projects, with the aim and desire of the Council to bring this to RIBA 4 (Cost Certainty) before Local Government Reorganisation (LGR) in March 2028. MyActive Biddulph Fitness Suite

3.3In the meantime and as no major construction refurbishment project will be delivered prior to LGR we are looking to provide a smaller project which will be quick to deliver but have a big impact on the customer experience. The main area identified was the fitness suite (gym) and the poor condition of the inherited equipment, including the replacement of the spin bike fleet.

3.4The new equipment will include premium cardiovascular and strength training items whilst the new spin bikes will feature the latest technology to give greater participant engagement and feedback.

3.5The general feel of the fitness suite is also tired and dated, which is not providing the motivational and feel-good factor which will encourage new, and retain existing customers. Therefore, the fitness suite will also be refurbished to include removal of the plinth floor, to improve accessibility, new safety flooring and full decoration of the space.

MyActive Biddulph reception & old café area

3.6Whilst reviewing the condition and offer to the customer it has been further identified that improving the reception and revitalising the old café area would provide more opportunities for customers to dwell and socialise which would provide a good source of secondary spend revenue for the business.

3.7The improvements to these areas could include a new reception desk, improved Food & Beverage (F&B) offer, modern seating area in the old café space with the addition of a small soft play facility aimed at young children, 5 years old and under. This would create an inviting interactive space, which would attract people to dwell with friends and family and promote secondary spend within the leisure centre.

3.8The business case for this wider improvement and the evaluation on the Return on Investment (ROI) will be reviewed by the Leisure Team and those responsible for the delivery of the Leisure Transformation Plan including the Programme Board which includes representation from Financial Services.

Birchall Sports Pavilion

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Leisure Facilities Capital ImprovementReport 94 KB DownloadRead as text

At this meeting

Whole meeting
2Leisure Facilities Capital ImprovementThis decision

On this subject at High Peak

Search all
  1. Leisure Facilities Capital ImprovementThis decision
  2. Leisure Facilities Capital ImprovementApproved
  3. 2020/18 - Proposal for use of Discretionary Disabled Facilities Funding for a Community Project at the South Moorlands Leisure Centre, CheadleApproved

More from High Peak Cabinet Delegated Decisions

All decisions
MeetingDecisionOutcome
5 Aug 2026 Application to register Greenspace at Vicarage Road, Tean as an Asset of Community ValueDECISION: That the Portfolio Holder recommend to list the parcel of land/greenspace around Vicarage Road, Tean, Staff... Decided Open
28 Jul 2026 Alliance MyActive Wellbeing LimitedDECISION: 1) The appointment of [name removed] as an Independent Director of Alliance MyActive Wellbeing Ltd, be appr... Approved Open
21 Jul 2026 Proposed Dog Fouling Public Spaces Protection Order (PSPO)DECISION: 1) That commencement of statutory consultation on a proposed Dog Fouling Public Spaces Protection Order, be... Approved Open
10 Jul 2026 Application to register Royal Oak Hotel, 68 High Street, Cheadle, Stoke-on-Trent, ST10 1AN as an Asset of Community ValueDECISION: 1) That the listing of the Royal Oak Hotel, 68 High Street, Cheadle, Stoke-on-Trent, ST10 1ANbe approved; 2... Approved Open
1 Jul 2026 Endon Tennis Club FinalDECISION: That the Portfolio Holder for Leisure and Tourism approved the proposed allocation of £6,400 from the Move ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies